3rd Change Order 06/20/2018Key West International Airport 06/18 Monroe County NIP Pilot Project Project No. GAKAP152 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 3 NIP Pilot Project INITIATED ON: June 11, 2018 CONTRACT: GAKAP 152 TO (Contractor): Kenmar General Contracting, LLC 1209 Truman Avenue, Unit #1 Key West, FL 33040 CONTRACT DATE: September 27, 2017 You are hereby authorized and directed to make the following change(s) in this Contract: Kenmar is r uestin an increase to the Contract Sum from the Bid Additive fund to address their additional cost in labor and materials to perform the abatement of asbestos containin materials in the en closets of units B204 and B 1.08, as described in the Scope of Work per the Contract Documents The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be increased by this Change Order ...................... The new Contract Sum including this Change Order willbe ............................................... The Contract Time will be increased by ........................................ $ 2,012 ' 570.39 $ - 185,760.59 $ 2,825.00 $ 1,829,634.80 ZERO (0) CALENDAR DAYS Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims, that pertain solely to the specific work covered by this change order. RECOMMENDED: THC, Inc. By Date Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 Wk- By _ Date AGREED TO: Kenmar General Contracting, LLC. By ate AUTHORIZED: Monroe County 1100 Simonton Street Key West, FL 33040 E Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Kenmar General Contracting, LLC is requesting the increase to the Original Contract Sum by $2,825.00 from the Bid Additive fund for the abatement of asbestos containing materials in two properties. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: