02nd Change Order 06/18/2018Jacobs Key West International Airport 04/18 Monroe County Drainage Improvements Phase 2 & 3 Project No. GAKAP149 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 2 Drainage Improvements Phase 2 & 3 INITIATED ON: April 13, 2018 CONTRACT: GAKAP149 TO (Contractor): Charley Toppino & Sons 129 Toppino Industrial Drive Key West, FL 33040 CONTRACT DATE: November 22, 2016 You are hereby authorized and directed to make the following change(s) in this Contract: Due to unforeseen site conditions, additional nice was needed to connect the proposed pumped injection well to the existing drainage system. The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be unchanged by this Change Order ...................... The new Contract Sum including this Change Order willbe ............................................... The Contract Time will be increased by ........................................ $ 1,655,480.85 $ NIA $ 14,960.00 $ 1,670,440.85 NIA Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: Jacobs Engineering 4a'm ' ' Ery ate Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 1l r By Date AGREED TO: Charley Toppino & Sons r I By Date AUTHORIZED: Monroe County 1100 Simonton Street Key West, FL 33040 ,aJ16 ml BY c 1ng oun Mims or IJate Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Due to unforeseen site conditions, additional pipe was needed to connect the proposed pumped injection well to the existing drainage system. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No ®' Explain: qw PRICE QUOTATION Attention: Lass Ennis DATE: 4/11/18 Jacobs Engineering Inc. 3750 NW 87th Ave #750 Miami, FL 33178 ITEMIZED QUANTITIES Location: KW IA Apron Project, Key West International Airport 1 Scope: EYW Drainage Improvements Phase 2 & 3 ESI No.1 REV Item Description Quantity Units Cost per Unit Line Item Cost Notes 1 Install 24" Drainage Pipe 68.0 LF $ 220.00 $ 14,960.00 'Includes connections "as per ESI No.1 REV Subtotal $ 14,960.00 2 Performance/Payment Bonds $20.00/Thousand 1.0 LS $ $ 3 Mobilization/Demobilization 1.0 LS $ $ 4 General Conditions Permits, Management, Pedestrian Safte , etc.. 1.0 LS $ $ Total: S 14,960.00 Notes: Net 30 payment terms, proposal valid for 90 days. Inclusions: Exclusions: Prepared by: W.4. r% Estimator Charley Toppino & Sons, Inc. Sheetl 1 of 1 q Date: 4/11/18 1