15th Change Order 07/13/2018PROJECT TITLE: The Redevelopment of Bernstein Park TO CONTRACTOR: Burke Construction Group, Inc. 10145 NW 19" Street Doral, FL 33172 The Contract is changed as follows: CHANGE ORDER NO: 15 INITIATION DATE: July 11, 2018 CONTRACT DATE: April 20, 2016 The original (Contract Sum) (Guaranteed Maximum Price)............................................$7,921,975.00 Net change by previously authorized Change Orders ............................................. .... ..$ (71,487.25) The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ........ .....$7,850,487.75 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order.......$ 0.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is......$7,850,487.75 The Contract Time will be (increased) (decreased) (unchanged) by .................................. 97 Days The date of Substantial Completion as of the date of this Change Order is ......................... .July 6, 2018 Detailed description of change order and justification: Extend substantial corn -letion by 97 days, from March 8(1 2 18 to Jul 8 2018 �IL1e to q wrrar�ty issues caused by Hurricane Irmma in_ September 2017. This change Order is 0.00% of the oriainal contract price. ARCHITECT: CONTRACTOR: DIRECTOR PROJECT MANAGEMENT: COUNTY/DEPUTY ADMINISTRATOR: Devi Lion Christine Hurley III III' *� • 1- ! • • 1A. Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Additional time was needed to work with insurance company on damages and warranty issues caused by Hurricane Irma. e Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: e Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes [] No If Yes, explanation as to why it is not subject for a calling for bids: Project architect approves the change order. Yes ® No ❑ If no, explanation of why: e Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: