14th Change Order 08/18/2018MEMORANDUM TO; Board of County Commissioners From. Assistant County Administrator Date: August 9, 2018 RE: Change Orders Attached is a proposed Change Order #14 Sea Tech of the Florida Keys, Inc., HVAC System Improvements Stock Island Jail Complex. The Contract Sum will be increased $45,585.00. The date of Substantial Completion as of the date of this Change Order is August 18, 2018. According to Ordinance No. 004 -1999 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners at least 24 hours prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. we__r of ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 14 HVAC System Improvements Stock Island Jail Complex INITIATION DATE: June 27, 2018 TO CONTRACTOR: Sea Tech of the Florida Keys, Inc 131 Palomino Horse Trail Big Pine Key, Florida 33043 The Contract is changed as follows:: CONTRACT DATE: June 15, 2016 Contractors Change Order Request: 14 The original (Contract Sum) (Guaranteed Maximum Price) .............. ..................$1,538,612.00 Net change by previously authorized Change Orders ....... ............................... $ 47,288.14 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was..$1,585,900.14 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (Unchanged) by this Change Order.. $ 45,585.00 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order $1,631,485.14 The Contract Time will be (increased) ( decreased) (unchanged) by .....................60 Days The date of Substantial Completion as of the date of this Change Order is......... August 18, 2018 Detailed description of change order and justification: Contractor needs a 60 -day time extension to have subcontractor install one control valves in the condensate lines at the towers and one equalizing line between the towers. None of this was outlined on the drawings or in the specifications. Once this is completed, the contractor will be able to complete the Test and Balance, Substantial completion increase of 60 days from July 19, 2018 to September 17, 2018 This change Order is 2.96% of the on inal contract price. M I - r :. ARCHITECT: CONTRACTOR: PROJECT MANAGEMENT: Date COUNTY /ASSISTANT ADMINISTR Date Date Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The two control valves in the condensate lines at the towers and one equalizing line between the towers were omitted from the original drawings and specifications. An additional 30 days is needed. e Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater).Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ® No ❑ Explain: Errors and omissions will be resolved with Architect at the end of the project. aTe a h P% inc. OF THE FLORIDA KEYS DESIGN BUILD CONTRACTORS June 26, 2018 Monroe County Engineering Attn: Dan Bensley 1100 Simonton Street, 2 -216 Key West, FL 33040 Re: MCSO HVAC Upgrades Subject: Request for Change Order 409 — Add Equalizing Line We hereby propose to furnish materials, equipment, perform the labor and supervision necessary to Install an equalizing Line between Cooling Towers CT1 & CT2 at the Monroe County Detention Center and revise sequence of operation with the condenser water pumps. 9'- Add Equalizing Line Install Equalizing Line between CT1 & CT2 and revise sequence of operation with the 9.1 condenser water pumps 1 Is @ 42774.4 $42,774.43 9.2 Superintendent 16 hr @ 40 $640.00 Subtotal $43,414.43 Overhead & Profit 5% $7,170.72 All material is guaranteed to be as specified and the above work to be performed in accordance with the manufacturer's specifications and completed in a substantial workmanlike manner for the sum of: Forty Five Thousand, Five Hundred Eighty Five Dollars ........ .....................$45,585.00 *This additional work will add 60 calendar days to the contract duration. Payment in full upon completion. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents, or delays beyond our control. Owner to carry fire, tornado and other necessary insurance upon above work. Workers Compensation and General Liability insurance on above work will be taken out by SEA TECH, INC. Note - This proposal may be withdrawn by us if not accepted within 30 days. ACCEPTANCE OF PROPOSAL The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work specified. Payment will be made as outlined above. Signature Page 1 of I 2 0 1111 T.E.M. E " pwomma nvironmental & Mechameal Services, Corp. Re: Stock Island Jail HVAC Improvements 6/20/2017 Add equalizing line to Cooling Towers at the Detention Center CO - 1505 -03 Our Price for the HVAC work on the above referenced project is ---- --- - -- $42,774.43 Fourty Thousand Seven Hundred Seventy-Four Dollars Forty- Three cents Our price includes the following: Install equalizing line between cooling towers CT-1 & CT-2 and revise sequence of operation with the condenser water pumps We thank you for the opportunity to provide you this proposal. If you have any questions please do not hesitate to contact us. We look forward to working with you in the future. T e nvironmental & Mechanical Services, Corp Tr " echne i 1 .1 � 1 Vice President 3210 Flagler Avenue Key West, FL33040 Tel: 305 nan iWAVY-_ temenvironmental@,yahoo.com Equipment & Material $ 3,293.92 Tax =B7+BIO $ 197.64 Subcontractors $ 36,796.00 Miscellaneous $ - Su rvn $ 450.00 Labor $ - Insurance $ - $ 40,737.56 Bid Amount 5% P t $ 42,774 43 WIM BID 42,774A3 -ME, Unit LOA Total LBR QTY Equipment & Materials Unit Price Cost HAS Hours LBR Dollars 30 18" sch 80 PVC $ 28.50 855 45.00 0 $ —,.- -8"Sch8O Flan ges $ 45.71 $ 274.26 $ 45.00 0 $ 6 B" Sch 80 90 deg elbow $ 79.61 $ 477.66 $ 45.00 0 $ I Gallon Glue & Cleaner $ 125.00 $ 125,00 $ 45.00 0 $ 1 8" Buttefly Valve S 378.00 $ 378.00 45.00 0 Gask Kits $ 21.00, $ 12&00 $ 45.00 0 Lt4 8" flan ers W/Rods 112.00 $ 4413.00 $ 45.00 0 $ - $ 45.00 0 2 Nights Housing for ISE 3 $ 610, 00 $ 45.00 0 45.00 0 SUBCONTRACTORS I.S.E. Welding — _L 8,440-()0 Siemens Controls 28,356.00 Controls Guess Overhead 1 Equipment Rental T&B 36,796.00 Miscellaneous . . . .. . . . ....... Plywood screws & Metal Submittals & 0&M's 0 Rough Material Factor Loo 1.00 Rough Material Total 45.00 0 Equipment Total 3,29192 INS Rate 0.09700 Equip & Material Total 3,293,92 -ME, pfWpOSAL SUBMITI ED TO TEM ENVIRONMENTAL &MECHANICAL SERVICES CITY. UA MX2wX I=. it teB lov 100 NE 3RD STREET UNIT (F) RALLANDALE FL. 33009 Mechanical Construction & Structural Welding OFFICE (954) 458-WELD (954) 458-9353 Fax (954) 455-7932 CELL (305) 804-1924 305 9894-2683 June 1, 2018 .. . ........ STOCK ISLAND CORRECTION CENTER . . . ... ......... 1 1 , 1 9 PAY OF 50% BEFORE START IN G MAIL OVER N TE BEFORE ARRI VAL, , 1) 50% AP PON COM PL ET I[ON. We ProPOSe hereby to furnish labor and materials ® complete in ac ance with above specifications, for the sum of: 50% BEFORE STARTING AND 50% APPON COMPLETION ($ $8,440.00 Payni�,t i;�b.iAde as WOW& F57-7rYT#-1TW-r-7=-- �.q mpmMIM Eu= � Siemens Industry, Inc., Building Technologies 3021 N Commerce Parkway, Miramar, Florida 33025 Stock Island Detention Center 5501 College Road Key West, Florida 33040 Project: Stock Island Detention Center CW Equalizer Line & Control Sequence Name Matthew Lammer Department Automation Service Project Telephone 954- 364 -6737 Fax NA Mobile 954 - 609 -3685 E -Mail Matthew. Lammer@Siemens.com Date 6/18118 Siemens Industry Inc is proposing to provide one control actuator for the equalizer line, one control actuator for the CWS suction crossover line, additional PXC 110 modules, relays, and transformers. Siemens shall furnish and install new rigid conduit, control wiring, and 120V power wiring from the Siemens control panel to the two new control actuators and specialist labor to implement the revised CW valve and pump sequence. Exclusions: • Permit fees. • Painting and patching This proposal is valid for 30 days from proposal date. Proposed Company Name: Siemens Industry, Inc. By (Signed): Name: Matt Lammer Title: Project Manager Date: 6/18/18 Siemens Industry, Inc. Building Technologies Division North America Headquarters Project Cost $28,356.00 Accepted I have read the attached Terms & Conditions of Sale, understand them fully, and agree to abide by them. I understand that payment is due upon receipt of invoice. 1000 Deerfield Parkway Buffalo Grove, IL 60089 United States Company Name: By (Signed): Name Title: Date: Tel, +1 (847) 215.1000 WWAAAOA p 1� , Irlrrlttlt.e`ii Page 1 of 2