14th Change Order 05/25/2018MEMORANDUM TO: Board of County Commissioners From: Assistant County Administrator Date: May 24, 2018 RE: Change Orders Attached is a proposed Change Order #14 Burke Construction Group, Inc., The Redevelopment of Bernstein Park. The Contract Sum will be increased $15,127.59. The date of Substantial Completion as of the date of this Change Order is March 30, 2018. According to Ordinance No. 004 -1999 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners at least 24 hours prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. mature County Administrator of Kevin G. Wilson Print Name ONROE COUNTY /ENGINEERING/ PROJECT M ANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: The Redevelopment of Bernstein Park TO CONTRACTOR: Burke Construction Group, Inc. 10145 NW 19 St Doral FL 33172 CHANGE ORDER NO: 14 INITIATION DATE: March 26' 2018 CONTRACT DATE: April 20, 2016 The Contract is changed as follows:: The original ( Contract Sum (Guaranteed Maximum Price).. ......... _ ....... ....... $7, 921,975.00 Net change by previously authorized Change Orders....., ... ---- ...... ................$(86,614.84) The ( Contract Sum (Guaranteed Maximum Price) prior to this Change order was ... $7,835,360,16 The ( Contract Sum) (Guaranteed Maximum Price) will be ( increased ) (decreased) (unchanged) by this Change Order ...... $15,127.59 The new ( Contract Sum (Guaranteed Maximum Price) including thi Change Order is ... $7,850,487.75 The Contract Time will be (indr sd) (decreased unchanged) y 00 Days The date of Substantial Co t letio as of the date ot this� r ge Order is... March 30, 2018 Detailed description of change order and justification: A dltion of door to s on classroom closet doors. Removal of umbo limbos and bou anville that conflict with the maintenance of the ark. Addition of a concrete li at the bottom of the flood P-a - 0 - e - Is - aLth e - entry doors to the rnaintenan e z h=t4 Increased size of Irrm tion meter fr�rr� t Inch tt� Clne In ch.. 0 111IIII 1 ' • ■ s r ARCHITECT: CONTRACTOR: DIRECTOR PROJECT MANAGEMENT/ COUNTY /ASSISTANT ADMINISTRATOR f ' Roman Gatesl Kevin Wilson, Christine Hurley Date Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Concrete is needed at the bottom of the flood panels to assure a watertight seal. Crash chains and kick down door stops will prevent the doors from hitting walls and wall mounted fixtures. • Change Order was included in the original specifications. Yes ® No ❑ If Yes, explanation of increase in price: Facilities recommended that the Bouganville and the Gumbo Limbos be eliminated at the park since they will impact the field maintenance. 9 Change Order exceeds $50,000 or 5% of contract price (whichever is greater).Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Change Order Request AIA Document G710 OWNER ARCHITECT CONTRACTOR FIELD SUBCONTRACTOR PROJECT. Bernstein Park 6751 5th Street Stock Island< Florida 33040 CONTRACTOR: Burke Construction Group, Inc. 10145 N.W. 19th Street Doral, Florida 33172 M BuKKE Construction Group Inc. CHANGE ORDER NUMBER: 037 DATE: 2/12/2018 CONTRRACTOR PROJECT #: 1611 Prime Contract Change Order #037: Concrete for Flood Panels TO: Monroe County Engineering FROM: Burke Construction Group, Inc. 1100 Simonton Street 1 Concrete for Flood Panels 10145 NW 19th Street Key West, Florida 33040 TOTAL: Miami Florida 33172 DATE CREATED: 2/12/2018 CREATED BY: Armando Silveira (Burke Construction Group, Inc.) CONTRACT STATUS: Pending - In Review REVISION: 1 DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY: Group, Inc.) DUE DATE: REVIEW DATE: INVOICED DATE: PAID DATE: SCHEDULE IMPACT: EXECUTED: No CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT: $ 5,533.00 DESCRIPTION: Cut asphalt and excavate a 12 "x12 "x30' section in front of Maintenance building. Install dowels and pour 4,000 psi concrete to provide sealed surface for flood panels. ATTACHMENTS: Qongp . dpo ,I�d , POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # Title Schedule Impact Amount 037 1 Concrete for Flood Panels 5,533.00 TOTAL: $ 5,533.00 CHANGE ORDER LINE ITEMS: Burke Construction Group, Inc. page 1 of 2 Printed On: 3/19/ 2018 09:50 AM Change Order Request AIA Document G710 PCO # 037 : Concrete for Fl Pa nels # Cost Code Description Type Amount 1 03 -100 - CONCRETE / MASONRY Concrete Pump Subcontractor $ 450.00 2 03 -100 - CONCRETE / MASONRY Demo (4 men B hrs @ $32.50) Subcontractor $ 1,040.00 3 03 -100 - CONCRETE / MASONRY Compact, vapor barrier, and install rebar ( men 6 hrs @ $32.50) Subcontractor $1.040.00 4 03 -100 - CONCRETE / MASONRY Mac materials ( rebar, epoxy, drill bits, vapor barrier Subcontractor $ 250.00 5 03 -100 - CONCRETE / MASONRY Small tools ( hammer drill, plate compactor) Subcontractor $ 150.00 6 03 -100 - CONCRETE / MASONRY Concrete material 12 yards (Short Load at Monroe Concrete) Subcontractor $1,200.00 7 03 -100 - CONCRETE / MASONRY Finisher ( minimum cost) Subcontractor $ 250.00 6 03 -100 - CONCRETE / MASONRY Dumpster (concrete debris) Subcontractor $ 650.00 Subtotal: $5,030.00 Overhead: 5.00% Applies to all line item types 251.50 Profit: 5.00% Applies to all line item types 251.50 Grand Total: $5,533.00 The original (Contract Sum) $ 7,921,975.00 Net change by previously authorized Change Orders ($86,614.84) The contract sum prior to this Change Order was $ 7,835,360.16 The contract sum would be changed by this Change Order in the amount of $ 5,533.00 The new contract sum including this Change Order will be $ 7,840,893.16 The Contract Time will be (increased) (decreased) (unchanged) by The date of Substabtial Compl as of the date of this Change Order therefore is Master Permit Issue Date 8/18/2016 Contract Base Days: Added Time Above: OWNER X ARCHITECT CONTRACTOR X FIELD SUBCONTRACTOR r ♦ • r Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime, acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related items prior to final settlement of this contract. Bill Horn (Architect) 915 Eaton Street Key West Florida 33040 Monroe County Engineering 1100 Simonton Street Key West Florida 33040 Burke Construction Group, Inc. 10145 NW 19th Street Miami Florida 33172 SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE Burke Construction Group, Inc. page 2 of 2 Printed On: 3/19/ 2018 09:50 AM Change Order Request AIA Document G710 OWNER ARCHITECT CONTRACTOR FIELD SUBCONTRACTOR PROJECT: Bernstein Park 6751 5th Street Stock Island< Florida 33040 x X BU KE Construction Group Inc. CHANGE ORDER NUMBER: 038 DATE: 2/12/2018 CONTRRACTOR PROJECT #: 1611 CONTRACTOR: Burke Construction Group, Inc. 10145 N.W. 19th Street Doral, Florida 33172 Prime Contract Change Order #038: Landscape Changes by Owner TO: Monroe County Engineering FROM: Burke Construction Group, Inc. 1100 Simonton Street 10145 NW 19th Street Key West, Florida 33040 Miami Florida 33172 DATE CREATED: 2/12/2018 CREATED BY: Armando Silveira (Burke Construction Group, Inc.) CONTRACT STATUS: Pending - In Review REVISION: 2 DESIGNATED REVIEWER: Armando Silveira (Burke Construction REVIEWED BY: Group, Inc.) DUE DATE: REVIEW DATE: INVOICED DATE: PAID DATE: SCHEDULE IMPACT: EXECUTED: No CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT: $ 2,714.25 DESCRIPTION: $ 2,714.25 Remove and replace 4 Gumbo Limbo with Sable Palm. remove and dispose of 9 bougainvilleas. ATTACHMENTS: R -evi d.,E t 84,5 — f r�na Ate ti,� Earl s ABrag_I?��rg Irt� ® 17.348.[00 POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # Title Schedule Impact Amount 038 1 Landscape Changes by Owner 2,714.25 TOTAL: $ 2,714.25 CHANGE ORDER LINE ITEMS: Burke Construction Group, Inc. page 1 of 2 Printed On: 3/14/ 2018 02:49 PM Change OWNER Order Request ARCHITECT CONTRACTOR FIELD AIA Document G710 SUBCONTRACTOR X Description X Type Amount rw * us0 : Lanascape %,nanges ray owner # Cost Code Description Type Amount 1 02 -901 - LANDSCAPE & SOD OUTSIDE THE SPORTS FIELDS Remove 4 Gumbo Limbo and replace with Sable Palm Subcontractor $ 2,000,00 2 02 -901 - LANDSCAPE & SOD OUTSIDE THE SPORTS FIELDS Remove 9 bouganvileas Subcontractor $ 350.00 3 02 -901 - LANDSCAPE & SOD OUTSIDE THE SPORTS FIELDS Overhead and profit 10% Subcontractor $ 235.00 Subtotal: $2,585.00 OH & P: 5.00% Applies to all line item types 129.25 Grand Total: $2,714.26 The original (Contract Sum) $ 7,921,975.00 Net change by previously authorized Change Orders ($86,614.84) The contract sum prior to this Change Order was $ 7,835,360.16 The contract sum would be changed by this Change Order in the amount of $ 2,714.25 The new contract sum including this Change Order will be $ 7,838,074.41 The Contract Time will be (increased) (decreased) (unchanged) by The date of Substabtial Completion as of the date of this Change Order therefore is Master Permit Issue Date: 8/16/2016 Contract Base Days: Added Time Above: Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime, acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related items prior to final settlement of this contract. Bill Horn (Architect) 915 Eaton Street Key West Florida 33040 SIGNATURE DATE Burke Construction Group, Inc. Monroe County Engineering 1100 Simonton Street Key West Florida 33040 SIGNATURE DATE page 2 of 2 Burke Construction Group, Inc. 10145 NW 19th Street Miami Florida 33172 SIGNATURE DATE Printed On: 3/14/ 2018 02:49 PM A quatic Landscaping Design, Inc. 25405 SW 107th Av, Princeton, FL 33032 Phone # 305.257.2220 Fax # 305.258.1584 Name /Address Burke Construction Group, Inc. 1355 NW 97th Ave., #200 Doral, FL 33172 P: 305.468.6604 x241 F: 305.468.6654 Bernstein Park Qty Descript Rto Total 4 Remove 4 Gumbo Limbo and replace with Sabal Palm 14 -16' 500.00 2,000.00 ht. 1 Remove and dispose (9) Bougainvilleas 350.00 350.00 Gfed` - a46 - 40 - 34Z - 00 1 Irrigation: 1 Quick Coupler and 2 heads at soccer field. 660 615� 1 .. - 47260-40 1 Overhead and profit of 10% $" Sod was installed Burke w ill pay the . Total Total price includes tax. Some plant material and /or sizes may not be available as per specifications at time of planting. Finish grade to within +/- 2" by others. Unless otherwise specified, all permits, removals, relocates, tree protection, manual continued watering, maintenance, MOT, soils, berms, swales, excavation, backfilling, cutting /patching of asphalt/concrete, coring, boring, compacting, hardscapes, pots, planters, tree grates, root barriers, weed fabrics, furnishings, lighting, irrigation, water meters, backfllow & certification, wells, pumps, design /plans, Davis Beacon /Prevailing wage are excluded from this proposal. Proposal good for 30 days. By signing this proposal /contract, Signature you accept the prices and specifications as set forth herein, and you are authorizing us to do the work as specified. Warranty does not cover loss due to sustained winds of 75 mph or more, floods, frost, lightning, vandalism or theft. Plr • U ntract Estimate NO. III � _ III www.aquaticlandscape.com Change Order Request AIA Document G710 OWNER ARCHITECT CONTRACTOR FIELD SUBCONTRACTOR PROJECT: Bernstein Park 6751 5th Street Stock Island< Florida 33040 CONTRACTOR: Burke Construction Group, Inc. 10145 N.W. 19th Street Doral, Florida 33172 x x BURKE Construction Group Inc. CHANGE ORDER NUMBER: 039 DATE: 3/16/2018 CONTRRACTOR PROJECT #: 1611 POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # Prime Contract Change Order #039: Crash Chains TO: Monroe County Engineering FROM: Burke Construction Group, Inc. 1 1100 Simonton Street 10145 NW 19th Street $ 974.09 Key West, Florida 33040 Miami Florida 33172 DATE CREATED: 3/16/2018 CREATED BY: Armando Silveira (Burke Construction Group, Labor Inc.) CONTRACT STATUS: Pending - In Review REVISION: 0 DESIGNATED REVIEWER: REVIEWED BY: DUE DATE: REVIEW DATE: INVOICED DATE: PAID DATE: SCHEDULE IMPACT: EXECUTED: No CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT: $ 974.09 DESCRIPTION: Supply and install crash chains and kick down stops in closet doors 27, 28, 34, 35, & 36. ATTACHMENTS: NCO Optspn,A,-R1, 040f, POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # I Title Schedule Impact Amount 039 1 Crash Chains 1 974.09 TOTAL: $ 974.09 CHANGE ORDER LINE ITEMS: PCO # 039: Crash Chains # I Cost Code Description 46.39' Type Amount 1 08521 -DOORS/FRAMES/HARDWARE Supply and install crash chains and kick down door stops. Labor $ 1,127.70 2 08521 - DOORS /FRAMES /HARDWARE Burke credit to Monroe County Labor 1 ($200.00) Subtotal: $92730 OH & P: 5.00% Applies to all line item types 46.39' Grand Total: $974.09 Burke Construction Group, Inc. page 1 of 2 Printed On: 3/27/ 2018 03:35 PM Change Order Request AIA Document G710 OWNER ARCHITECT CONTRACTOR FIELD SUBCONTRACTOR The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The Contract Time will be (increased) (decreased) (unchanged) by The date of Substabtial Completion as of the date of this Change Order therefore is Master Permit Issue Date: Contract Base Days: rl • s r e $ 7, 921, 975.00 ($86,614.84) $ 7,835,360.16 $ 974.09 $ 7,836,334.25 Added Time Above: Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime, acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related items prior to final settlement of this contract. Bill Horn (Architect) 915 Eaton Street Key West Florida 33040 SIGNATURE DATE Monroe County Engineering 1100 Simonton Street Key West Florida 33040 SIGNATURE DATE Burke Construction Group, Inc. 10145 NW 19th Street Miami Florida 33172 SIGNATURE DATE Burke Construction Group, Inc. page 2 of 2 Printed On: 3/27/ 2018 03:35 PM Doors, d - W ♦• Request for Change Order Project Name: BERNSTEIN PARK Project Location: 6751 5th Street Stock Island, A. 33040 2000 NW 16th St, Suite B, Pompano Beach FI. 33069 Ph. 954 - 821 -9139 • Fax 954 - 491 -9833 Date: 1/25/2018 RCO #: 05 -A Contact: Armando Silvera Burke Construction Phone: 305 - 322 -7862 COST I TOTAL Below materials requested by Daniel 1- 17 -18; Add Chains & Stops to Closet Doors 27, 28, 34, 35, 36 10 CCS -1 Heavy Crash Chain Stop - Silver Zinc $52.99 $529.89 10 KDS - B Kick Down Stop (Brass Base) - 26D $15.34 $153.40 Material Cost $ 683.29 Tax $ 44.41 Installation $ 400.00 Total Change Order Amount $ 1,127.70 Please proceed with the above changes to this project - formal change order for this amount to follow Signaturej I Print Name: Date: Title: Change OWNER x Order Request ARCHITECT CONTRACTOR X FIELD AIA Document G710 UKK SUBCONTRACTOR Construction Group Inc. PROJECT: Bernstein Park CHANGE ORDER NUMBER: 040 6751 5th Street DATE: 4/6/2018 Stock Island< Florida 33040 CONTRRACTOR PROJECT #: 1611 CONTRACTOR: Burke Construction Group, Inc. 10145 N.W. 19th Street Doral, Florida 33172 Prime Contract Change Order #040: 1 inch Irrigation Meter TO: Monroe County Engineering FROM: Burke Construction Group, Inc. 1100 Simonton Street 10145 NW 19th Street Key West, Florida 33040 Miami Florida 33172 DATE CREATED: 4/06/2018 CREATED BY: Armando Silveira (Burke Construction Group, Inc,:) CONTRACT STATUS: Pending - In Review REVISION: 0 DESIGNATED REVIEWER: REVIEWED BY: DUE DATE: REVIEW DATE: INVOICED DATE: PAID DATE: SCHEDULE IMPACT: EXECUTED: No CONTRACT FOR: 1:Redevelopment of Bernstein Park TOTAL AMOUNT: $ 5,90625 DESCRIPTION: Cost difference between 5/8" meter to 1" meter thru FKAA. The site contractor will not charge to change the meter box and RPZ. ATTACHMENTS: Beru(c nPaTK_'rigatic 00121 Op0000 0,pdt POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO # Title Schedule Impact Amount 040 11 inch Irrigation Meter 5,906.25 TOTAL: $ 5,906.25 CHANGE ORDER LINE ITEMS: PCO # 040 : 1 inch Irrigation Meter # Cost Code Description Type Amount 1 02 -665 -WATER & SEWER 5 /6" irrigation meter from FKAA Subcontractor ($3,750.00) 2 02 -665 - WATER & SEWER 1" irrigation Meter from FKAA Subcontractor $ 9,375.00 Subtotal: $5,625,00 Overhead & Profit: 5.00% Applies to all line item types 261.25 Grand Total: $5,906.25 Burke Construction Group, Inc. page 1 of 2 Printed On: 4/6/ 2018 04:04 PM Change Order Request AIA Document G710 The original (Contract Sum) Net change by previously authorized Change Orders The contract sum prior to this Change Order was The contract sum would be changed by this Change Order in the amount of The new contract sum including this Change Order will be The Contract Time will be (increased) (decreased) (unchanged) by The date of Substabtial Completion as of the date of this Change Order therefore is Master Permit Issue Date: Contract Base Days: $ 7,921,975.00 ($86,614.84) $ 7,835,360.16 $ 5,906.25 $ 7,841,266.41 Added Time Above: Reservations: This proposal is based solely on the usual cost elements such as labor material and normal markups, and does not include any amount for additional changes in the sequence of work, delays, disruptions, rescheduling, lost productivity, extended or unabsorbed overhead, overtime, acceleration and or impact costs, unless speciffically stated. The right is expressly reseved to amend and make claim for any and all of these related items prior to final settlement of this contract. Bill Horn (Architect) 915 Eaton Street Key West Florida 33040 SIGNATURE DATE Burke Construction Group, Inc. OWNER ARCHITECT CONTRACTOR FIELD SUBCONTRACTOR � s a ■ Monroe County Engineering 1100 Simonton Street Key West Florida 33040 SIGNATURE DATE page 2 of 2 Burke Construction Group, Inc. 10145 NW 19th Street Miami Florida 33172 SIGNATURE DATE Printed On: 4/6/ 2018 04:04 PM Florida Keys Aqueduct Authority Service Worksheet Estimate Orly -Fees Subject to Change µ!"iris shoot is applicable on date of preparation only. Owner's flame and Mailing Address: Agent's Name and Mailing Address.:. Monroe Coun Johnnie Yost ue 1100 