2nd Change Order 06/29/2018Key West International Airport 06/18 Monroe County NIP Pilot Project Project No. GAKAP152 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 2 NIP Pilot Project INITIATED ON: June 11 2018 CONTRACT: GAKAP152 TO (Contractor): Kenmar General Contracting, LLC 1209 Truman Avenue, Unit #1 Key West, FL 33040 CONTRACT DATE: September 27, 2017 You are hereby authorized and directed to make the following change(s) in this Contract: The Original Contract Sum is changed per the attached documents The Schedule of Values is being reduced by the removal of three (3) properties creating a deductive value of $220,203.59. The modified Contract Sum is being increased by the approval of twelve (12) Contract Modifications for an additive value of $34,443.00. The net change will be the reduction in the contract sum of -$185,760.59 The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be reduced by this Change Order ...................... The new Contract Sum including this Change Order willbe ................ ............................... The Contract Time will be increased by ......... ............................... $ 2.012,570.39 $ 0 $ - 185,760.59 $ 1,826,809.80 ZERO (0) CALENDAR DAYS Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims, that pertain solely to the specific work covered by this change order. RECOMMENDED: THC, Inc. ��q- 6-1L-_L y Date Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 By Date AGREED TO: Kenmar General Contracting, LLC. By bate AUTHORIZED: Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Adjustment in Original Contract Sum reducing the value by $220,203.59 for the removal of three (3) properties, from the contract. Kenmar requested increase in Contract Modified Sum by $34,443.00 for twelve (12) approved mofifications. Net change to the Original Contract Sum of - $185,760.59. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ® No If Yes, explanation as to why it is not subject for a calling for bids: The change order is the result of a combined deductive change order and an additive change order. The results area deductive change order which reduces the Original Contract sum by greater than 5 %. • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: