HomeMy WebLinkAbout04th Change Order 07/05/2018Jacobs Key West International Airport 06A 8
Monroe County
Drainage Improvements Phase 2 & 3
Project No. GAKAP149
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 4
Drainage Improvements
Phase 2 & 3 INITIATED ON: June 28. 2018
CONTRACT: GAKAP149
TO (Contractor): Charley Toppino & Sons
129 Toppino Industrial Drive
Key West, FL 33040
CONTRACT DATE: November 22, 2016
You are hereby authorized and directed to make the following change(s) in this Contract:
The proposed power pole location was modified in the field by Keys Energy. The new location increased the electrical
conduit, fittings, conductors and pull box quantity from the pumped injection well.
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be unchanged
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by ..................................
S 1,655,480.85
S 29,480.00
S 14 754.20
S 1,699,715.05
0 Days
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims.
RECOMMENDED:
Jacobs Engineering
jr99
y D to
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
..
By Date
AGREED TO:
Charley Toppino & Sons
O.-ilni 1 2,01 el
Date
AUTHORIZED:
Monroe County
l 100 Simonton Street
Key West, FL 33040
--9 �� -1-15[15
By Date
0
E
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The proposed power pole location was modified in the field by Keys
Energy. The new location increased the electrical conduit, fittings, conductors and pull box
quantity from the pumped injection well.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
CHARLEY TOPINO & SONS, INC.
CHARLEY TOPPINO & SONS, INC. Change Order Request
P.O. BOX 787 Number: 4
KEY WEST, FL 33041 Phone: 305 296-5606
Fax: 305 296-5189
PROJECT: KWIA Drainage Improvements DATE: 6/27/2018
TO: Lasa Ennis
Jacobs Engineering
Jacksonville, FL
DESCRIPTION OF CHANGE:
Change in distance to power pole
ITEM DESCRIPTION
I Conduit & Fittings (Parallel Runs)
2 CU Conductors (250 MCM & #4G)
3 Electric Pull Box
4 Labor
5 Tax
6 Overhead & Profit
7
8
QuanritN Unit Price
too 5.56/LF
680 5.85/LF
1 Each
PROJECT #: 1621
COST CODE:
ANIOUNT
$779.47
$3,982.75
$1,500.00
$6,650.61
$469.67
$1,371.70
TOTAL: $14,754.20
1,. It is understood and agreed that the acceptance for this Change Order by this Subcontractor constitutes an accord and satisfaction vdth the terms of this Change Order
2, The amount of the Change Order covers all direct and indirect costs.
3. It is further understood and agreed that all terms and conditions of said Contract, as it may therefore have been modified shall remain the same
4. Acceptance of the Change Order acknowledges acceptance of all previous Change Order work by the Subcontractor and Contractor as well as any adjustments to the Subcontractor amount and modifications as reflected above
5. This Change Order includes all items necessary for a complete installation including, but not necessarily limited to labor, supervisionmaterials, transportation, incidentals, taxes, and any other items necessary for a complete installation
The Original Contract Sum was .....................................................
Net Change by Previously Authorized Requests & Changes ..................
The Contract Sum Prior to This Change Order was.
The Contract Sum Will be Increased / Decreased............
The New Contract Sum Including This Change Order
The Contract Time Will / Will Not be Changed (Days)..
ACCEPTED:
CHARLEY TOPPINO & SONS, INC.
By: Jordan Mannix-Lachner
Project Admin
Printed Name & Title
By:
Datt 6/22/2018 Date:
$1,655,480.55
$ 29,480.00
$1,684,960.55
$ 14,754.20
$1,699,714.75
Printed Name & Title
0