02nd Change Order 06/18/2018Jacobs Key West International Airport 04/18
Monroe County
Drainage Improvements Phase 2 & 3
Project No. GAKAP149
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 2
Drainage Improvements
Phase 2 & 3 INITIATED ON: April 13, 2018
CONTRACT: GAKAP149
TO (Contractor): Charley Toppino & Sons
129 Toppino Industrial Drive
Key West, FL 33040
CONTRACT DATE: November 22, 2016
You are hereby authorized and directed to make the following change(s) in this Contract:
Due to unforeseen site conditions, additional nice was needed to connect the proposed pumped injection well to the
existing drainage system.
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be unchanged
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by ........................................
$ 1,655,480.85
$ NIA
$ 14,960.00
$ 1,670,440.85
NIA
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims.
RECOMMENDED:
Jacobs Engineering
4a'm ' '
Ery ate
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
1l r
By Date
AGREED TO:
Charley Toppino & Sons
r
I
By Date
AUTHORIZED:
Monroe County
1100 Simonton Street
Key West, FL 33040
,aJ16 ml
BY c 1ng oun Mims or IJate
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Due to unforeseen site conditions, additional pipe was needed to
connect the proposed pumped injection well to the existing drainage system.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No ®'
Explain:
qw
PRICE QUOTATION
Attention: Lass Ennis DATE: 4/11/18
Jacobs Engineering Inc.
3750 NW 87th Ave #750
Miami, FL 33178
ITEMIZED QUANTITIES
Location: KW IA Apron Project, Key West International Airport 1
Scope: EYW Drainage Improvements Phase 2 & 3 ESI No.1 REV
Item
Description
Quantity
Units
Cost per Unit
Line Item Cost
Notes
1
Install 24" Drainage Pipe
68.0
LF
$ 220.00
$ 14,960.00
'Includes connections
"as per ESI No.1 REV
Subtotal
$ 14,960.00
2
Performance/Payment Bonds $20.00/Thousand
1.0
LS
$
$
3
Mobilization/Demobilization
1.0
LS
$
$
4
General Conditions Permits, Management, Pedestrian Safte , etc..
1.0
LS
$
$
Total:
S 14,960.00
Notes:
Net 30 payment terms, proposal valid for 90 days.
Inclusions:
Exclusions:
Prepared by:
W.4. r%
Estimator
Charley Toppino & Sons, Inc.
Sheetl
1 of 1
q
Date:
4/11/18
1