03rd Change Order 07/05/2018Jacobs Key West International Airport 06/18
Monroe County
Drainage Improvements Phase 2 & 3
Project No. GAKAP149
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 3
Drainage Improvements
Phase 2 & 3 INITIATED ON: June 22, 2018
CONTRACT: GAKAP149
TO (Contractor): Charley Toppino & Sons
129 Toppino Industrial Drive
Key West, FL 33040
CONTRACT DATE: November 22, 2016
You are hereby authorized and directed to make the following change(s) in this Contract:
Due to Hurricane Irma and the increased flood elevation the platform elevation was increased to 10 feet The time
extension is for the procurement of the platforms.
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be unchanged
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by .......................................
$ 1,655,480.85
$ 14,960.00
$ 14,520.00
$ 1,684,960.85
32 Days
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims.
RECOMMENDED: AGREED TO:
Jacobs Engineering
y l: ate
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
VJ- Ak�— � b. // F
By ate
Charley Toppino & Sons
Alll•
10- Date
AUTHORIZED:
Monroe County
1100 Simonton Street
KeNett, FL 33
y Dat
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Due to Hurricane Irma and the increased flood elevation, the platform
elevation was increased to 10'. The time extension is for the procurement of the platforms.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
CHARLEY TOPPINO & SONS, INC.
CHARLEY TOPPINO & SONS, INC. Change Order Request
P.O. BOX 787 Number: 3
KEY WEST, FL 33041 Phone: 305 296-5606
Fax: 305 296-5189
PROJECT: KWIA Drainage Improvements
TO: Lasa Ennis
Jacobs Engineering
Jacksonville, FL
DESCRIPTION OF CHANGE:
Additional height on aluminum platforms
ITEM DESCRIPTION
DATE: 6/22/2018
PROJECT #: 1621
COST CODE:
AMOUNT
1 Labor (for both platforms)
$10,000.00
2 Additional detailings (for both platforms)
$1,100.00
3 1 114" Sch 80 Pipe (for both platforms)
$320.00
4 10" Channel (for both platforms)
$1,200.00
5 5" Pipe (for both platforms)
$500.00
6 4x4x3/8 Angle (for both platforms)
$400.00
7 10 Steps @ 100 Each (for both platforms)
$1,000.00
8 Time Extension
$0.00
TOTAL:
$14,520.00
1. It is understood and agreed that the acceptance for the Charge Order by this subcontractor constitutes an accord and satisfaction will the terms of In Change Order,
2. The amount of are Change Order covers all Bred and indlred coats.
3. It is further understood and agreed that all temp and conditions of said Contract, as it may therefore have been modified shell remain the same.
4. Acceptance of the Change Order acimowledges acceptance of all previous Change Order work by the Subcontractor and Contractor as well as any ad ustments to the Subcontractor amount and modificatans as reflected above.
S. This Change Order includes ell items necessary for a complete installation including, but not necessarily lies led to habor, supervision, materials, transportation, incidentals, taxes, and any other items necessary for a complete installation.
The Original Contract Sum was................................................................... $1,655,480.55
Net Change by Previously Authorized Requests & Changes ................................. $ 14,960.00
$1,670,440.55
The Contract Sum Prior to This Change Order was ...........................................
$ 14,520.00
The Contract Sum Will be Increased / Decreased ...............................................
$1,684,960.55
The New Contract Sum Including This Change Order ........................................
The Contract Time Will / Will Not be Changed (Days) ....................................... 32 Days
ACCEPTED:
CHARLEY TOPPINO & SONS, INC.
By: Jordan Mannix-Lachner By:
Project Admin
Printed Name & Title
Datf 6/22/2018 Date:
JACOBS ENGINEERING
Printed Name & Title
Charley Toppino & Sons
129 Toppino Industrial Dr
Key West Ft
305-296-5606
Lasa Ennis
Jacobs Engineering
245 Riverside Avenue, Suite 300
Jacksonville, Florida 32202
United States
June 22, 2018
Dear Lasa,
Charley Toppino & Sons is requesting a four -week extension for the Key West
International Airport Drainage Improvement Project Phase 2 & 3. We would like to request
a completion date of July 31, four weeks after the approved date of June 29. We are
requesting this extension as a result of the procurement time for the pumps required for
the project.