#6th Change Order 07/26/2018Jacobs Key West International Airport 07/ 18
Monroe County
Strengthen/Rehabilitate Commercial Apron
Project No. GAKAP148
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 6
Stren- hen/Rehabilitate
Commercial Aron INITIATED ON: July 9, 2018
CONTRACT: GAKAP 148
TO (Contractor): ABC Construction, Inc.
7215 NW Th Street
Miami, Florida 33126
CONTRACT DATE: November 22, 2016
You are hereby authorized and directed to make the following change(s) in this Contract:
Due to weather conditions, construction activities and taroduction were delayed and reduced. There were 25 work days
cancelled due to weather, resultine in 37 calendar days (See Attached). This chanee order is for time only. ADDroval
of this change order does not preclude ABC from seeking costs limited solely to their subcontractors associated with
this time extension for consideration_ by the County and the FAA.
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be unchanged
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by ........................................
S 9,250,000.00
S 41,583.30
S TBD
S 9,291,583.30
37 DAYS
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims.
RECOMMENDED:
Jacobs Engineering
*By
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
By
s
4.
l
AGREED TO:
Monroe County
1100 Simonton Street
Key, ,' L 330401
n
y qDe*
1,q 1'94 4, com 0 S,'�'0'4
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
Due to weather conditions, construction activities and production were delayed and reduced.
• Change Order was included in the original specifications. Yes ❑ No ® '
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
ABC CONSTRUCTION, INC.
7215 NW 7th Street Phone: 305-663-0322
MIAMI, FL. 33126 Fax: 305-267-2403
07/09/2018
Jacobs
200 W. Forsyth Street,Suite 1520
Jacksonville, FL 32202
Phone: 904,636.5432 Fax:904.636.5433
Attn: Christopher W. Bowker, Jr., P.E.
Project: Keys Strengthen Rehabilitate Commercial Apron Contract/PO #: GAKAP145
Re: Time Extension Project completion Job #: GAKAP145
Dear Christopher W. Bowker, Jr., P.E.:
This letter serves as ABC Constrution Inc.'s "ABC" is requesting a Time Extension of 25 1/2 days of delay
for the Key West Project based on below breakdown:
2/27/18, Rain starts up and stop. Rained out. 1 day
3/11/18, Rain and lightning have us removed from the AOA. 1 day SUNDAY SF1 F T . 2 DAYS = 3 CAI.... DAY
3/12/18, Lost one shift of grading due to rain on and off all day and flooding. Had to dewater area. 1
day
4/13-4/15/18, EYW notifies us that an approaching cold front will impact the airport. They tell us to call
it off, A lot of rain. - 3 days
5/2/18, Rain light and then heavy had to cancel shift. 1 day
5/3/18, Daytime rain has us dewatering.1 day TFiURSDAY S1...i1FT+ 2 DAYS = 3 CAIL,AY
5/6/18, Hard, local daytime rain has us dewatering. It rains again at night. 1 day
5/8/18, Rained out.1 day
5/13/18, Rained out. 1 day l AY SHIF-r DAYS = CAL AY
5/14/18, Rained so hard today it was over the top of the catch basins, Dewatering. Work canceled
again.1 day THURSDAY SHIFT+ 2 DAYS = 3 CAL DAY
5/17/18, Early rain causes delay to pour. Lost half the shift. 1 day
5/21/18, Rained out. 1 day
5/25/18 thru 5/28/18, Memorial Day weekend, rain every day. 5/29/18 rain forces the cancellation of
daytime striping.4 days
5/29/18, Rained out. 1 day
6/6/18, Rained out. 1 day SL)INDAY S...HFT4 2 DAYS=UA "
6/10/18, EYW denies us access to the AOA for lightning in the area. Lost half a shift. %: day.
6/12/18, Daytime rain goes over the top of the catch basins again. We had to dewater. 1 day
6/18/18, More daytime rain stops us from working in the hole, water is over the top of the CB's
Eventually we are able to dewater. 1 day Page t of 2
6/20/18, More daytime rain has us me dewatering, 1 day
6/28/18, More daytime rain and dewatering. 1 day. THURSDAY I MF° 2 DAYS = 3 CAL DAYS
Consequently, ABC is requesting a Time Extension from February 27, 2018 to June 30, 2018.
Page 2 of 2