3rd Change Order 06/20/2018Key West International Airport 06/18
Monroe County
NIP Pilot Project
Project No. GAKAP152
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 3
NIP Pilot Project
INITIATED ON: June 11, 2018
CONTRACT: GAKAP 152
TO (Contractor): Kenmar General Contracting, LLC
1209 Truman Avenue, Unit #1
Key West, FL 33040
CONTRACT DATE: September 27, 2017
You are hereby authorized and directed to make the following change(s) in this Contract:
Kenmar is r uestin an increase to the Contract Sum from the Bid Additive fund to address their additional cost in
labor and materials to perform the abatement of asbestos containin materials in the en closets of units B204 and
B 1.08, as described in the Scope of Work per the Contract Documents
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be increased
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by ........................................
$ 2,012 ' 570.39
$ - 185,760.59
$ 2,825.00
$ 1,829,634.80
ZERO (0) CALENDAR DAYS
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims, that pertain solely to the specific work covered by
this change order.
RECOMMENDED:
THC, Inc.
By Date
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
Wk-
By _ Date
AGREED TO:
Kenmar General Contracting, LLC.
By ate
AUTHORIZED:
Monroe County
1100 Simonton Street
Key West, FL 33040
E
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Kenmar General Contracting, LLC is requesting the increase to the
Original Contract Sum by $2,825.00 from the Bid Additive fund for the abatement of
asbestos containing materials in two properties.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: