3rd Change Order 12/04/2018 ONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 3
Demolition of Old, and Installation of New
Transfer Station Offices INITIATION DATE: November 19, 2018
TO CONTRACTOR: CONTRACT DATE: May 17, 2017
Pedro Falcon Contractors, Inc.
31160 Avenue C Contractors Change Order Request: 004
Big Pine Key, Florida 33043
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)................................$1,105,410.00
Net change by previously authorized Change Orders.................................. .... $ 0.00
The (Contract Sum) (Guaranteed Maximum Price)prior to this Change order was..$1,105,410.00
The (Contract Sum) (Guaranteed Maximum Price)will be(Increased)(decreased)
(Unchanged)by this Change Order.. $ 0.00
The new(Contract.Sum) (Guaranteed Maximum Price)including this Change Order
$ 1,105,410.00
The Contract Time will be (increase (decreased)(unchanged)by............. .......... 164 Days
The date of Substantial Completion as of the date of this Change Order is ---,—April 4, 2019
Detailed description of change order and justification:
s cdU iT 1' s " c trailers from the manufacturer
l , 1 dg it e lryi . _a4cl IL'on°dly
order to minimize the l ac t ... v a�t� �o lon l ad,itgM C'u�o
&1iM1rom Bebco fildus rles
in rev," ..j ` 0 A ' n1Ja mi
z r ti wt p d Rail °At : , on , " ltl�with He Indusl M r gcit rat .
Icj g—dAkionA'_osJ aecring nulgo . DMtLi a:t't0_m
This chanqe Order is / of tbg on inal contract price.
Not valid until slaned by Own ar Arc lkact i ll en Dorttractor
ARCHITECT:
Avon Mod la�" „,�— , Date
CONTRACTOR: �a .
e ro corn Con r , I Date
PROJECT MANAGEMENT: 4
Ca ght Date
R: --
COUNTYIASSISTANT ADM INISTRATO
Ro an , stesl Date
in Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation:
The Cudjoe Key site ramp and rail system were revised from Babco Industries, or
equal, to a local shop fabricated ramp and rail system. Continuing with Babco Industries
would create even longer delays. Hurricane Irma originally impacted scheduled delivery
of the office trailers from the manufacturer, and subsequent scheduling installation.
Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater).Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Request for Change Order
Revised
27 November 2018
Project: Deniolitiog and Installation of New Transfer Offices
Change Order Request No: PCO - 004
Description: No C'ost 'fitne Extension Due to Hurricane Irma Related Delay�s
Mutt I— Extend Contract Substantial Completion rain 22 October 2018 to 04,4ttL t
2019 Due to Hurricane Irma Scheduling Dely
Hurricane Irma impacted scheduled delivery of office trailers from the Manufacturer and
subsequent scheduling installation. Additionally, in order to minimize the impact to
overall completion, long lead item (Cudjoe Key Site Ramp and Rail System from Bebco
Industries) is being revised to a local shop built system matching the specified pre-
manufactured Ramp and Rail System. No engineering included for shop built matching
Ramp and Rail System
NetAmount of Request for Change Order:........................................................$0.00
Additional Time Requested for Change:
164 Calendar Days for Substantial Completion.
Respectfully Submitted,
Ken Bygler
Project Manager
I I P a g e