Item B1 3.14 Capital Improvements Monroe County Comprehensive Plan Update
3.14 CAPITAL IMPROVEMENTS
GOAL 1401
Monroe County shall provide and maintain, in a timely and efficient manner, adequate public
facilities for both existing and future populations, consistent with available financial resources
and the other elements of the Comprehensive Plan. [9J 5.016f & 163.3177(3)(a)D, F.S.]
Obiective 1401.1
Monroe County shall provide the capital improvements necessary to correct existing
deficiencies, to accommodate projected future growth, and to replace obsolete and worn-
out facilities, in accordance with an adopted Capital Improvements Program. {
5704-6f&163.3177(3)(154)11., F.S.I
Policy 1401.1.1
By January 4, 1997, Monroe County shall reviseupdate annually the existing
County Capital Improvements Program to incorporate the improvements
identified in the Five -Year Schedule of Capital Improvements incl��Table
4.1 . .. - - - . - - - . • ..J& 163.3177(3)(a)5.(b), F.S.]
Policy 1401.1.2
Monroe County shall annually update the Comprehensive Plan Five -Year
Schedule of Capital Improvements. Proposed revisions to the Schedule, including
those addressing the replacement and renewal of capital facilities, shall be
evaluated,— and updated, and rankcd in accordance with the following
considerations (not listed in order of priority):
1. consistency with the relevant elements of the Comprehensive Plan;
2. the elimination of public hazards;
3. consider sea level rise projections as they relate to transportation and
bridging projects in particular;
4. the County's need for financial expenditures for infrastructure
improvements within or proximate to vulnerable areas;
375. the elimination of existing deficiencies;
476. financial feasibility including the impact on the annual operating and
capital budgets;
677. the location in relation to the Future Land Use Map;
6:.8. accommodation of the demands from redevelopment and new
development;
Capital Improvements Element 1 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
7:9. the consistency of the improvement relative to the plans of state agencies
and the South Florida Water Management District; and
8, 10. the availability of other revenue sources including, but not limited to,
FDOT Project funding and FDOT Traffic Operations funds from District
Dedicated Revenue (DDR) sources.
Revisions to the schedule shall be incorporated into the Capital Improvements
Program on an annual basis. [9J 5.016f §163.3177(3)(e)1 and 3]a)5.(b), F.S.]
Policy 1401.1.3
Capital improvement projects required to correct existing facility deficiencies
shall receive priority over those projects required to serve future development.
[9J 5.Ol6g163.3177(3)(ea)1 }., F.S.1
Monroe County shall amend thc Comprehensive Plan Fivc Ycar Schedule of
Capital Improvements by January 1, 2000 to acknowledge funding of
improvcmcnts to thc 18 mile stretch of US 1 by the Florida Department of
FDOT Fivc Year Plan for completion by Junc 1, 2002.
Poliey1404
!!!!
improvements to mile markers 80 to 90 section of US 1 by thc Florida
■ .. -
years of thc FDOT Fivc Year Plan for completion by Juno 1, 2010.
<The Remainder of This Page Intentionally Left Blank>
Capital Improvements Element 2 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upuate
I Five -Year Schedule of Capital Improvements Table
(Adopted by BOCC January 16, 2014 - Ordinance 001 -2014)
MONROE COUNTY, FLORIDA
Schedule of Capital Improvements
Fiscal Year 2014 - 2018
1 TRASNPORTATION (Policy 301.1.1)
Road & Bridge Projects Project Appropiated
Protect 8udret As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Taal
gonda Department of Transportation
:• 9+: sou :nca r- f M tat or 7 ! stage 893+123 aeoar 6• cce -•e: M •eq- 12.261 502,215 - - - 514.476
1ar•oar &Qt 'rage atone for ae +ca.• •ere_ - 2 60.000 - - - 260,000
Yoe Corry ...Late rrer•ostor -3.a c Car»rx:.ar r= ••c■•• [ng.•.eerag 200,000 350.000 200,000 200.000 - 950.000
vo• roecol+•y :row NraCCOetrer_ --fr-w 59,977 83,285 64,2220 66,220 68570 342.272
vo•roe Carey Xs •ea •Ice Corgnge.:r •ezr'serg 10,000 - - • - 10,000
Vernoe COI.,rvwCe OD/ OA C ~t'90r 50.353 - - 800,000 - 850,353
vo•roe Ca'tyroe Dray.age Drayage ...V'' e 222 418 39,140 254,469 - 286,012 802,039
vonroecareomoel.ctrg va.rterr= 37,991 39.131 40,305 41.514 42,759 201,700
vorroe Ca•eyrae ae:v'wrg'rget •n •ear + acrg - - 48.740 30,583 1.000.000 1 079.323
vo•.oe Ca.rerra *.y„ ooeraoor: - 70 3 3o Ce: - . r a.e - 372.860 - 327.300 - 700,160
a :a 9aC :.eg a 'rage meow r Ore-a • •Caro: 9,796 - - - - 9,796
•rx.e.7 VC Ctro..✓ Mr+t:•r Co Ctc•t•Cr'or aue.rt •ro •ear tcrg - 966.453 1.469,844 1490.270 1 570 270 5.496,837
7 3. M9 993 tavM :a:! 41,3 rg 30,000 345.348 - - 375.348
:a ! My 2a ! to va z! at tare •O•a•r'`erc: 1.438 183 - - - - 1.438.183
:a 3 MV 3.9 3 to WA U Z! •tanccrg 35,378 - - - - 35,378
:a! Vv :: 3 to VM :3 9 •tarascrg 317.277 - - - - 317,277
:• ! MV GI 21 to %4M .. 3 392 •eorrecrg 6,120.240 - - - - 6.120,240
:a ! ..AV 9C t to Vet s- xcaxg 936,072 21 .5 - - - 1.153,649
? ' 93 to Vat r •ecv•aCrg 623 621 - - - - 623.621
:a ! MV 9 to vM P99 rwrg 488,020 1:2.198 - - - 600,218
:•!MVterr V..t:ar2 •e:v'ecrg 84.71C - - - - 84,710
.
• ! •.'V 92 to Vr.t 93 •ea.r scrg 85.912 - - - - 85.912
:
a ! My 99 t to vr.t :af 1 arcmorg 952.963 206,000 - - - 1.158,963
:• ! : or _ang lawn s..c to •. or •:rg sea_ - r a .c • tu'+crs 684,064 - - . - 684,064
:•! •eu'•crg 7,849.717 1.133,000 - - - 8.982,717
:• ! MV 21 to MM 32 99 an:Ma'r; • 110,000 - 372 501 - 482.501
:• ! MV 9: to V9.1 92 •ear'lCrg 135,901 - - - - 135,901
:• • MV 2' 4 to VM 29! •tarYcrg 2 02,441 - - - - 202,441
:9, Cve• -tre WO .e, crenne trey •eae • rare -+enan 'aenao 2 ,059,833 - - - - 2.059,833
:a ! Ow. Cr c -rn:.s r (Trutt trege Rem rare-awe Rear: ` 277,597 - - - - 2 77,597
:• ! - M.e s- age one• Mate Carr,* sr age meow rages ear• 'Rene:, 1 C4".132 7 346 731 1,475,032 9 868.895
Capital Improvements Element 3 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
ProOIC1 01dppt As et 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2013 TOW
S• 1 .t T.1 M S..,, . .rb .r..v4 Orifte MM 1 1 SW .INO Ir.. 1,900,575 - - - - 1,900,575
S• t ...1 T.1 w 14 W MM 11 o4..! ; 1..1, 504,000 - - - - 504,000
u S*Iv 11.IM•f 16 S bMM 143 w.►a,. T..4 145,535 - - - - 145,535
S.1 s .•a..1 •....a 111.4 to t ./ Ma u...d V+... 1,040,365 118,450 - - 1,158,315
>• 4 C.. O 1...A.tn.. 1.... thaw. •a
S. wg..
•.... •..4AWNS. 302,750 - - - - 302,750
lit 4 u.w e., lt..... ■ ,i ..s, OM 1 100074 •w. •••.. •.5..A.1.r 839,161 173,040 - - 1,062,901
IN 4 .. Cr. 4 r, •..1 & • .*wain M r...n.
N.. ..1.+ 130,347 - - - -
d her, 4...71.. WA 130,347
Subtotal - FOOT 27,338,153 5,730,481 9,769,657 4,303,420 2,967,611 51,109,327
Revenues - FOOT 27,833,158 5,730,481 9,769,657 4,803,420 2,967,611 51,109,327
Monroe Canty
6.4 Nowt rwp... $ 22.81.111 S - S5,000,080 S5,000,000 13,500,110 54,000,080 4,500,000 22,000,000
,w •M•b +.61 55.000.000 S2. 500 -000 S2.500.000 53.500 -000 4,500,000 13,000,000
tar .,..1. so So SO $500.000 500,000
1w •..r a ...qr. ...MI 146.... SO 52.500 000 S 1.000.000 SO - 3. 500,000
•04. •........ 55,000,000 S5,000,000 53 54,000,000 54,500,000 22,000,000
T.......•`. ..q ..•..le S 150.011 S 20.11 825,000 104,520 - - 929,520
11C "° ^ "' / .+11.4...• 325,000 104,520 - - - 929,520
.n 1 ..r.d..i•/51..•.4 u.. ►..1. S 2.513.141 S 423.1[5 1,037,900 1,001,216 - - - 2,059,116
ftrtorsan
IJS Stal•u..b 1,053,021 - - - - 1.053,021
sio ••••••••• 1.1..1 •.../..a 34,379 1.001286 - - - 1.036,165
r r. ....' . .. 1,087,900 1,001,286 - - - 2,059,136
IS 103 w l«.... S 3.104.111 S 282.051 1,350,003 571,443 - - - 2,721,446
ftnemars
■
1 .wnsw....•a «- . . vet ....a sr..:. 1,150,003 571,143 - - 2,721,446
urw.,r..•1..> S 1,13,100 S 1.111 1,096,166 - - - - 1,098,166
14 •.a. r..e. 1,091,166 - - - 1,095,166
o.t +o •••-t•• • .. S 80,101 $ 315.2.5I 545,510 - 545,510
Capital Improvements Element 4 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upuate
Project eudget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
N " 545,510 - - - - 545,510
.- . w.a. L>♦.....1 liar. S 3.005.636 S 2.831.662 176,974 - - 176,974
us "" wan" 176,971 - - - 176,974
._ w.... u.y. S 6.:10.133 S 1 6,335,945 - - - - 6,335,948
t "' su. w..n 5,2'0 013 - - - - 5 :'0,013
ix •�'1•. 1,065,935 - • - - 1065.935 ■
+ a " ^.^ S4.333.918 - - - - 6,335,948
4....-.5.....d ►..d• •...• a .t......... S fk60.000 S 66.813 513,186 - - - 51.3,186
1, I woe,* l...rt. 513,156 - - - - 513,156
, -............A.,,. M••• rr-t Soar. w.rios. S 1.230.000 S - 150,000 1,080,000 - - - 1,230,000
'rs S"" ..a.. 150,000 1,080,000 - 1,230,000
•.r-. �.., r.+.tnr, l' S 180.000 S - - - 480,000 480.000
" s •'•'. " "' - 480,000 - 480,000
Subtotal - Monroe County 42,315,440 4,195,504 17,582,687 8,057,249 3,980,000 4,000,000 4,500,000 38,119,936
!Total Road & 8rde Projects 1 1 1 1 45,420,845' 13,787,730' 13,749,657 1 8,803,420' 7,467,611' 89,229,263 I
Mass Transit
Project Fr 201.4 FY 2015 FY 2016 FY 2017 FY 2018 Total
•LR,
ti r.ut..t,
Mu..... C..,*,
%, ."s.p.t.
Capital Improvements Element 5 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Ports
Protect FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
TOOT
You P,....
etm.... <aw .
4, Fula .
Aviation Project 4PPtoPneted
Protect Budget 4s of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Marathon Airport
001.0006 Imam Moro■ a..rw. ...r...eo.. 1,000,000 S 116,710 230,707 652,513 - - - 803,290
bawl.
" ji°"t ftegwoar, 162,712 652.583 - - - 815,365
Tm T•r ..«m■ 64,350 - - - - 64,350
401 sum vm.e 3.575 - - - - 3,575
%we.AT••w••a 230,707 652,513 - - - 883,290
1OOT •Otl! SIraviTo14.4k awtls. P,....•.mm 147,940 - 147,940 - - - - 147,940
kremeTvors
lQa up. raybw....... 73,970 - - - - 73,970
Tau S4m. Lewd, 73 - - - - 73,970
Noce • nrew•e 147,940 - - - - 147,940
1 001 A0110 W l..•.....re 013 K+w...■) awU' live/COT 1,560,000 59,400 440,600 601,930 - - - 1,042,530
DOT •0s» Tmw..aTtm.•.fm. K.,r..a) a...0a. w.d0m. 325,000 - - - 325,000
....... i....6.11141401.11 OW 11 )crtm..) Adobe. ...woo. 133 - - - - 133,070
T..1 nme..ta..wr4nw 1,540,000 59,400 894,670 401,930 - 1,500,600 •
■
mw Deo e^•^ 349 300.965 - - - 650,000
mat T•d•r W ' "T ' 200.600 - - - - 200,600
' ""• '""° 349,035 300.965 - - - 650,000
Tuaa••mw.e. 191,670 601,930 - - - 1,500,600
100T 00043 Mom, Sono*, a +°°".i.t, 100,000 - 100,000 - - - - 100,000
AnaTsTves
sir up= stay Imam .r.
20,000 - - - - 20,000
Capital Improvements Element 6 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan _ ite
K0 sct Budget As 4 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
w sv• -.nb 8(1.000 - - 80,000
�• • • 100,000 - - - 100,000
*1844. ' .Nw.w++.N ....,,. ...,.« 36.000 - - - -
36.000 36.000
a,. twat/rata .... » 1800 - - - 1.800
...0 redo. al ,...w 32 600 - - - 32,400
' -•.ft
' 1.800 - - - - 1,800
+ 36,000 - - - 36,000
ubbaa bv■...ow. Mt.'tiwn ..,.r... ...e. 457,121 - 457,121 - - - - 457,121
40$ Up.a na..M-w :
22 856 22,856
-
ant r.w«oll ...nt>
411 609 - - - 311.309
■OJ '"l• 1.,..'i° 22.656 - - - - 22.856
`W el a ^tr"ta' 457,121 - - - - 457,121
• «.,■.:r..rtap...... "'"• t ' •••' 3,250,000 - - 3,250,000 - 3,250,000
4:1 u..r.n.y w.. -,,., - 650 000 - - - 650,000
' 5u.• %et. " 2.600.000 - - 2.600.000
' tea" '-'-n - 3,250,000 - - 3,250,000
co......... al r: r •n...+...., -. ••.��.• i 1500,000 - - 1.500.000 - - - 1,500,000
newava
..:J ttata .t n' ..... -,.., 300 OLIO - - - 300.000
.. 200 000 - - 1.200,000
1,500,000 - 1,500,000
• ' ■.rw.e.. Jc . •b .■w """ •« «''', 20 000.000 - 20 - - 20,000,000
ry uowt ^■ ""''"" - - 1.000 0 - - 1 000,000
.WI r.br■1 to ants - 18.000 000 - - 18 000,000
wJ rata - 1,000.000 - 1,000,000
.' «For+ 20,000,000 -
- - - - 20,000,000
t....i ■�
�..rl» • „r 2,000,000 2,000,000 2,000,000
wJ uyn r .,, ,... ,.., - - 100 000 - - 100,000
Mari 1•64 totaala - - 1.800000 - - 1 800,000
6 .J :u• 1�...4 - 100 000 - - 100.000
, n......., „ - - 2,000,000 - 2,000,000 •
• Capital Improvements Element 7 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Protect Budget As or 9/30/13 FY 2014 r 2015 FY 2016 FY 2017 FY 2019 Total
4....4.t.twWc.......-.w.M.... ..4..., +. 2,000,000 - - 2,000,000 - - 2,000,000
401 Uporsrla e.44"'° 100,000 - - 100,000
404 t'd'd ""1° - - 1,900,000 - - 1,600,000
4m La. `".i° _ 100.000 - 100,000
Nisi Ammon 2,000,000 - - 2,000,000
144044.. 4404444h P44% 44.01. 4s.ei.. 44444.4 5.4441, 75,000 -
- - 75,000 - 75,000
Mw...,
.m ow.rr.. - - - 7.500 - 7,500
*W ■••1•41 •"" - - - 67.500 67,500
44....• - - - 75,000 - 75,000
44•44.. 14,4.4.., 4•t..4rA.4.. £,, k,.......44,... 1,200,000
1,200,000 1200,000
4l U^ Ong `4""" - - - - 60,000 60,000
40,1 t441.4144444
- - - • 1,080,000 1,090,000
404 54.4 ti44a
60,000 60,000
, s. 4..w4.. - - - - 1,200,000 1,200,000
44w t4. 1.444144444. 4.44.4 4 4 . 4 , -40 400,000 - • - - - 900,000 600,000
.....v.
405 0r.0146 444444m, - - 40,000 40,000
401 #4.144414•4441 - - 320,000 320,000
401 S44t4 w..e - - - 40,000 40,000
'Y '''^• - - - - 400,000 400,000
t.r44r 4144441 tsy....+ Mama 444x ..1. , 250,000 - - - - - 250,000 250,000
4.....1.+
403 un..4ft 41•08,41. . - . - 125,000 125,000
40.1 54•4• ...4m
- 125,000 125,000
'ace mFO 1O - • - - 250,000 250,000 '
t..4.,t o...... w.. Milky. 14..n.41104 0 00 . 000 - - - - - 2,000,000 2,000,000
401 Uwe 4 44/4.•..., - - - - 1,000,000 1,000,000 '
"" 54"4 (•..b - 1,000,000 1,000,000
, a. ......w. - - - - 2,000,000 2,000,000
*Sage 944`d 11/41.0.•• ttn.d.t♦ 4 •0°' 14.0."404 590,000 - - - - - S00,000 500,000
Capital Improvements Element 8 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upudte
Project !Midget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
4441 '.J" •....«...' - - • - 250,000 250,000
40i 1... W..b
- - - -
250,000 250,000
• 40 044w - - - - 500,000 500,000
t....d Wins l....r.. • 1Wwt.wn..0d a"'°.. "^`o" 5,000,000 - - - - - 5,000,000 5,000,000
eat U .m,,. 4444" - - - - 2. 500,000 2.500,000
.W :1.. W4.D
2,500,000 2,500,000
•u.. A■••■•. - _ _ - 5,000,000 5,000,000
A.*l l.r WM. None A.Ylkw A.'.iU.. 1 ,500 - - - -
1,500,000 1,500,000
Aggoonwin
401 ".. O4 A........ • - - • 750,000 750,000
401 ' 44... b
- • - - 750,000 750,000
•Y.. A... -- - - -
1,500,000 1,500,000
tt..r...... Air.. 11.4(w• 500,000 - - - _ - 500,000 500,000
Mamma
40.+ upowwg ^�
- - - - 250,000 250,000
441] SW. Went.
250,000 250,000
.a. A44.a4 - - - - 500,000 •00,000
Total Marathon Airport 43,476,061 176,110 1,870,438 6,004,513 24,000,000 75,000 11 ,350,000 43299,951
Key West International Airport
1007 1* %KUMTY i AITY A..do. 1.4v, 1,320 ,185 1,242 ,260 77,925 - - - - 77,925
00..00,..
.o. 01• J b 77,925 - - - - 77,925
11410461 AMA tLVTh IV* 40.0W *WU.. 224.318 45 328 178,990 - - - - 178,990
ArrvrlAw SW II AI Awn.. Mru. 775.316 515.544 259.772 - - - - 259,772
4•6tU10T04 OAS Awe.. O.. 300000 297 636 2,364 - - - - 2,364
T.4.i.40044 4...40.0. 1,299,634 851,500 441,126 - - - - 411,126 •
A.,.....
A u..... A-..... + 110,281 - - - - 110,281
$ .A
404 WW1 V`4b 220,564 - - - _ 220,564
au vtli "4b 110,281 - - - - 110,281
'•-. 441,126 - - - - 441,126
w+ ISO NW* SW* *34 Aw414 0.16/040 447,260 382,799 64,461 _ - - - - 64,441
Capital Improvements Element 9 - Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Progect Budget As of 9/30/13 it 2014 n 2013 n 2016 FY 2017 FY 2018 Total
4•04.0on
as 110101 e44g 40■•••■ 3,223 - - - - 3,223
a0s `i°"r..•'n° 61238 - - - 61,238
•
tot. a....... 64,461 - - - - 64,461
root &w on gw Kw*. sraw Adage. g.4rog. 262,687 - 262,687 - - - - 262,667
4.0.44.,
404 1040004104444014 131,343 - - - - 131,343
404 Mole 0400 131,344 - - - - 131,344
' 4.'•..4.0'n 262,667 - - - - 262,687
P.. e4.r...4. vd era Anr4. 4._0.4.0 102,550 81,973 20.577 - - - - 20,577
4.0.4...
404 "•" 6400 104.440. 1,029 - - - - 1,029
404 0'46"x' """' 18,519 - - - - 18,519
404 5484• "e b 1,029 - - - - 1,029
'4.A....,.,. 20,577 - - - - 20,577
the% MAP "tr A.0100 44.04,000 265,000 151,940 113,040 - - - - 113,040
44.0.4
401 l)4444002 4444444404 5,652 - - - - 5,652
e04 r.d•.41 0040 101,736 - - - - 101,736
ao' Mee 0.010 I 5652 - - - - 5,652
, 4240410440044 a 113,040 - - - - 113,040
OOUAprMO A' CUSTOMS 44 . 84 . 111 .Pag• 90,934 - 90,934 - - - - 90,934
4.0.4,•,
"" 0•000 ""'"'"' 2,273 - - - - 2,273
00 '•d• -.l "'•"b 06,388 - - - - 86,388
4"'' 14414 "' " 2,273 - - - - 2,273
.4. ewe.... 90,934 - - 90,934
+
WWI eon MO S re
tar A'., p...-..a.. 657,300 - 657,300 - - - - 657,300
44.40,
404 014444444.4.444.40-a 32,865 - - - - 32,365
404 4o41061%00w 591,570 - - - - 591,570
.a s4r• to-dots 32,865 - - - - 32,365
T ula b...0. 657,300 - - - - 657,300
uw ACau 0044 40004 144.104.000 552,000 • 552,000 - - - - 552,000
44..0•4
404 "'erred 444'•'a'^ 27,600 - - 27,600
-
Capital Improvements Element 10 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upaate
VrOJect Budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TO121
066 ..a.r w...b
496,800 - - - - 496,800
406 54604 04010 27,600 - - - - 27,600
,... •..•.e 552,000 - - - - SS2,000
lima 4..M0' Z? 01•01/4/ •0000. b -
436,400 - 436,400 - - - 436,400
.06 u.m r.. e....... 21,820 - - - - 21,620
046 4•406r wont. 392.760 - - - - 392,760
106 buts w,..b 21,820 - - - - 21,820
,.w- •....r. 436,400 - - - - 436,400
DOM OROS OSP•r •.,.Y., N..,.rivw 567,200 - 567,200 - - - - 567,200
Nnarwon
6 "l' •ei 1001101, 28,360 - - - - 28,360
"
°m "dir wants 510,480 - - - - sio,aso
'w -. 28,360 - - - - 28,360
, a. 1.00020 567,200 - - - - 567,200
ems wwn 17 (.060060 0.6 ••fien 0006 5,500,000 - 5,500,000 - - - - 5,500,000
.on V°• eiriwr 275,000 - - - - 275,000
101 fidii0"'•nb 4,950,000 - - - - 4,950.000
406 e•.0• "s _ 275,000 - - - - 275.000 •
re0.•...... 5,500,000 - - - - 5,500,000
C.a n..raW 40-00 e..e...n,.tl.., n...1 •..m. r•......een 3,000,000 - 3,000,000 - - - - 3,000,000
.o+ °°"°"e 101000' 150,000 - - - - 150,000
.a. 001r46 wr0616 2.700,000 - - - - 2,700,000
ar. 041• 0,4016 150,000 - - - - 150,000
'ass •.••••.e 3,000,000 - - - - 3,000,000
r...6. V6411604 1401 006 • 16.0. Aowtlest 010060 150,000 - 150,000 - - - - 150,000
"a Op. Om e. " ' 7.500 - - - - 7,500
101 •.d.. "'•"b 135,000 - - - - 135,000
606 54a. Lb 7,500 - - - - 7,500
.e0. •y...,e 150,000 - - - - 150,000 ,
•
C...v.a.u.ge. Mamie 1 10.e., 000 400,000 - 400,000 - - - - 400,000
16..6.n
N.6 w•+.6 e....... 200,000 - - - - 200,000
Capital Improvements Element 11 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Propect Ott As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Tot41
• keg t ' • " b 200.000 - - - - 200,000
tut Manua 400,000 - - - - 400,000
( .w . � t•+ Or. tion PL... J Moak.. ••aeo. 3,000,000 - - 3,000,000 - - - 3,000,000
.Ot UM. One .•■•■••. - 150,000 - - - 150,000
.w .M..el ',..e, - 2,700,000 - - - 2,700,000
1104 "•`• °0•"b - 150,000 - - 150,000
s.. "........ - 3,000,000 - - - 3,000,000
e,..... 947 O.i.w..... W... MP.. e...M ...r... P.m...e... 400,000 - - 400,000 - - - 400,000
..). u°"O"O •........ - 20,000 - - - 20,000
..y •.d...l inO • 360,000 - - - 360,000
"" ""• ""° - 20.000 - - - 20,000
'.•. a••.•..e - 400,000 - - - 400,000
N... .,wl.er. hope. then W O.ws. rw....r." 743,500 - - 743,500 - - - 743,500
ftwnwes
' Uwe atom ^ - 18,538 - - - 18,543
.o. ` idiel "' 706,324 - - - 706,324
101 SSA• Wants - 18,543 - - - 18,588
No. •.•••••• • 743,500 - - - 743,500
r. t. n....1 A.M. .4111111.41.0ft 4,000,000 - - 4,000,000 - - - 4,000,000
40. uo.r.y... " • 100,000 - - 100,000
• 1441.1 `•nb - 3,400.000 - - - 3,800,000
.w 1.Wto y. b
• 100,000 - - - 100,000
'w• Arveywis - 4,000,000 - - - 4,000,000
• t "' o " e ' /•r.. IrArty 500,000 - - 500,000 - - - 500,000
Olrornun
• }• u....". """"" - 250,000 - - - 250,000
.111 sta. W..b - 250.000 - - - 250,000
..r.. w...... - 500,000 - - - S00,000
Mon. ^O" UpaNr • •■^e+M•deo•• 600,000 - - - 600,000 - - 600,000
.......
401 u'.'°"s O"'"^ - - 30,000 - - 30,000
.0. • ,..,..b 540,000 - 540,000 - - 540,000
AUG Late t✓..b - 30,000 - - 30,000
•
Capital Improvements Element 12 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upudte
Protect Budget As 019/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2011 Total
, a.444owe - - 600,000 , - - 600,000
.
4..4.44Y.... P..y . w 44
. ci. .41..4 b4w4. 1
4o4 1,381,500 - - - -
341 sa0 1,381
404 Ur.4404. 144444440 - - 34.538 - - 31,534
40. 4./.41 w0/44 - - 1312,424 - 1,312,424
.a W. v..b 34,538 - 31.534
..440 444.4.., - • 1,381,500 - - 1,381,500
00 a 044..1 44■1444 r4.le.4r,o. 4,000,000 - - - 4,000,000 - - 4,000,000
'°' 0 ........ 4...-... 100,000 - - - 100,000
-- 4.1.414Mwb - - 3,800,000 - - 3,400,000
404 Wo4r4eb - - 100.000 - - 100,000
'.4w .b4.4s - - 4,000,000 - - 4,000,000
...4•444 1 -0 44444414444444 P144. l K44■•4444441 44144w. •...4..e.. 4,000,000 • - • 4,000,000 - - 4,000,000
444•4....
484 4044 4444.44"444 - - 200,000 - - 200,000 Upoi
404 404.41 .000 - - 3,600,000 - - 3600,000
404 W. .Arta - - 200,000 - 200,000
, u4• 44... - - 4,000,000 - - 4,000,000
11.... (Mow Dan l..r.41.. 4444144 44444041144 500,000 - - - 500,000 - - 500,000
44..44..
40.4 U,- obey 4.4...w - - 25,000 - - 25,000
4a 4.4.41 worn. - 450,000 - - 450,000
401 Male ....44b 25 - 25000 - - 25,000
, ,0 444. - - 500,000 - - 500,000
OW 41•041 4444404 WW1, 301,000 - - - 301,000 - - 301,000
444444441
4041 0404144. 44404441 - - 15,050 • - 15,050
404 4.41..41 won4 - - 270,900 - - 270,900
404 W. 1,440 - - 15,050 - - 15,050
, ....4.4..0 - - 301,000 • - 301,000
Avow 1.0 5JLUl444. Plano Z K44444e40.44 444•04 4444•4•4044 4,000,000 - - - - 4,000,000 4,000,000
400 ,•4+411484"4" - - 200,000 - 200,000
404 4.11..41 ,44040 - - - 3,600,000 - 3.600,000
404 W. Lomb - - 200,000 200,000
Capital Improvements Element 13 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
PTotect Budget As of 9/30/13 FY 2014 FY 2015 Fr 2016 Fr 2017 FY 2018 Total
- - - 4,000,000 - 4,000,000
• r • Y t •.•rnr w.....r. r• 4,000,000 - • - - 4,000,000 - 4,000,000
•
L� � • �• - - 100.000 100,000
LA •.J..1 ....A
- 3.800,000 3800.000
L � '• - - 100,000 - 100,000
••^ - - - 4,000,000 - 4,000,000
. N,.....• .dM. t.... t tta ...wt •.,.... .. , 500.000 - - - - -
500.000 500,000
'4 .iy.0 n•Nw. - w,
25,000 25.000
LI ..a.d •...m. - - - - 450,000 450,000
«4 !AM • '_, wA
250,000 250.000
"° ••••••d' - - - 725,000 725,000
• 1,500,000 1,500,000
LI US.. n• new -...,
- - '5,000 '5,000
«-4 t.Md -
1 350,000 1 350,000
6...I `..• ;.