S6monton Street Ste 2 -216 _ Kev Went. FL 33040 vonoue- atann etMrnonroecountyfi.00v Date: 3123/201$ Reviaed 4/4, S Map No. I -045 & 1.046 Key: Stock Island Name: 'Bernstein Park Lot: Pt 1.2.3,4,& Pt5 Block: 57 Subdivision: Maloney Address or Other: 6751 5th Street Real Estate #: 00127300 000000 Water Fixture Value Charge 0 X $75.00 - $0.00 Sewer Fixture Value Charge 0 X $0.00 $0.00 Size Drop -in or Tap No. Meters: 1.0" Drop -In Fee 1 X $580.00 = $580.00 0 X $0.00 $0.00 0 x $0.00 - $0.00 Deposit - $150.00 Service Charge 1 X $20.00 $20.00 Front Footage 0 X $0.00 - $0.00 Water S.D.C. Credit Grandfather Fixtures 0 X $75.00 = $0.00 Water S.D.C. Unit Credit 0 X $5,000.00 - $0.00 Sewer S.D.C. Credit Grandfather Fixtures 0 X $0.00 $0.00 Sewer S.D.C. Unit Credit 0 X $2,700.00 _ $0.00 Plan Review Fee 0 X $50.00 - $0.00 Water S.D.C. Single Family 0 X $9,375.00 $0.00 Water S.D.C. Single Family (3 or Less) 0 X $3,188.00 - $0.00 Water S.D.C. Single Family (4 or More) 0 X $2,813.00 - $0.00 Irrigation Fee 1 X $9,375.00 g $9,375.00 Sewer S.D.C. Single Family Unit 0 X $0.00 $0.00 Fees Waived Due to Government Service - - $150.00 TOTAL[ $9,975.00 lfater_Only) Front Footage Due: No - Existing Account on Property of the Line: 8 & V Installed: *FIXTURE WORKSHEET* I Description: Number of Units: 1 11 Date: 3/23/2018, Revised 4/4/2018 Map No.: 1 -045 & 1 -046 Key: Stock Island Name: Bernstein Park Lot: Pt 1,2,34,& Pt5 Block: 57 Subdivision: Maloney Address or Other: 6751 5th Street Weight of Sub -Total Description of Fixtures Numberof X Fixture Units Fixture Value Fixtures Water Sewer Water Sewer Bathtub /Spa X 8 mm Shower Head (Shower Only) X 1.5 Water Closet: Tank Type X 1.6 = Lavatory: 1/2" X 4 Water Closet: Flush Valve X 1.6 3 Compartment Sink X 1.5 Wash Sink X 1.5 Washing Machine: 1/2" X 6 Janitors Sink X 1.5 = Hose Bib 3/4" X 12 Drinking Fountain (public) X 2 Urinal: Pedestal Flush Valve X 35 Irrigation System with 16 zones 80 gpm of highest zone TOTAL FIXTURE VALUES: 0 Backflow Prevention f r Comm r i T e pev810 mOnt; AGKFLOW Backlow Assembly: Conditions On canal or waterfront with normal fixtures Hazard: high BackflowAssembl: RPX Additional Notes: Contractor to Instali new 1" meter box and RPZ to serve Irrigation systern as part of eAst'ing utility peww t. FKAA to drop In 1 °" ureter once permit is closed by Engineering. No sewer us6ng fixtures allowed. Hold work order until notified by Engineering, RPZ reaur red. *GRANDFATHERED FIXTURES WORKSHEET* Description: Number of Units: 1 Date: 3123)2018, Revised 41412018 Map No.: 1 -045 & 1 -046 Key: Stock Island Name: Bernstein Park Lot: Pt 1,2,3,4,& Pt5 Block: 57 Amount: Subdivision: Maloney Address or Other: 6751 5th Street Number of Weight of Sub -Total Description of Fixtures X Fixture Units Fixture Value Fixtures Water Sewer Water Sewer Bathtub /Spa X 8 Shower Head (Shower Only) X 2.5 Water Closet: Tank Type X 3 m Lavatory: 318" X 2 Water Closet: Flush Valve X 35 Kitchen Sink: 1/2" X 3 Ice Machine (Commercial) - X 2 Washing Machine: 1/2" X 6 Service /Bar Sink 1/2" X 3 =— Hose Bib 1/2" X 6 Urinal: Wall or Stand X 12 TOTAL FIXTURE VALUES: 0 Additional Notes: Contractor to Install new I" meter box and RPZ to serve irrigation system as part of existing utility permit. FKAA to drop M I" meter once permit is c0osed by Engineering. No sewer using fixtures a&lowed. Fold work order until notified by Engineering. RPZ required. Prepared by: Kim Judge Date: 3/23/2018 Pre- TreatmentRev: Reviewed by: Marnie Walterson Date: 4/4/2018 Date: Date Paid: