Marathon Annex 1st Change Order 11/30/2018 oNROE CouNTYIENGiNEERiNGI PROJECT MANAGEmENT CONTRACT CHANGE ORDER PROJECT TITLE: Marathon Annex Mold Remediation INITIATION DATE: 07116/2018 CHANGE ORDER NO: 1 TO CONTRACTOR: Global Disaster Recovery CONTRACT DATE: 02/12/2018 1333 Overseas Hwy Marathon FL 33050 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)............................................$48,751.17 Net change by previously authorized Change Orders................ ..................................$0 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$48,751.17 The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased) (unchanged) by this Change Order.......$17,270..62 The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is.......$66,021.79 The Contract Time will be (increased) (decreased) (unchanged) by............................--,0 days The date of Substantial Completion as of the date of this Change Order is......................... May 11, 2018 Detailed description of change order and justification: Corttr, ctor was rec tared to rerrrove traore water ttama, ct material in order to reach clear report as re rtr (J by the in yr trial hW,ienist, hQmtm l f MQ Qriginatcontract orice, of valid until signed, by Owner Architect fif applicable), and Contractor ARCHITECT: A Date CONTRACTOR: zl��' k D�µ e mm... DIRECTOR PROJECT MANAGEMENT ate COUNTY/ASSISTANT ADMINISTRATORS ��� Ro n Gdstesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 Change Order was not included in the original contract specifications. Yes® No❑ If Yes, explanation: More water damaged parts of the building were discovered once mold remediation began. Contractor was required to demolish and haul away damaged kitchen and drywall in portions of the building that were discovered to be water damaged once the work began. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes❑ No If no, explanation of why: No Architect of record on this project. • Change Order is correcting an error or omission in design document. Yes❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: y Global Disaster Recovery Inc. Invoice P,O, Box 500493 Marathon FI 33050 = 7/20/2018 13149 Phone# globaldisasterrecovery@hotmail.com ..m. n_w.,._w...._ ..,..m.W Fax# 1-305-742-2767 www.gdreat.com rr MonroelllCounty Annex 500 Whitehead Street 63rd i Key West, FL 33040 ........... ......................... .......... Due on receipt 1 Cont: Clean-General Items 2,091.52 2,091,52 1 Cleaning 3,442,10 3,442,10 1 Content Manipulation 147.62 147.62 1 General Demolition 1,914.24 1,914,24 1 Hazardous Material Premeditation 2,800.14 2,800.14 1 Water Extraction & Remediation 6,875.00 6,875.00 See Attached Spreadsheet Total $17,270.62 Payments/Credits $0 00 Balance Due $17,270.62 Client: Anex Buidling Home: (305)299-6088 Property: 490 E 63rd Street Ocean Marathon,FL 33050 Business: 490 E 63rd Street Ocean Marathon,FL 33050 Operator: PAUL Estimator: Alex Sweeney Business: (305)896-1949 Position: Project Manager E-mail: Alexsweeney84@gmail.com Business: 133330 Overseas Hwy Marathon,FL 33050 Type of Estimate: Hurricane Date Entered: 7/16/2018 Date Assigned: Date Est.Completed: 7/20/2018 Date Job Completed: Price List: FLKW8X MAR18 Labor Efficiency: Restoration/Service/Remodel Estimate: ANEXMARATHON This work order change Its for the additional work performed during the remediation process at the 63rd st Annex.The additional areas found within the estimate were performed outside of the original scope of work in order to insure the proper remediation of the building.If you have any questions or concerns please contact Paul Sweeney at(305)481-4885. CONTINUED-Break Area/Room DESCRIPTION QTY UNIT PRICE TOTAL Tear out wet drywall,cleanup,bag-Cat 3 176.50 SF @ 1.30= 229.45 Partial Ceiling and wall drywall removed Cat 3 affected material. Remove Cabinetry-lower(base)units 24.00 LF @ 8.27= 198.48 Lower cabinetry removed. Cat 3 affected material. Remove Countertop-flat laid plastic laminate 24.00 LF @ 4.75= 114.00 Countertop removed. Cat 3 affected material. Clean more than the ceiling-Heavy 573.00 SF @ 0.36= 206.28 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean stud wall-Heavy 176.50 SF @ 0.86= 151.79 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean floor-the-Heavy clean 265.50 SF @ 0.68= 190.54 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 3.00 EA @ 7.65= 22.95 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Apply anti-microbial agent to more than the floor 1,015.00 SF @ 0.32= 324.80 Antimicrobial application require to prevent further microbial growth. Hallway Height:8' Door 2' 10"X 6'8" Opens into HVAC_ROOM Door 3'X 6'8" Opens into MEN_BATHROOM Door 3'X 6'8" Opens into JANITORIAL_C Door 3'X 6'8" Opens into WOMAN_BATHRO Door 3'X 61811 Opens into BREAK_AREA_R Missing Wall 5' 10"X 8' Opens into Exterior Door 3'X 6' 8" Opens into Exterior Missing Wall 5' 10"X 8' Opens into Exterior Door 3'X 61811 Opens into OFFICE_1 DESCRIPTION QTY UNIT PRICE TOTAL w .. ...._ ................. _ .. .. .......... Containment Barrier/Airlock/Decon.Chamber@ 120.00 SF 1.00— 120.00 ANEXA TON 7/20/2018 Page:3 CONTINUED-Office I DESCRIPTION QTV UNIT PRICE TOTAL Clean floor-the-Heavy clean 222.40 SF @ 0.68= 151.23 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 3.00 EA @ 7.65= 22.95 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Apply anti-microbial agent to more than the floor 882.12 SF @ 0.32= 282.28 Antimicrobial application require to prevent further microbial growth. Mechanical Room Height:81 Door Y X 61 811 Opens into Exterior DESCRIPTION QTY UNIT PRICE TOTAL ........................................... --------------- Containment Barrier/Airlock/Decon.Chamber 21.00 SF @ 1.00= 21.00 Critical require to prevent cross-contamination&as a means of dust control. Peel&seal zipper-heavy duty 1.00 EA @ 15.12= 15.12 Critical require to prevent cross-contamination&as a means of dust control. Tear out wet all,cleanup,bag-Cat 3 60.00 SF @ 1.30= 78.00 Partial Ceiling and wall drywall removed. Cat 3 affected material. Clean more than the ceiling-Heavy 135.24 SF @ 0.36= 48.69 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean stud wall-Heavy 60.00 SF @ 0.86= 51.60 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean floor-the-Heavy clean 32.57 SF @ 0.68= 22.15 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 2.00 EA @ 7.65= 15.30 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Apply anti-microbial agent to more than the floor 227.81 SF @ 0.32= 72.90 Antimicrobial application require to prevent further microbial growth. Remove wet ceiling tile&drywall and bag-Cat 3 16.28 SF @ 1.60= 26.05 Partial Ceiling Tile removed Cat 3 affected material. ANEXMARATHON 7/20/2018 Page:5 Men Bathroom Height:8' Door Y X 6'8" Opens into HALLWAY DESCRIPTION QTY UNIT PRICE TOTAL Clean the walls and ceiling-Heavy 642.00 SF @ 0.36= _231.12 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean floor-the-Heavy clean 198.00 SF @ 0.69= 134.64 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 2.00 EA @ 7.65= 15.30 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Apply anti-microbial agent to more than the floor 840.00 SF @ 0.32= 268.80 Antimicrobial application require to prevent further microbial growth. Janitorial Closet Height:8' Door 3'X 6'8" Opens into HALLWAY DESCRIPTION QTY UNIT PRICE TOTAL Clean the walls and ceiling-Heavy 228.00 SF @ 0.36= 82.08 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean floor-the-Heavy clean 40.00 SF @ 0.68= 27.20 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 2.00 EA @ 7.65= 15.30 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Apply anti-microbial agent to more than the floor 268.00 SF @ 0.32= 85.76 Antimicrobial application require to prevent further microbial growth. Woman Bathroom Height:8' Door 3'X 6' 8" Opens into HALLWAY DESCRIPTION QTY UNIT PRICE TOTAL ..Clean the walls and ceiling-.Heavy � 832.72 SF @ 0.36= 299.78 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean floor-the-Heavy clean 278.06 SF @ 0.68= 189.08 Cleaning require due to Cat 3 microbial contaminates and dust settlement cause by the demolition process. Clean door(per side)-Heavy 2.00 EA @ 7.65= 15.30 ANEA TON 7/20/2018 Page:7 Summary Line Item Total 17,270.62 Replacement Cost Value $17,270.62 Net Claim $17,270.62 Alex Sweeney Project Manager ANEXMARATHON 7/20/2018 Page: 9 Recap by Room Estimate:ANEXMARATHON Area:Main Level 9,699.18 56.16% Break Area/Room 1,776.46 10.29% Hallway 1,784.01 10.33% Office 1 1,198.21 6.94% Mechanical Room 350.81 2.03% Electrical Room 330.45 1.91% Hvac Room 411.69 2.38% Men Bathroom 649.86 3.76% Janitorial Closet 210.34 1.22% Woman Bathroom 859.61 4.98% Area Subtotal: Main Level 17,270.62 100.00% Subtotal of Areas 17,270.62 100.00% Total 17,270.62 100.00% ANEXMARATHON 7/20/2018 Page: ll .......... �14 311 O -Al .411-1 ,fl;,6 0 ki,I Yon ue-Johnnie From: Accounting <gdr@gdreat.com> Sent: Friday, July 20, 2018 1:18 PM To: Yongue-Johnnie Subject: Change order invoice 13149 Attachments: Annex 13149.pdf, ANEXMARATHON_63rd.pdf Johnnie, Please find attached the work change order for the Annex at 63rd. The work order change is for the additional work performed during the remediation process at the 63rd St Annex. The additional areas found within the estimate were performed outside the original scope of the work in order to insure the proper remediation of the building. If you should have any questions, do not hesitate to contact me. Best regards, Whitney Bryant GLOBALI RECOVERY, INC. o Box 500493 13333 Overseas Highway Marathon, FL33050 Office: ( ) 1 - 5 Fax: ( 05) 72- 77 2 r Emergency Response FLOOD * MOLD * FIRE * RE('(),N S'1'R U CT1O N