-
' 5,000 ' 5,000
- - 1,500,000 1,500,000
.ti a• Salt tt.•.biibta, Awed. a.. .. t 1,300,000 - - - -
1,800,000 1.500.000
LJ• Up..ln• N.yf•. ,-. - . . - 90 90,000
Lit 'ode el .,•.," - - - - 1620.000 1.620.000
- -
90,000 90,000
, ,w,. ••.•...., - . - 1,800,000 1,800,000
.» t ......... I .v.t«n •.,.t.. ,.t..• 1,000,000 - - - 1,000,000 1,000,000
4.r Uproot. .y now-...,
50.000 50,000
4d I.,i•e d ..r.' - _ - _ 900.000 900,000
L/ .it. - '.,A
50,000 50,000
'" t" N^^ - - - 1,000,000 1,000,000
t.rtr Y...t t MU..... 250,000 - 250,000 250,000
LA ut..+d.n••...^..+ - - . 125.000 125.000
- - - - 125,000 125,000
••• - - - - 250,000 250,000
Capital Improvements Element 14 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan _ Ite
PT ojeCt budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
u11..11.1Iw +M. ••••• ^•• o. 5.000,000 -
5,000,000 5,000,000
101 Uwe an. Mww -w'.
2 500,000 2 500,000
401 'J.1.'., ant. - - - 2 500.000 2 500,000
'.no n•••.un - - - 5,000,000 5,000,000
l...4 ,..... l.a►1y 500,000 ' - - - - 500,000 500,000
nnrK.
..1 U... I:..1 ....-ui.,
250.000 250.000
6)1 vw.'. --..e - - 250,000 250,000
No. "..w..r. - - - - 500,000 500,000
Total Key West International Airport 53,027.150 2,717,500 12.333,650 8,643,500 10.782,500 8,000,000 10,550,000 50,309,650
T0t4l- MA.1Wn 96,503,211 2,893,610 14,204.088 14,648.013 34.782500 8,075,000 21,900,000 93.609,601
Capital Improvements Element 15 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Potable Water (Polrcy 701.1.1) 1
Project Title Protect Appropriated
Budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Florda Keys Aquaduct Authority
evict-ere 4.300,000 3 2.100.000 2.100 000 2.100 000 14 300,000
+�- :rrce ►. +::z x wxo e-�: 750 000 7 50,000
. ^r :ix ai are.: 500.000 500.000 500 000 500 000 2 000,000
fix.:' t .' - 'rr: L :a Mee :vets 200,000 200,000
l:tr out or P 50,000 ' 50 000 7 50 000 1.550,000
'ore ca ! "£ oreFe "an* 2.600,000 2.600 000 5 200,000
are ►_raa t N L A erg TA a -..t— 1.000,000 1.000 000 2 000,000
Total - FKAA 4,500,000 4,200,000 6,250,000 6,950,000 4,100,000 26,000,000
Revenue: - FKAA 4,500,000 4,200,000 6,250,000 6,950,000 4,100,000 26,000,000
Monroe County Protects
Ocean eeeef Reverse osmosis Prow 2,600,000 - 2,600,000 - - - 2,600,000
"s. s - as
a]c- rratr.,sJr are: +a. 2,600,000 - - 2,600,000
Total 2,600,000 4,500,000 6,800,000 6,250,000 6,950,000 4,100,000 * 28,600,000
Capital Improvements Element 16 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upudte
Sold Waste (Policy 801.1.1)
Project Title Project App.opn.ted
budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
■
M.:mat Shed -Cudpe Transfer Station 175,000 - 175,000 - - - 175,000
414 - MSD F,. ^e C ^a-ge:'o- Se ce 175,000 - - - 175,000
H.zmat Shed -Long Key Transfer Station 175,000 - 175,000 - - - - 175,000
Fc.c ^..cs
.:1G - MSD F;. -'e C ^a-se:'o• Se -. ce 175,000 - - - 175,000
Renovatson of Trensf Stn 61dg - Cudpe Transf Stn _ 125,000 - 125,000 - - - - 125,000
cc.a - - e;
413 • MSD f,..e C ^arse: fo• Se -..ce 125,000 - - - - 125,000
Renovstn of Transf Stn bids -Long Key Transf Stn 125,000 125,000 - - -
va 125,000
Fe.ar,ras
114 - MS0 f, ^e C^a- ge :'o- Se-, ce 125,000 - 125,000
Renov.on of Trnnsf Stn bldg -Key largo Transf Stn 125,000 125,000 - - - -
t. 125,000
Ps.a ^.les
414 - MSD f. ^d C.2-;e: 'a- Se-. ce 125,000 - - - - 125,000
Total 725,000 - 725,000 - - - 725,000
1 Capital Improvements Element 17 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Sanitary Sewer (Polity 901.1.1)
Project Title Project Appropr.ted
Budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Florida Keys Aquaduct Authority
•- r -•..er _Die- r:.r, cara -- 't :150 - 650.000 2,500.000 1.000,000 - - 4.150.000
a•vor . _xig . e. . ss ateaor :.t 4,araon 150 000 - - 150,000 100 000 250.000
Total - FKAA 4,400,000 - 650,000 2,500,000 1,150,000 100,000 - 4,400,000
Revenues - FKAA 4.400,000 - 650,000 2,500,000 1,150,000 100,000 - 4,400,000
Monroe County Projects
Wastewater Upgrade to County Owned Facilities 1,020,886 449,858 571,028 - - - 571,028
5e.an-w
3.x • nibs:MCI-e :Ott :✓i, 571,028 - - - - 571,028
Duck Key Wastewater System -County Portion 14,233,101 14,057,210 175,891 . 175,891
Duck Key Wastewater System -FKAA Portion 2,988,767 2,988.767 - - • - -
Total Protect Expenditures 17,221,868 17,045,977 175,891 - - - 175,891
cir. .n_.
3:: - D>> . e..+.•.∎ :iota Fr: :aorta Oar. 175,891 - - - - 175,891
Cudtoe Regional Wastewater System 175,735,643 29,847,581 58,107,390 67,575,400 15,599,048 4,606,224 145,888,062
se. .n.w
112 - C,..e,oe tte; x.. wit Cars Fare :a; ,e ' '03,390 2,2'5.400 1.137,700 - 4,116,490
:b • :tote Grar' - .ten^ee 30.000,000 - - - - 30,000.000
.:.7 - storm, ant.- -it cr ,t, . ^r: - 1,300,000 1,300,000 - - 2.600.000
3==- _0.7; ar --Dar 2'.404,000 61.000.000 10,161,348 3 606 224 - 103.171.572
•
Capital Improvements Element 18 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upuate
Budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2011 Total
134 - :ra. - 3,000.000 3.000.000 - - 6,000.000
Tow! Revenues 58.10'.390 6' 15.599.048 4.606.224 - 145,811,062
Key larjo W •rtewater Treatment D,stnct 153,160,543 144,738,661 8,421,882 - - - - 1,421,882
:tint S 8,421,882 - - 8,421,882
Total 351.538.910 192,082.0" 6'928.191 '0.0'5.400 16.'49.048 4.'06. - 159.456.863
Drainage and Storm Water (Policy 1001.1.11
Project Title Project Appropruted
budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Grouper lane - Key Largo 421,824 - 421,824 - - - - 843,648
Ps. ate. cs
102 - F - 'a. 421,824 - - - - 421,824
Nrnth Avenue - Stock Island 746,874 - 746,874 - - - 1,493,748
102 - F_e 'a. 746,874 - - - - 746,874
Total 1,168,698 - 1,168,698 - - 2,337,396
On January 16, 2014. the 6OCC approved the tab.e above with a total of ;2,337,396, however the total is actually S1 168,698 (total column doubled the value
Capital Improvements Element 19 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Parks and Recreation (Policy 1201.1.11
Project Title Project 4ppro pr.ated
budget As of 9/30/13 Fr 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
thus Beach G.tness Trod 15,500 5.000 10,500 - - - - 10,500
)J.. Innzz -,c,e Je: ;.m. 10,500 - - - 10,500
Hsu: Beach Master Plan 3,600,000 - 1,000,000 260,000 1,170,000 1,170,000 - 3,600,000
ax 2- r_._rt ;ae:;..r"i. 1,000,000 260,000 1,170,000 1,170,000 - 3,600,000
Rowe! s Manna Waterfront Park 5,000,000 - 5,000,000 - - - 5,000,000
P°:a ^,eS
304 - I.•rraz -,cve lee: ;.m. 5,000,000 - - - - 5,000,000
Dernste.n Park 3,232,000 6.599 275,401 1,475,000 1,475,000 - - 3,225,401
:3:- M: 1°e=eator *Dacia: 25401 - - - - 25 401
304 - •enta+.c.ne ;sic ;.o.t.. 250,000 1,475.000 1. - 5. 000 - - 3.200 000
Total Protect Revenues 275,401 1,475,000 1,475,000 - - 3,225,401
Bay Point Park 60,350 45,350 15,000 - - - 15,000
:3: ►vs: L ae=tst or 'roac'r. 15,000 - - - 15,000
Capital Improvements Element 20 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upuate
Budget As of 9/30/13 FY 2011 FY 2015 FY 2016 FY 2017 FY 2018 Total
8.8 Copp.tt Park 20,000 - 20,000 - - - 20,000
Rc.c ^;s:
_3. -'vs: t Re7at er ,Dedc rt. 20,000 - - - - 20,000
Old Seven Mde Brodie 2,700,000 1,350,000 1,350,000 - - 2,700,000
sc:•^.,s:
3 '.."1.2---G=' %c 1,350,000 1,350,000 - - - 2,700,000
14 Poe s.avn.vn8rope 2,000,000 - - 600,000 1,400,000 2,000,000
Rs:s
304 - -r 2 .. ? w c :..r s. Pool eta - - - 500 000 500.000 1.000 000
tee `
-
100 000 900.000 1 000
Total Project Revenues - - - 600,000 1,400,000 2,000,000
Boson( Improvement Fund Projects
e.- ue sec loot ■a +t 219,831 24.831 225.000 - - - - 225 000
erzhrr Sr,' : ew, ert ttw 67,000 67,000 - - - - 67 000
a:e V to bet 411 ■ _tte'ra . e, 25,000 25,000 - - - - 25 000
Be'. r-t:tet BE It-c 5,000 5,000 - - - - 5 000
•x.r 1 :6xt q^c 250,000 250,000 - - - 250 000
-or-, - e^+: ev% eoet'a 68,000 68,000 - - 68 000
:.rset sartM Low q-u •e..srso, 25,000 2 5,000 - - - 25 000
r•A t c F+Att PW2.4T7M .J%ADO,eE sm a 719,416 24,950 200,050 : 350 - '24466
Total Bosons Improvement Project Revenues 1,439,247 49,781 865,050 174,116 350,000 - 1,389,466
Psa ^,,ss
r Ics nr, - cro.e c.i+c 865,050 174,416 350,000 - - 1,389,466
Total 18,067,097 106,730 8,535,951 3,259,416 2,995,000 1,770,000 1,400,000 17,960,367
Capital Improvements Element 21 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
I Land Development & land Acquisition (Goof 105, ONeaives 101.6 & 102.4)
Project Title Project Appropnoted
Budget As of 9/30/13 FY 2011 FY 2015 FY 2016 FY 2017 FY 2016 Total
Monroe County land Authority -
Land Acau s�to, --Fi Revs £C5( 3,276,027 3,276,027
POGO Reserve: 4.274,123 - - - 4.274,123
Total 7,550.150 - - - - 7,550,150
RevMNea
Tourat Impact Ta. 950,000 950,000
State park Surcharge 360,000 360,000
Monroe County Lana Authorty F,,nd Balance 6,240,150 6,240.150
To Revenues 7,550,150 - - - - 7,550,150
Total 7,550,150 - - - - 7,550,150
Capital Improvements Element 22 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan _ Lte
General Government
1
Project Title Project Appropnated
budget As of 9/30/13 FY 2014 Fr 2015 FY 2016 FY 2017 Fr 2018 Total
■
General Government Function Projects
Lester 6udd.n4 Roof Replacement 339,405 289,405 50,000 - - - - 50,000
Pa. a ^.es
331 zx ^ ;Ise: ;.ray 50,000 - - -
rn 50,000
leffe.son Browne 6401dn1 Rehabd.utton 6,000,000 - 600,000 5,400,000 - - - 6,000,000
3.3 Dr_- ►xeet: 600,000 5,400,000 - - 6,000,000
Varwut ►tsbbc Worts Prefects 1,440,183 111,813 3,249,907 775,463 - - - 4,025,370
pa ' "'ny_'�l.re %K = :vta. 3,249,907 775,463 - - - 4,025,370
Tot.t-Gener&GetrenwnentFunction 10,779,588 704,218 3,899,907 6,175,463 - 10,075,370
Publsc Safety Function Projects
MCDC Spr.nkler P p.n4 Replacement 308,575 37,451 271,124
-
-
-
- 271,124
Pe.4-_es
304 - rts.. r :at: :arts, 271,124 - - 271,124
Fire /EMS Vehicle Replacement 1,975,000 - 1,000,000 975,000 - - - 1,975,000
Pa.r.e:
31.14 - ^'*1x ^r_ve :sie: Zu'ts. 1,000,000 975,000 -
1 Capital Improvements Element 23 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Key Largo tore Vague le & Hydrants 250,000 - 250,000 - - - - 250,000
ps. s'_f.
■
All n*a2 ^ JCVi;ae: ira. 250,000 - - - - 250,000
Stock bland Fore Stat.on 4,574,013 4,116,665 457,348 - - - 457,348
P.:• Jes
301 -Der. • 457,348 - - . 457,348
Conch Key Fire Staton 2,363,446 2,353,446 10,000 - - - - 10,000
301 - Dec ►'%tea• 10,000 - - - - 10,000
Summational Key Fore 5tatoon 4,500,000 - - 450,000 3,000,000 1,050,000 - 4.500,000
3:3'x' • ,. - 450 3,000,000 1,050,000 - 4,500,000
Fore Traomn4 Academy -Crawl Key 1,200,000 1,200,000 - - - - 1.200.000
Fs. " -s:
3:3 - x- • 1,200,000 - - - - 1,200,000
Tota4-Publ.c Safety Function 15,171,031 6,507,562 3,188,472 1,425,000 3,000,000 1.050,000 - 8,663,472
Physical Environment Function Projects
Canal Master Plan 5,000,000 47,500 1,650,000 1,650,000 1,652,500 - - 4,952,500
Cs: s '_s:
30+- r^az - J- _re sae: Ara, 1,650,000 1,650,000 1,652,500 - - 1,952,500
Culture & Recreation Function Projects
Library Automaton Update 175,000 128,703 25,000 21,297 - - - 46,297
Capital Improvements Element 24 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan upudte
budget As of 9/30/13 FY 2014 FY 2015 FY 2016 FY 2017 FY 201E Total
Pc.•!_,c:
:3: uW'C ,-dect gec 25,000 21,297 - - - 46,297
Marathon library 3,000,000 - 300,000 2,400,000 300,000 - - 3,000,000
Pa. is _ to:
1.3 - De^_"' «fete 300,000 2,400,000 300,000 - 3,000,000
Total Culture & Recrnt.on Fu nctson 3,175,000 128,703 325,000 2,421,297 300,000 - - 3,046,297
Court Related Funct on Protects
Marathon Courthouse 1,752,023 1,716,523 35,500 - - - - 35,500
3w ax ^.e_re r e: ;..rts. 35,500 - -
35,500
Freeman lusuce Center 20,618,230 20,027,330 590,900 - - - - 590,900
Pc:•rae:
lor' I rice ^. u'e ;M!: uur 590,900
-
-
- - 590,900
Freemen Justice Center lobby Espensron 334,346 175,508 158,838 - - - - 158,838
Ps.'- -c:
1St - aZ^.,:: _re :ae :xis, 158,838 - - - - 158,838
PK Courthouse & hod 10,600,000 1,060,000 4,770,000 4,770,000 - - 10,600,000
"c.c'_
3.3 Dec-.. 1,060,000 4,770,000 4 - - 10,600,000
Total Court Related Function 33,304,599 21,919,361 1,845,238 4,770,000 4,770,000 - - 11.385,238
Total 67,430,221 29,307,34.4 10,908,617 16,441,760 9,722,500 1,050,000 38,122,877
Capital Improvements Element 25 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Obiective 1401.2
With the following exceptions, County public expenditures within the Coastal High
Hazard Area (CHHA) shall be limited to the restoration or enhancement of natural
resources and parklands, expenditures required to serve existing development such as the
maintenance or repair of existing infrastructure, and expenditures necessary for public
health and safety:
1. County public expenditures within the CHHA may be permitted where required to
meet adopted level of service standards or to maintain or reduce hurricane
evacuation clearance times and where no feasible alternatives to siting the
required facilities within the CHHA exist.
2. County public expenditures within the CHHA may be permitted for
improvements and expansions to existing public facilities, which improvements or
expansions are designed to minimize risk of damage from flooding. {93-
016(-3-)( }
Peiiey- lE401:34-
5.016(3)(c)1 and 91
Policy 1401.2.21
No County public expenditures shall be made for new or expanded public
facilities in areas designated as units of the Coastal Barrier Resources System,
undisturbed saltmarsh and buttonwood wetlands, or offshore islands not currently
accessible by road, with the exception of expenditures for wastewater systems.,
expenditures for conservation and parklands consistent with natural resource
protection, and expenditures necessary for public health and safety. {93-
5 016(3)0- and-91
<The Remainder of This Page Intentionally Left Blunk>
Capital Improvements Element 26 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Objective 1401.3
Monroe County shall ensure that future development pays its proportionate share of the
costs of improvements necessary to serve new development at the adopted level of
service standards. [9J 5.016[& 163.3177(3)(b )4}a)3., F.S.j
Policy 1401.3.1
By January 4, 1997, Monroe County shall adeptrevise and update the Land
Development Regu'atio n •which a ~dCode to update the County's current
expenditure procedures and proportional fair share assessment of impact fees, in
accordance with the adopted levels of service referenced in Policy 1401.4.1. The
revised Land Development RegulatiensCode shall also include provisions for the
collection of impact fees to offset the public costs of public facilities and services.
{ 5406 }
<The Remainder of This Pajre Intentionally Left Blank>
Capital Improvements Element 27 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Objective 1401.4
Monroe County shall coordinate land use decisions and fiscal resources with a schedule
of capital improvements in order to maintain the adopted level of service (LOS) standards
for bother issued development orders and future development. f 9J-
5- 016f$163.3177(3)(ba)3 and 5]., F.S.1
Policy 1401.4.1
Monroe County shall adopt and maintain level of service (LOS) standards for the
following public facility types: roads, sanitary sewer, solid waste, drainage,
potable water, and parks and recreation. The LOS standards are established in the
following sections of the Comprehensive Plan:
1. The LOS for roads is established in Traffic Circulation Policies} 301.1.1
and 301.1.2;
2. The LOS for potable water is established in Potable Water Policy 701.1.1;
3. The LOS for solid waste is established in Solid Waste Policy 801.1.1;
4. The LOS for sanitary sewer is established in Sanitary Sewer Policy
901.1.1;
5. The LOS for drainage is established in Drainage Policy 1001.1.1; and
6. The LOS for parks and recreation is established in Recreation and Open
Space Policy 1201.1.1. [9J 5.016(3)(c)1]
Policy 1401.4.2
Monroe County shall adopt a Capital Budget at the same time it adopts its Annual
Operating Budget. The Capital Budget shall include those projects necessary to
maintain the adopted levels of service referenced in Policy 1401.4.1. f9-J-
541-6
Policy 1401.4.3
To the extent allowed by Florida Statutes, Monroe County supports the use of
tourist- related charges to offset tourist- related impacts on public facilities.
Monroe County supports the use of Tourist Development Council funds to
provide public facilities that will serve both tourists and residents.
Policy 1401.4.4
Public facilities and services needed to support development shall be available
- : • _ . - = • . • • - • • • :: - : : = :: - - , in accordance with the adopted
levels of service referenced in Policy 1401.4.1 and Chapter 9J 5.0055,
Development approval may be phased to allow the provision of public facilities
and services necessary to maintain the adopted levels of service. 1-9J .
5 x( 3 )(c) 6 ]
Capital Improvements Element 28 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Policy 1401.4.5
Monroe County hereby adopts a Concurrency Management System to ensure that
facilities and services needed to support development are available concurrent
with the impact of development. The Concurrency Management System shall
ensure that the County shall issue no development order or permit which results in
a reduction in the level of service (LOS) below the adopted LOS standards
referenced in Policy 1401.4.1 for those public facilities that are subject to the
system. The guidelines established in Policies 1401.4.6, 1401.4.7, 1401.4.8,
1401.4.9, and 1401.4.10 shall ensure that concurrency is successfully
implemented.
Policy 1401.4.6
The following guidelines identify the stages in the development review process
when the test for concurrency must be met.
1. Preliminary Development Order Stage - A preliminary development order
is a development order that precedes the issuance of a building permit,
such as a subdivision plat, development plan, certificate of compliance,
conditional use permit, or development of regional impact development
order. A proposed development must receive a conditional concurrency
determination prior to receiving a preliminary development order.
2. Final Development Order Stage - A final development order is a building
permit or any other development permit authorizing the construction or
expansion of a structure, an increase in development intensity, or
a change of use requiring a new certificate of occupancy. A proposed
development must receive a final concurrency determination prior to
receiving a final development order.
Policy 1401.4.7
The following guidelines identify the effect of a concurrency determination::
1. A Conditional Concurrency Determination shall indicate that adequate
public facilities are available at the time the determination is issued, but
shall not guarantee the adequacy or availability of public facilities at
subsequent stages of development review.
2. A Final Concurrency Determination shall indicate that adequate public
facilities will be available at all subsequent stages of development stages
of development review, subject to certain limitations such as elapsed time
and the payment of fees.
Capital Improvements Element 29 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Policy 1401.4.8
The following guidelines identify the minimum criteria necessary to meet the
concurrency requirements of each public facility type.
1. The concurrency requirements for roads, potable water, solid waste,
sanitary sewer, and drainage facilities and services shall be satisfied if one
or more of the following conditions are met:
a) the necessary facilities and services are in place at the time a
development permit is issued; or
b) the necessary facilities and services are in place at the time a
certificate of occupancy, or its functional equivalent is issued.
b) thc dcvclopmcnt permit is issucd subjcct to thc condition
is-issueder
d) an enforceable dcvclopmcnt agrccmcnt guarantees that the
may include, but is not limited to, dcvclopmcnt agreements
pursuant to scction 163.3220, F.S., or an agrccmcnt or
2. The concurrency requirements for recreational facilities shall be satisfied
if one or more of the following conditions are met:
a) conditions 1(a) or 1(b), or 1(c) listed above or, in the case of
acreage for parks and recreational facilities, which shall be
dedicated to or acquired by the County prior to issuance of a
building permit, or funds in the amount of the developer's fair
share are committed no later than the approval to commence
construction; or
e)b) an enforceable development agreement guarantees that the
necessary facilities and services will be in place within one y° r of
with the issuance of the applicable development permit. An
enforceable development agreement may include, but is not limited
Capital Improvements Element 30 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
to, development agreements pursuant to section 163.3220, F.S., or
an agreement or development order issued pursuant to Chapter
380, F.S.
3. The concurrency requirements for roads shall be satisfied if one or more of
the following conditions are met:
a) conditions 1(a) or 1(b) listed above; or
b) a binding executed contract is in place at the time the development
permit is issued which provides for the commencement of the
actual construction of the required facilities or provision of
services; or
c) an enforceable development agreement guarantees that the
necessary facilities and services will be in place with the issuance
of the applicable development permit. An enforceable development
agreement may include, but is not limited to, development
agreements pursuant to section 163.3220, F.S., or an agreement or
development order issued pursuant to Chapter 380, F.S.
Policy 1401.4.9
The following guidelines identify the minimum components of the County's
concurrency monitoring system.
1. The County shall maintain a database of permitting data that includes the
amount of development for which final development orders have been
issued, development for which final development orders have expired,
development which is under construction, and development which has
been constructed.
2. The County shall maintain a database of public facility data that includes
the capacity of existing public facilities, the additional capacity created by
facility improvements, the impacts of existing development, and the
impacts anticipated due to committed development.
3. The County shall prepare a :.- :, .• .: : - ..- - - - ' - :.. _ .. - - Public
Facilities Capacity Report assessing the capacities of all public facilities
subject to the Concurrency Management System. The Concurrency
Management Report shall be used to monitor changes in the capacity of
public facilities and the levels of service provided by the facilities based
upon development activities and capital improvement projects completed
Policy 1401.4.10
Capital Improvements Element 31 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Monroe County shall use the following guidelines for interpreting and applying
level of service standards to development order applications. For the purposes of
this policy, reserve capacity refers to the capacity of existing public facilities plus
the capacity of public facilities which do not exist but which meet the applicable
requirements of Policy 1401.4.7, less the existing demand for those facilities and
the demand expected to be created for those facilities by approved but unbuilt
development as determined by the databases in Policy 1401.4.9.
1. Potable Water- The County shall not render a final concurrency
determination unless the quantity of water available under the FKAA
Consumptive Use Permit meets or exceeds the estimated water demand of
the proposed development together with the estimated water demand of all
existing and committed development.
2. Solid Waste - The County shall not render a final concurrency
determination unless capacity available at solid waste facilities either
under contract with Monroe County meets or exceeds the
estimated daily solid waste generation of the proposed development
together with the estimated daily solid waste generation of all existing and
committed development for a period of three (3) years from development
approval.
3. Sanitary Sewer- The County shall not render a final concurrency
determination unless the proposed development will be served by a
treatment plant permitted by the
D~RFDEP with adequate reserve capacity to accommodate the
impact of the proposed development or an on -site sewage disposal system
permitted by the ` = .. - . - . - ' - .. • • • • - - _ • - _ DOH.
4. Drainage- The County shall not render a final concurrency determination
unless the proposed development will be served by stormwater
management facilities approved by the South Florida Water Management
District; or has received an individual construction permit or written
authorization to proceed pursuant to a general permit from the South
Florida Water Management District. If the proposed development requires
a permit from the South Florida Water Management District, such permit
must be obtained prior to the final concurrency determination or the
applicant's drainage plans must be consistent with Monroe County's
stormwater management requirements.
5. Parks- The County shall not render a final concurrency determination
unless the park facilities either in existence or programmed within the next
year will meet or exceed the estimated park demand of the proposed
development together with the estimated park demand of all existing and
committed development. Within each impact area for park facilities, the
County shall determine the population capacity of both resource -based and
Capital Improvements Element 32 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
activity -based facilities by multiplying the level of service standard by the
number of acres of existing or programmed parks.
6. Roads- The County will not render a final concurrency determination
unless the estimated traffic impacts of the proposed development, together
with the estimated traffic impacts of all existing and committed
development, will not exceed either the segment or overall reserve
eapfteitythe level of service of U.S. 1, as determined by the U.S. 1 Level of
Service Task Force Methodelegymethodology. The trip assignment for
proposed developments with an estimated trip generation rate of more than
10 trips per day shall be based on a traffic impact report prepared by the
developer based on a professionally accepted methodology. The trip
assignment for proposed developments with a trip generation rate of 10
trips or less (such as a single family home) shall be limited to the segment
of U.S. 1 most directly impacted by the development.
Policy 1401.4.11
Annual debt service on Monroe County's direct debt shall not exceed the
following annual median ratios for medium size counties published by Moody's
Investment Services:
1. debt to operating revenue;
2. debt to assessed valuation; and
3. debt per capita.
Moody's Investment Services, a bond rating agency, publishes annual medians
depicting local governments' debt service as a percentage of population, operating
revenue, and assessed valuation. [9J 5.016(3)(c)2}
•
• • .
Sanitary Sewer Policies 901.1.7 and 901.1.8).
Policy 1401.4.4 - 312
By January '1, 1997, Monroe County shall revise the Comprehensive Plan Five -
Year Schedule of Capital Improvements and the County Capital Improvements
Program annually to include funding for any improvements required to provide
for solid waste disposal after expiration of the current solid waste haul out
contract (See Solid Waste Objective 801.3 and related policies).
Capital Improvements Element 33 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Master Plan which shall be implemented beginning in Fiscal Year 1999. Prior to
required by the Stormwater Management Master Plan Note: Monroe County
recognizes its obligations under the stipulated sctticmcnt agreement but
date prcmiscs.
..• -- ...
The County shall coordinate with the FKAA, the Florida Departments of
Environmental Regulation (DER) and Health and Rehabilitative Services (HRS),
and the U.S. Environmental Protcction Agency (EPA), at a minimum, concerning
joint preparation and funding of the Master Plan. Note: Monroe County
recognizes its obligations undcr the stipulated sctticmcnt agrccmcnt but
practicality of timcframe implementations may require modifications of
agreement date prcmiscs.
Policy 1401.4.13
Monroe County shall revise the Comprehensive Plan Five -
Year Schedule of Capital Improvements and the County Capital Improvements
Program annually to include funding for the improvements identified in the
Sanitary Wastewater /Stormwater Management Master Plan.
P 140 17
expanding the Card Sound Road and Toll District to include CR 905 on North
ego and US 1 between the Dade County line and CR 905.
<The Remainder of This PaLe Intentionally Left Blank>
Capital Improvements Element 34 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015
Monroe County Comprehensive Plan Update
Obiective 1401.5
Monroe County shall provide public facilities sufficient to maintain adopted level of
service standards that are within the ability of the County to fund, or within the County's
authority to require others to provide. Evaluation of funding alternatives for
improvements identified in other plan elements will include consideration of
improvements required by existing versus future development in order to ensure a fair -
share allocation of costs. [9J 5.016f $163.3177(3)(b)5 }a), F.S.]
Policy 1401.5.1
The estimated capital expenditures for all needed public facilities shall not exceed
conservative estimates of revenues from sources that are available to the County
pursuant to current law, and which have not been rejected by referendum, if
referendum is required to enact a source of revenue. [9J 5.016(3)(b)5]
Policy 1401.5.2
Monroe County shall not provide a public facility, nor shall it accept the provision
of a public facility by others, if it is unable to pay for the subsequent annual
operating and maintenance costs of the facility. {9J 5.016(3)(b)5]
Policy 1401.5.3
Monroe County's Capital Improvements Program shall be monitored in
conjunction with the evelopment review process to
ensure that the County is not required to construct improvements beyond its
financial capacity. [93- 57016(3)(b)54
<The Remainder of This Page Intentionally Left Blank>
Capital Improvements Element 35 Keith and Schnars, P.A.
Comprehensive Plan: Jan. 2015