2nd Change Order 06/13/2018ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Demolition of Old, and Installation of New
Transfer Station Offices
TO CONTRACTOR:
Pedro Falcon Contractors, Inc.
31160 Avenue C
Big Pine Key, FL 33043-4516
The Contract is changed as follows:
CHANGE ORDER NO: 2
INITIATION DATE: June 5, 2018
CONTRACT DATE: May 17, 2017
The original (Contract Sum) (Guaranteed Maximum Price) ........................................... $1,105,410.00
Net change by previously authorized Change Orders ...................................................$ 0.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ........
.....
$1,105,410.00
The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased)
(unchanged) by this Change Order.......$ 0.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is.....-$1,105,410.00
The Contract Time will be (increased) (decreased) (unchanged) by ........................... e...... 179 days
The date of Substantial Completion as of the date of this Change Order is ..................... October 22, 2018
Detailed description of change order and justification:
This change Order is 0.00/ of the original contract Drice. __ s
ARCHITECT:
CONTRACTOR:
DIRECTOR OF PROJECT MANAGEMENT
Pike Ar ).1 _ Date
E
COUNTY/ASSISANT ADMINISTRATOR —
m Gas d Date
evin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Hurricane Irma caused delays in the demolition and installation of new
offices at all three Monroe County Transfer Stations.
e Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
e Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
e Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
e Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Revised
05 June 2018
Project: Demolition and installation of New Transfer Offices
Change Order Request No: PCO - 003
Description: No Cost Tfine Extension
Item I — Extend Contract Substantial Coatetion (roin 26 ALH1,2018 to 15 No venjAff-
2018 Due to Hurrictine Irma Dela
get Amount of
Additional Time Requested for Change:
,-AH--ealendar Days for Substantial Completion.
Respectfully Submitted,
Ken Bygler
Project Manager