#8th Change Order 08/30/2018 t. Jacobs Key West International Airport 08/18 Monroe County Strengthen/Rehabilitate Commercial Apron Project No. GAKAP148 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 8 Strengthen/Rehabilitate Commercial Apron INITIATED ON: August 23, 2018 CONTRACT: GAKAP148 TO (Contractor): ABC Construction, Inc. 7215 NW 7 Street Miami, Florida 33126 CONTRACT DATE: November 22, 2016 You are hereby authorized and directed to make the following change(s) in this Contract: The increase of the contract time by 60 calendar days is in accordance with the attached Substantial Completion Letter. The additional contract time is for the completion of the remaining punch list items. The original Contract Sum $ 9,250,000.00 Net change by previously approved Change Orders $ 41,583.30 The Contract Sum will be unchanged by this Change Order $ NA The new Contract Sum including this Change Order will be $ 9,291,583.30 The Contract Time will be increased by 60 DAYS Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: AGREED TO: Jacobs Engineering ABC Cons ction, Inc. Cb y D to I By AUTHORIZED: AF4 ROE ` 11 ,A1TORN • �o • Key West International Airport Monroe County p .; -;• 3491 South Roosevelt Blvd. 1100 Simonton Street •1• 1ST. • COUNT Oftr Key West, FL 33040 Key West FL 33040 Date, // �� // � PY• ,r836 / 3 `- a 006 Date By g ounty i Admmrstratoro IICE-1■1\1 1/4 v '‘)kk ACkw■ 417-' A (iOI\ctt 4l 41°46''( QOwtiNeA;TN 44- c +LW 4Lis 61\conk, 4. Change Order Attachment per Ordinance No. 004 -1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The increase of the contract time by 60 calendar days is for the completion of the remaining punch list items. • Change Order was included in the original specifications. Yes ❑ No El If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: C ounty of Monroe ___n•_• BOARD OF COUNTY COMMISSIONERS i i , \ Mayor David Rice. District 4 The Florida Keys . i . \. ' Mayor Pro Tcm S)h ii1 J. Murphy. District 5 � r — ' ; j� , Danny L. Kolhugc. District 1 \'` ' -` George Ncugcnt. District 2 ` : Flcalhcr Carruthers. District i August 22, 2018 Mr. Jorge Gonzalez ABC Construction, Inc. 7215 N.W. 7 Street Miami, FL 33126 Subject: Substantial Completion Strengthen /Rehabilitate Commercial Apron Key West International Airport Monroe County Project No. — GAKAP148 Mr. Gonzalez: The work identified in the contract documents for the above contract dated November 22 2016, has been reviewed and found, to the Engineer's best knowledge, information and belief, to b 1 (..-- substantially complete. The date of Substantial Completion is August 0� 018. The Contractor will complete or correct the Work as approved by the Owner's Authorized Representative (OAR) on the list of items within 60 days from the above date of Substantial Completion. A list of items to be completed or corrected is attached. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. This list may be amended based on the results of the final inspection. A final inspection will be scheduled at a date determined by the Owner, OAR and Contractor after the Contractor has completed the list of items attached. Unless otherwise agreed to in writing, the date of commencement of warranties for items on the attached list will be the date of issuance of the final Certificate of Payment or the date of final payment, whichever occurs first. The estimated cost of the remaining items is $400,000.00. The Owner and Contractor hereby accept the responsibilities assigned to them in this Substantial Completion: Pe- Ciaidtl‘ AG \ ` 0 a CONTRACTOR 1 c A U - PRI ED NAME A D ATE (Firm Name) TITLE Monroe County � � T. J. Henderson BOCC . �., Acting Director of Airports ,.11- 2z , z of $ OWNER S . • RE PRINTED NAME AND DATE TITLE