03rd Change Order 07/05/2018Jacobs Key West International Airport 06/18 Monroe County Drainage Improvements Phase 2 & 3 Project No. GAKAP149 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 3 Drainage Improvements Phase 2 & 3 INITIATED ON: June 22, 2018 CONTRACT: GAKAP149 TO (Contractor): Charley Toppino & Sons 129 Toppino Industrial Drive Key West, FL 33040 CONTRACT DATE: November 22, 2016 You are hereby authorized and directed to make the following change(s) in this Contract: Due to Hurricane Irma and the increased flood elevation the platform elevation was increased to 10 feet The time extension is for the procurement of the platforms. The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be unchanged by this Change Order ...................... The new Contract Sum including this Change Order willbe ............................................... The Contract Time will be increased by ....................................... $ 1,655,480.85 $ 14,960.00 $ 14,520.00 $ 1,684,960.85 32 Days Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: AGREED TO: Jacobs Engineering y l: ate Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 VJ- Ak�— � b. // F By ate Charley Toppino & Sons Alll• 10- Date AUTHORIZED: Monroe County 1100 Simonton Street KeNett, FL 33 y Dat Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Due to Hurricane Irma and the increased flood elevation, the platform elevation was increased to 10'. The time extension is for the procurement of the platforms. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: CHARLEY TOPPINO & SONS, INC. CHARLEY TOPPINO & SONS, INC. Change Order Request P.O. BOX 787 Number: 3 KEY WEST, FL 33041 Phone: 305 296-5606 Fax: 305 296-5189 PROJECT: KWIA Drainage Improvements TO: Lasa Ennis Jacobs Engineering Jacksonville, FL DESCRIPTION OF CHANGE: Additional height on aluminum platforms ITEM DESCRIPTION DATE: 6/22/2018 PROJECT #: 1621 COST CODE: AMOUNT 1 Labor (for both platforms) $10,000.00 2 Additional detailings (for both platforms) $1,100.00 3 1 114" Sch 80 Pipe (for both platforms) $320.00 4 10" Channel (for both platforms) $1,200.00 5 5" Pipe (for both platforms) $500.00 6 4x4x3/8 Angle (for both platforms) $400.00 7 10 Steps @ 100 Each (for both platforms) $1,000.00 8 Time Extension $0.00 TOTAL: $14,520.00 1. It is understood and agreed that the acceptance for the Charge Order by this subcontractor constitutes an accord and satisfaction will the terms of In Change Order, 2. The amount of are Change Order covers all Bred and indlred coats. 3. It is further understood and agreed that all temp and conditions of said Contract, as it may therefore have been modified shell remain the same. 4. Acceptance of the Change Order acimowledges acceptance of all previous Change Order work by the Subcontractor and Contractor as well as any ad ustments to the Subcontractor amount and modificatans as reflected above. S. This Change Order includes ell items necessary for a complete installation including, but not necessarily lies led to habor, supervision, materials, transportation, incidentals, taxes, and any other items necessary for a complete installation. The Original Contract Sum was................................................................... $1,655,480.55 Net Change by Previously Authorized Requests & Changes ................................. $ 14,960.00 $1,670,440.55 The Contract Sum Prior to This Change Order was ........................................... $ 14,520.00 The Contract Sum Will be Increased / Decreased ............................................... $1,684,960.55 The New Contract Sum Including This Change Order ........................................ The Contract Time Will / Will Not be Changed (Days) ....................................... 32 Days ACCEPTED: CHARLEY TOPPINO & SONS, INC. By: Jordan Mannix-Lachner By: Project Admin Printed Name & Title Datf 6/22/2018 Date: JACOBS ENGINEERING Printed Name & Title Charley Toppino & Sons 129 Toppino Industrial Dr Key West Ft 305-296-5606 Lasa Ennis Jacobs Engineering 245 Riverside Avenue, Suite 300 Jacksonville, Florida 32202 United States June 22, 2018 Dear Lasa, Charley Toppino & Sons is requesting a four -week extension for the Key West International Airport Drainage Improvement Project Phase 2 & 3. We would like to request a completion date of July 31, four weeks after the approved date of June 29. We are requesting this extension as a result of the procurement time for the pumps required for the project. Thank you, *vlv� in 10 (w�— Jordan Mannix-Lachner Project Administrator Charley Toppino & Sons E r E L C H I 91