Historic Courthouse 1st Change Order 11/30/2018 ONROE COUNI'YANGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Old Courthouse Mold Remediation INITIATION DATE: 07/16/2018
CHANGE ORDER NO: 1
TO CONTRACTOR:
Global Disaster Recovery CONTRACT DATE: 05/14/2018
1333 Overseas Hwy
Marathon FL 33050
The Contract is changed as follows:
The original(Contract Sum) (Guaranteed Maximum Price).............................................$89,643.39
Net change by previously authorized Change Orders...................................................$0
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was..............$89,643.39
The (Contract Sum) (Guaranteed Maximum Price)will be(increased) (decreased)
(unchanged) by this Change Order.. —.$1,490.00
The new(Contract Sum)_(Guaranteed Maximum Price)including this Change Order is...,...$91,133.39
The Contract Time will be (increased) (decreased) (unchanged) by..................................0 days
The date of Substantial Completion as of the date of this Change Order is.................... ... Aug 15, 2018
Detailed description of change order and justification:
ntrp~tor Mp
jgood chilled water/ncrla iota above aoastic cafling that wa: /eact/n ,to constant dringing,
Chancyq is 1,6% of the on ina/contract nrica
Not valid until si ned by Owner Are iteot if applicable),and Contractor
ARCHITECT: N/
Date
CONTRACTOR:.
Oat
»
DIRECTOR PROJECT MANAGEMENT m /
Date
COUNTY/ASSISTANT ADMINISTRATOR;
Ro si Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes® No❑
If Yes, explanation:
The condition of the chilled water pipe insulation was discovered after the contractor began drywall
removal. To leave the damaged insulation without new drywall would have caused more damage to
the building due to more condensation.
• Change Order was included in the original specifications. Yes❑ No
i
If Yes, explanation of increase in price:
I
• Change Order exceeds $50,000 or 5% of contract price (whichever is greater). Yes❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes❑ No
If no, explanation of why:
No Architect of record on this project.
• Change Order is correcting an error or omission in design document. Yes❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Global Disaster Recovery Inc. Invoice
Marathon FI, 33050
DBA/Advanced Cleaning System
7/16/2018 13143
Phone# globaldisasterrecovery@hotmail.com ............ .....................•..........._... ..e, w.,.,. .... ...................�.
Fax# 1-305-742-2767 www.gdreat.com
IIIIIIII ��
Monore County
5501 College Road C") R rya
Key West, FI 33040
r
f .......... .. __................ . ...
iiii B"mm'IV
Due on receipt PS
7 Work Order Change to install hangers for the A/C Line
9 Hours of Labor @$110,00 110.00 990.00
1 Materials 500.00 50000
Dates 6123/18-6/24/18
Total $1,490.00
ments/Credits $0 00
ENCIMEMIUBalanceDue
$11,490.00
Yon ue-Johnnie
From: Accounting <gdr@gdreat.com>
Sent: Monday, July 16, 2018 4:02 PM
To: Bensley-Dan;Yongue-Johnnie
Subject: Work Order Change Inv
Attachments: Historic CourtHouse Change Order Inv.pdf
Your invoice is attached. Please remit payment at your earliest convenience.
Thank you for your business - we appreciate it very much.
Sincerely,
Whitney Bryant
GLOBAL DISASTER RECOVERY, INC.
Po Box 500493
13333 Overseas Highway
Marathon, FL33050
Office: (888)818-8858
Cell: (863)233-7222
Fax: (305) 742-2767
24Hr Emergency Response
FLOOD * MOLD * FIRE * R11;CONS TP UCTION,