County Commission Meeting
November 20, 2018
Agenda Item Number: H.1
Agenda Item Summary #4950
BULK ITEM: Yes DEPARTMENT: Budget and Finance
TIME APPROXIMATE: STAFF CONTACT: Julie Cuneo (305) 292-4460
N/A
AGENDA ITEM WORDING: Report of Hurricane Irma finance activity by the Office of
Management and Budget.
ITEM BACKGROUND:
PREVIOUS RELEVANT BOCC ACTION:
CONTRACT/AGREEMENT CHANGES:
N/A
STAFF RECOMMENDATION:
DOCUMENTATION:
Hurricane Irma Project Update November
FINANCIAL IMPACT:
Effective Date:
Expiration Date:
Total Dollar Value of Contract:
Total Cost to County:
Current Year Portion:
Budgeted:
Source of Funds:
CPI:
Indirect Costs:
Estimated Ongoing Costs Not Included in above dollar amounts:
Packet Pg. 1064
H.1
Revenue Producing:
Grant:
County Match:
Insurance Required:
Additional Details:
None
REVIEWED BY:
Tina Boan
Kathy Peters
Board of County Commissioners
If yes, amount:
Completed
Completed
Pending
11/06/2018 8:41 AM
11/06/2018 8:43 AM
11/20/2018 9:00 AM
Packet Pg. 1065
H.1.a
Tina Boan, Sr. Director I Monroe County Budget and Finance
d
m
-a
a
D
N
16
C
Q
V
N
O
IL
Projects Submitted to FEMA as of 10/31/18
Project ID
Date Uploaded
to FEMA Portal
Description of Project
Project Cost
Submitted
Project Cost
Obligated
Payments
Received
MC-13-003 FEMA5072 PW 22
11/14/2017
Force Account Labor 100% Cost Share
$2,701,506
$2,667,614
$1,690,337
MC-13-018 FEMA9657 PW 41
12/1/2017
Temporary Sanitary Facilities 100% Cost Share
$62,005
$60,950
$60,950
MC-13-019 FEMA8880 PW 39
12/1/2017
Fire/Rescue Medical Supplies 100% Cost Share
$110,478
$106,465
$106,465
MC-13-020 FEMA9376 PW48
12/1/2017
Temporary Fencing 100% Cost Share
$25,008
$23,508
$23,508
MC-13-021 FEMA9386
12/1/2017
Satellite Systems 100% Cost Share
$102,586
$50,902
MC-13-010 FEMA11613 PW 164
1/13/2018
Force Account Vehicle & Equipment 100% Cost Share
$611,817
$524,115
$370,678
MC-A-023 FEMA11667
1/13/2018
Higgs Beach Sand Cleanup 100% Cost Share
$62,599
$61,263
MC-13-015 FEMA16549
1/13/2018
Emergency Repairs of Roads and Bridges 100% Cost Share
$11,780
$11,214
MC-13-026 FEMA26503
1/25/2018
Temporary Road Repair 75% Cost Share (labor, road signs,
orange cones, barricades, asphalt and rock)
$66,303
$46,547
MC-13-035 FEMA16038
2/16/2018
Emergency Operations Center 100% Cost Share (materials,
contracts, rentals)
$222,860
MC-13-011 FEMA16035
2/16/2018
Base Camp 100% Cost Share
$6,593,062
MC-A-002 FEMA 9400 PW 2061
2/16/2018
Contract Debris Removal 92% Cost Share
$5,097,357
$4,682,553
MC-13-030 FEMA32556
2/16/2018
Temporary Repairs, Equipment, Materials including Mileage &
Meals 100% Cost Share
$447,721
$344,965
MC-13-028 FEMA 16162
3/22/2018
Sheltering and Evacuation 100% Cost Share
$562,125
MC-13-044 FEMA 37290
3/21/2018
Emergency Operations Support 100% Cost Share
$50,000
MC-13-043 FEMA 34105
3/29/2018
Emergency Operations Center 75% Cost Share (materials,
contracts, rentals)
$121,598
MC-A-014 FEMA38258
4/13/2018
Contract Debris Removal 75% Cost Share
$13,764,152
MC-A-014 FEMA43342
7/6/2018
Contract Debris Removal 77% Cost Share
$7,681,385
MC-13-056 FEMA 41002
4/23/2018
Sheltering and Evacuation 75% Cost Share
$14,394
MC-13-012 FEMA 41018
6/8/2018
Mold Testing & Remediation 75% Cost Share
$1,331,295
MC-E-060 FEMA36054
9/17/2018
Big Pine Key AARP 75% Cost Share
$88,952
MC-E-001 FEMA 36222
10/5/2018
Gato Building 75% Cost Share
$1,530,799
MC-E-072 FEMA 41062
10/16/2018
Fuel Tank & Pumps 75% Cost Share
$3,427
MC-E-070 FEMA 36682
10/19/2018
Monroe Count Detention Center 75% Cost Share
$70,533
MC-E-048 FEMA 36861
10/23/2018
Monroe Count Sheriff Headquarters 75% Cost Share
$1,092,206
MC-F-052 FEMA 36209
10/31/2018
Monroe Count Communication Towers 75% Cost Share
$49,282
$42,475,231
$8,580,094
$2,251,938
G7
O
L
a
C
G7
t
U
Category A: $26,605,493 Category B: $13,034,538 Category E:
$2,835,200
Q
Packet Pg. 1067
Preliminary Cost Estimates by Category as of 10/31/18
FEMA Total Estimate
Category A Debris Removal --Land 92/4/4 Cost Share $5,097,357
Category A Debris Removal --Land 77/11.5/11.5 Cost Share $7,689,385
Category A Debris Removal --Land 75/12.5/12.5 Cost Share $14,103,633
Category A Debris Removal --Marine 75/12.5/12.5 Cost Share $500,000
Category B Emergency & Protective Measures 100/0/0 Cost Share $11,897,403
Category B Emergency & Protective Measures 75/12.5/12.5 Cost Share $1,716,303
Category C Roads & Bridges 75/12.5/12.5 Cost Share $2,195,187
Category D Water Control Facilities 75/12.5/12.5 Cost Share $3,870,000
Category E Buildings & Equipment (Buildings Only) 75/12.5/12.5 Cost Share $10,580,287
Category E Buildings & Equipment (EquipmentNehicles/Content Only) 75/12.5/12.5 Cost Share $1,511,813
Category G Parks, Recreational Facilities & Other Items 75/12.5/12.5 Cost Share $12,329,097
$71,490,465
USDA Natural Resources Conservation Service (NRCS) Emergency Watershed Protection (EWP) Program Grant Total Estimate
Debris Removal --Marine 75/25 Cost Share NRCS $31,721,532
Debris Removal --Marine Technical Assistance 100/0 Cost Share NRCS $2,731,607
(See see slide 10 for complete grant budget)
Florida Keys Stewardship Act Funds Appropriation
$34,453,139
Total Estimate:
Note --estimates are preliminary and do not include mitigation
Insurance Estimated
Proceeds County Portion
$203,894
$884,279
$2,908,739
$619,549
$1, 762, 954
$500,000
$0
$214,538
$274,398
$483,750
$958,943
$111,533
$1,541,137
$6,935,428
County Portion
$7,930,383
$7,930,383
($5,500,000)
$2,430,383
$9,365,811
H.1.a
Items in blue are new or updated estimates. Category E Buildings Only Estimate increased and Insurance Proceeds increased. Estimated County Portion decreased due to insurance payments
Category E Equipment/Vehicles/Content Estimate increased, Insurance Proceeds increased and Estimated County Portion increased.
Expenses by Fund as of 10/31/18
Hurricane Irma Activity by Fund
FY17
FY18
FY19
Actual
Actual
Actual
Actual
Total
Grant Fund - Fund 125
125 �0459110 Personnel
$2,509,179
$686,520
$2,797
$3,198,495
125 0459110 Operating
$3,470,917
$8,183,404
$0
$11,654,321
125 '0459110 Capital
$46,642
$24,551
$0
$71,193
$6,026,738
$8,894,475
$2,797
$14,924,009
Total
Card Sound Road - Fund 401
401 22559 Personnel
$0
$0
$0
$0
401 22559 Operating
$0
$13,175
$0
$13,175
401 22559 Capital
$0
$0
$0
$0
$0
$13,175
$0
$13,175
Total
Marathon Airport - Fund 403
403 635102 Personnel
$30,116
$8,607
$0
$38,724
403 635102 Operating
$3,505
$246,653
$0
$250,158
403 635102 Capital
$0
$25,902
$0
$25,902
$33,621
$281,163
$0
$314,784
Total
Key West Airport - Fund 404
404 630191 Personnel
$77,258
$1,094
$0
$78,352
404 630191 Operating
$28,516
$86,457
$0
$114,973
404 630191 Capital
$0
$5,026
$0
$5,026
$105,773
$92,577
$0
$198,350
Total
MSD Solid Waste - Fund 414
414 40003 Personnel
$49,396
$1,883
$0
$51,279
414 40003 Operating
$1,326,521
$23,581,916
$0
$24,908,437
414 40003 Capital
$0
$0
$0
$0
$1,375,916
$23,583,799
$0
$24,959,716
Total
TOTAL
$7,542,048
$32,865,189
$2,797
$40,410,034
H.1.a
M
a
D
0
a`
Packet Pg. 1069
H.1.a
Estimated Damages Submitted to Insurance as of 10/31/18
Buildings:
Citizen's Property Insurance
Wright National Flood Insurance
Lloyd's of London
Total After Deductibles
Proceeds Received
Estimated Balance
$4)486)213
$1)477)316
$11)058)008
$17)021)537
$ 393579898
$1396639639
Packet Pg. 1070
Estimated Damages Submitted to Insurance as of 10/31/18
Fire Apparatus and Portable Equipment for Fire Rescue:
Volunteer Firemen's Insurance Service, Inc.
Total After Deductibles
Vehicles & Equipment:
Florida League of Cities Total After Deductible
Proceeds Received
Progressive Insurance Total After Deductible
Proceeds Received
Estimated Balance
$560)139
$2909794
$269)345
$41)194
$33)589
$ 1,860
1 860
$ 7,605
H.1.a
Packet Pg. 1071
H.1.a
FEMA Site Inspections on Monroe County Projects
Project
FEMA Site
Inspection Date
Estimated Cost
Big Pine Key Community Park & Sheriff's House
4/2/2018
$3,600,000
Watson Field
4/13/2018
$800,000
Blue Heron Park & Community Center
4/4/2018
$950,000
Harry Harris Park
4/6/2018
$4,000,000
Higgs Beach
4/23/2018
$100,000
Key West Historic Courthouse & Lighthouse
4/26/2018
$200,000
Marathon Government Annex
4/16/2018
$370,000
Marathon Tax Collector
4/11/2018
$600,000
Monroe County Sheriff Headquarters
V 5/29/2018
$1,500,000
Stiglitz Community Center at Watson Park
✓ 4/9/2018
$750,000
Tavernier Fire Station
4/20/2018
$200,000
West Martello & East Martello
4/25/2018
$2,450,000
Middle Keys Facilities --Public Defender/State Attorney Office, Court House, Clerk of the Court, Ruth Ivans Health Center, Senior
Center, Medical Examiner, Government Center, Animal Shelter, Public Works/Fleet, Marathon Library
✓ 4/17/2018
$538,700
Veteran's Park
4/19/20181
$1,250 000
a
a
H.1.a
FEMA Site Inspections on Monroe County Projects
Project
FEMA Site
Ins ection Date
Estimated Cos
Boat Ramps --State Rd 4A, Big Coppitt, Geiger Key, Blimp Road, Koehn's Avenue, Sunset Point Park
4/24/2018
$94,485
Key West Airport
5/1/2018
$263,200
Gato Building
5/7/2018
$750,000
Marathon Airport
5/8/2018
$1,380,000
Lower Keys Parks --Pines Park, Bay Point Park, Fireman's Park, Wilhelmina Park and Boca Chica Beach
5/8/2018
$118,230
Transfer Stations --Lon Key and Cud'oe
5/9/2018
$110,000
Lower Keys Facilities --Fleet Garage, Ba shore Manor, Key West Library, DMV
5/11/2018
$107,329
Upper Keys Parks--Rowell's Waterfront Park, Old Settler's Park, Garden Key Cove, Frienshi Park, & Key Largo Community Park
5/14/2018
$666,382
Communication Towers--NAS Si sbee Tower, Long Key Tower, Scout Key Tower, Grassy Key Translator, Card Sound Road
5/16/2018
$110,800
Stock Island Detention Center
5/23/2018
$100,000
Fire Rescue --Big Coppitt Fire Station, Sugarloaf Fire Dorm, Conch Key Fire Station, Layton Fire Station, Stock Island Fire Station, Crawl Key
Fire Academy
5/24/2018
$101,451
Freeman Justice Center
5/25/2018
$750,000
Upper Keys Facilities --Ellis Building, Islamorada Library, Key Largo Library, Murry Nelson Building, Plantation Government Center, Roth Buildin
5/30/2018
$673,235
a-
FEMA Site Inspections on Monroe County Projects
Project
FEMA Site
Inspection Date
Estimated Cost
Cud'oe Substation
7/12/2018
$34,700
Fire Station #13
✓ 7/12/2018
$5,872
Big Pine Library
✓ 7/12/2018
$50,000
Marathon Substation Building
7/12/2018
$35,000
Total Estimated Costs
$22 684 384
H.1.a
Packet Pg. 1074
H.1.a
USDA Natural Resources Conservation Service (NRCS)
Emergency Watershed Protection (EWP) Program Grant
Total All Areas
Project Budget
NRCS Cost Share
Local Cost Share
Construction FA 75%/25% Cost Share
$45,821,212.00
$34,365,909.00
$11,455,303.00
Other TA 100% Cost Share
$3,436,590.90
$3,436,590.90
$0.00
Total Project:
$49,257,802.90
$37,802,499.90
$11,455,303.00
Monroe County
Project Budget
NRCS Cost Share
Local Cost Share
Construction FA 75%/25% Cost Share
$31,721,532.00
$23,791,149.00
$7,930,383.00
Other TA 100% Cost Share
$2,731,606.90
$2,731,606.90
$0.00
Total Monroe County:
$34,453,138.90
$26,522,755.90
$7,930,383.00
Marathon
Project Budget
NRCS Cost Share
Local Cost Share
Construction FA 75%/25% Cost Share
$7,509,500.00
$5,632,125.00
$1,877,375.00
Other TA 100% Cost Share
$375,475.00
$375,475.00
$0.00
Total Marathon:
$7,884,975.00
$6,007,600.00
$1,877,375.00
Islamorada
Project Budget
NRCS Cost Share
Local Cost Share
Construction FA 75%/25% Cost Share
$6,590,180.00
$4,942,635.00
$1,647,545.00
Other TA 100% Cost Share
$329,509.00
$329,509.00
$0.00
Totallslamorada:
$6,919,689.00
$5,272,144.00
$1,647,545.00
Total Project:1
$49,257,802.90
$37,802,499.90
$11,455,303.00