24th Change Order 10/17/2018GJ Z COURTS °
o:
Kevin Madok, CPA
.... Y1
Clerk of the Circuit Court & Comptroller — Monroe Count Florida
•R OE COUN
DATE: October 26, 2018
TO: Beth Leto, Airports
Business Manager
FROM: Pamela G. Hancock, D.C.
SUBJECT: October 17' BOCC Meeting
Attached is an electronic copy of Item C18, Change Order 24 with OAC Construction
Corp., increasing contract time by 60 days, to October 31, 2018, for the Key West International
Airport Customs Facilitv Phase II Project, funded 50% by FDOT grant AQH10 and 50% Airport
Operating Fund 404, for you handling.
Should you have any questions, please feel free to contact me at (305) 292 -3550. Thank
you.
cc: County Attorney_
Finance
File
KEY WEST MARATHON PLANTATION KEY
500 Whitehead Street 3117 Overseas Highway 88820 Overseas Highway
Key West, Florida 33040 Marathon, Florida 33050 Plantation Key, Florida 33070
305 - 294 -4641 305 - 289 -6027 305 - 852 -7145
PK/ROTH BUILDING
50 High Point Road
Plantation Key, Florida 33070
305 - 852 -7145
MONROE COUNIY /ENGINEERING /PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 24
Key West Airport Customs Facility
Phase 11 Renovations
INITIATION DATE: October 1, 2018
TO CONTRACTOR: CONTRACT DATE:December 09, 2015
OAC Action Construction, Corp. a ,
11980 SW 144 Ct, Suite 101 0 m .... -- n
Miami, FL 33186 a C. c r"
The Contract is changed as follows: rr:m PO.- -r:
;.y 7:! Cis
CD CY 73
The original (Contract Sum) (Guaranteed Maximum Price) %1; 12,50 . 0 :
Net change by previously authorized Change Orders - $£8,3,720. 1. c
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was I:17696,2201
3:
The (Contract Sum) (Guaranteed Maximum Price) will be (increased)_(decreased) `'
(unchanged) by this Change Order Y $ 0.00
The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is $1;696,220.81
The Contract Time will be (increased) (decreased) (unchanged) by 60 days.
The date of Substantial Completion as of the date of this Change Order is .......... Ocober 31, 2018
Detailed description of change order and justification:
This change order is for unforeseen delays due to the review of plan revisions still pending at the building
department.
This change Order is 0.00% of the original contract price.
Not valid until signed by Owner, Architect (if applicable), and Contractor
ARCHITECT: „.,,.../,Z7 ' � E eA A Ee. , u AC�,�� tc /Z( l$
K2M /•. Date
CONTRACTOR: I / fib/ s 2._
0. O .n n Co r Corp. Date
(r
, Wit^ -°.
a D(� F F AIRPORTS
r?t � w t, - A / Date
t `�(5Ek % ;
D ES' KEVIN MADOK, CLERK ✓ �',,
e Mayor /Chai ' ''- Date
Deputy Clerk �n
PNROE /"' .,/
APPA • ' ` a 'TT F�
D A I' ," COUNTY ATTORNEY l l) /� // is
Change Order Attachment per Ordinance No. 004 -1999
• Change Order was not included in the original contract specifications. Yes No
If Yes, explanation:
This is system and application was not part of original design.
• Change Order was included in the original specifications. Yes No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater).Yes No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes No
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes No
Should a claim under the applicable professional liability policy be made? Yes No
Explain: