11th Change Order 01/18/2019Jacobs Key West International Airport Monroe County Strengthen/Rehabilitate Commercial Apron Project No. GAKAP148 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 11 Stren hen/Rehabilitate Commercial Aron INITIATED ON: January 7, 2019 CONTRACT: GAKAP148 TO (Contractor): ABC Construction, Inc. 7215 NW Th Street Miami, Florida 33126 CONTRACT DATE: November 22, 2016 01119 You are hereby authorized and directed to make the following change(s) in this Contract: Due to unforeseen conditions that included Hurricane Irma and excgpti2nally hip gh "King" tides the Contractor was required to dewater the area prior to construction activities. During construction, three of the concrete slabs were damaged. After inspecting the damage, the Airport decided to apply spall repair to the damaged concrete slabs in lieu of replacing the three slabs. The Contractor agreed to offer a credit for the three slabs. The chan a order also includes the Contractor's Bid cost compared to the As -Built cost. Refer to the attached document for the net reduction. This change order includes the cost for dewaterin $44 352.00' the credit for s all repair - $ 14 362.50 and also the rice deduction for the final as -built ouantities The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be changed by this Change Order ...................... The new Contract Sum including this Change Order willbe ............................................... The Contract Time will be increased by ........................................ $ 9,250,000.00 $ 132,873.25 $ (561,354.55) $ 8,688,645.45 NA Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: AGREED TO: Jacobs Engineering ABC Construction, Inc. y Dade Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 By Date AUTHORIZED: Monroe County 1100 Simonton Street Date Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Due to unforeseen conditions that included Hurricane Irma and exceptionally high "King" tides, the Contractor was required to dewater the area prior to construction activities. During construction, three of the concrete slabs were damaged. After inspecting the damage, the Airport decided to apply spall repair to the damaged concrete slabs in lieu of replacing the three slabs. The Contractor agreed to offer a credit for the three slabs. The change order also includes the Contractor's Bid cost compared to the As -Built cost. Refer to the attached document for the net reduction. This change order includes the cost for dewatering ($44,352.00), the credit for spall repair (- $ 14,362.50), and also the price deduction for the final as -built quantities (- $591,344.05). • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No ta If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: ABC CONSTRUCTION, INC. PROPOSED CHANGE ORDER 7215 NW 7th Street Phone: 305-663-0322 NO. 12 MIAMI, FL. 33126 Fax: 305-267-2403 TITLE: Pumping and Dewatering from 11/12/17 to 8/20/18 DATE: 10/17/2018 PROJECT: Keys Strengthen Rehabilitate Commercial Apron TO: Attn: Lasa (Adams) Ennis, P.E. Jacobs 200 West Forsyth Street Suite 1520 Jacksonville, Florida 32202 Phone:904.636.5432 Fax:561.799.6579 1 3«4IiiLo ,I JOB: GAKAP145 CONTRACTlPO: GAKAP145 SUBMITTED: 10/17/2018 COMPLETED: REQUIRED: Dewatering time at Pumping f= 68 days 11/12/17, 11/14/17, 11/15/17, 11/16/17, 11/21/17' , 11/22/17, 11/26/17, 11/27/17, 11/28/17, 11/29/17, 11 /30/17, 12/03/17, 12/05/17m 12/04ml7m 12/06117, till 01/30/18.- TE # 2 = 25.5 days - Pumping = 8 days 3/12/18, 5/3/18, 5/6/18, 5/14/18, 6/12/18, 6/18/18, 6/20/18, 6/28/18,- Additional dewatering dates: Pumping = 8 days 07/22/18, 7/23/18, 7/24/18, 7129/18, 8/05/18, 8/16/18, 8/19/18, 8/20/18 Total dewatering days pumping: 68+8+8 = 84 days (24 hours each day) Num Item Description Ref Qty Unit Unit Prlce Amount 1 TE #1 Dewatering TE # 1 1,632.000 Hrs 20.00 32,640.00 2 TE # 2 Dewatering TE # 2 192.000 Hrs 20.00 3,840.00 3 Dewatering Dewatering addit. Dates 192.000 Hrs 20.00 3,840.00 #3 Item Total: $40,320.00 Overhead & Profit 10% $4,032.00 Total: $44,352.00 By: Strengthen/Rehabilitate Commercial Apron Spall Repair Credit Item Spec No. Item Description Unit Quantity Unit Price Total 3 P-102-2 Portland Cement Concrete (PCC) Removal SY 75 $ 31.50 $ 2,362.50 15 P-501-1 Non -Reinforced Portland Cement Concrete (PCC), 13" Thick SY 75 $ 160.00 $ 12,000.00 TOTAL: $ 14,362.50 STRENGTHEN/REHABILITATE COMMERCIAL APRON KEW WEST INTERNATIONAL AIRPORT PROJECTNO. GAKAP148 FINAL QUANTITY AND COST SUMMARY them No, Bid .... ............ .. ...... U it ADJUSTNIFNI JUS I MEN AS BIJI8-1 I 'A. PRICIL: Got', (D.II_ Base I -LN i7- ---- -- M-6-R-1-5-7-A-F-1-0-N - - - - - ---- - - - --- - - - - - - -------- - - - - - ------------------ - - - - - F --- I -A . '510,07.00 1 3 540,I)D0,00 $ 1 $ 540,000,00 .............. 101 1 ............ B. I )MINOUS PAVENIENT REMOVAL . . ........... . . ............... sy . 10,W ...................... . . . . . ---------- 46,(AlJ $ 460,0(70,M) .... . ........... (2,4U4,55) $ y219, 5,FO) $ 435,0 4 50 --- - - -------- -- '(�r I LAND CEME� q I CONCRF.'. TE (P CC) REMOVA I. Gy 31,5 0 1,020 $ 32, 130 X) 2CGAU $ 7,q50,30 1,212 $ 4 0,030 60 4 Il 101 '1 PAVEMENT MARKING REMOVAL sr $ 4,00 525 2,100,00 (330,00 $ (1,320,100) 195 7800 6. 5 ...... . . ........ P 101 4 ��..-.MPORARY I IE. IDOWN ANCHOR INO FALLAHON ........... r A 200,00 . .. .. ........... . .. 12 2,100,00 (Ooo� -s H'doo,00) .. . 3 ................... 00000. 6 Il 101 5 PERMANEN) Fll DOWN ANCHOR INSIALF-A-1 ION F.. A $ 200 00 6 $ ',200 00 $ 6 $ 12W,00 . ....................... I 7 . ............................................... 1, Wl (3 ........................... . . .......................................................................................... . . ............................... . . . ................ 1 IF DOWN ANCHORRF IAOVA[ . . . . . .................... F-A ...................... $ . . . ..... . IF 00 . . ................................... -- 18 - - $ - - - ----------------- (14,00) A H,400,00) 4 400,011) --- - --- ---- 102. 1 SAFE [YANDSICURHY Ls $ 100,000,00 11 - - - - 100,1000,00 ---- --- ------------- ------ $ ------ - - - ) $ 100,0U0,00 rl 152 1 UNCLASSIFIED EXCAVAI ON cy 50,00 13,boo 680,000 (A) (3,98854} $ (199,4?7,00) 9,6 11 . . ..... $ . . . . . ...................... 480,573 00 11 ... P. ... ... ... ... ............ ............ ASPI-0,IJ X MILUNGS PFrOl-_ROAFD_ SY ....... . .................. 37 NO . ..... 275 $ - ------- 10,175.00 --------------- (175,00) (13,4/5,00) loo $ . ................... . . .... . 3,700,00 F, 15G I E VI F10 RAR Y MR AND WA I ER PID L.A. u T ON so I I. ......... .. .. . . .. I . . .................................... 10,000,00 ................. . . . ..... . .. .......... $ - ------ 1 (1,00() oo ............. ............................................. F ROISION, AND Fil I A I ION CON I R01 -BASE ......... 211 1 11 ROCK cou-RSE SY S 2,00 47,020 $ 94,010,00 (4,670,0n� (9,340,00) 42,350 84,700,00 3 334 1 ASPHA� I TFMPORARY I RANSI I ON RAMP SY $ 12,0) 2,121 $ . 25 500 00 . ...... . . . . ................... ?1 ON $ . . . ..... . .. 352,00 2,196 14 -- - --------- ---------- 1 1 2 M I X A G I i A I. I I IMA) FOR $ 300,0 225 $ 67,500,00 r. 45,00 $ 13,5WKO 270 000 - 115 p 501 1 '1 NON RF, NFUKGED POWEAMY, SY $ 16c,00 37,1 11 $ 5,992,000,00 (3,022,76) $ (4B3,641,0)) 34,427 24 $ 5,508 3,15D 00 IICC!, 13'THICK 0 1 2 R[-4NFORCF-F, PORrIANF) GlI NIFIN T CONC RF IF (P A; SY $ 185,00 1 28,675,00 (155,00) $ (28,FT5 00) $ 13� 1 HICK 17 p 501 3 NON -REINFORCED POR I LANr� CEMEN I CONCRE FE 1,52K� IECCI, CY I HICK . ....... . . .......... ------ 91,00 - - -------------- 138,775,00 40,70 $ 3,703 70 1,566 $ 142,478,70 F�Aol 4 cc)Ncrl,�- I FE (pccG, 8- SY I loo 1050 $ 19,04 $ 1904 1069 $ 106,904 0 ,,01 , 19 p 501 5 ;, E popfruom-, NON REINFORCED THICKENED El �G, - - - - ---------- NY - $ 1 IK ON 3,om) K54 ............ I $ no on 61430 $ 70,644 50 1,694 $ 014 844 SO 0) F, 501 6 NON REINFORCED 1HICKENE1.) EDGE POFULAND SY $ 105,00 1,675 $ 175,87500 (10,00) $ 1,665 $ t 74,82F,,(M CEIMENIF l,,'ONCRF-T-1 PCA��r-,VTHILI� 21 P 501 7 Sy $ . . ... . Q10,00 . . . ... ... ... . .. 850 ..................... $ . ...... . 102,00000 . . . ....... .. (2b,00)A8,880,00 .. . . . ...... . . ................. .... . ....... 11 - - 22 K 1501 b KEINI-ORCED THICKLNED I �DGE POR FLAND CEMEN I ClOW-PETE f,Tllr lHIAK SY - - - $ ------------- 109,00 --- - xA) --------- $ ----------- 27,250 00 - - - ----------- (50,clo $ --- - (5,4510,00) 200 . . $ . ................... ? 1,800,00 23 f. "501 9 'REIII F.) M.1 0' SLAB 1",500,0() 7- 10,500 W (200 $ (3,000 OF)) 5 $ 7 500 00 24 p 602 1 1,13" 111 )'�'A'i'N 61JS PR"� M C"(5-A-T . ............... . ............ ('+Al 14 OF) 175 $ 2,4,,0 oo $ F,Kqo ooO 40 S 5n) on 25 p 603 1 . . ...................... . . ..................... C�2A F . ............. ............................. . ...... . ............ . . ........... 2,24000 .. 1 �� uo)$ ............ -_._._._iv' (1, Ol 0 oo)Sin . . . . . . 00 ...................... . ..... 20 p (320 1 JHEFLF--(,� f VI, I'AVL-.VI,[`fl MARKING VVI-I (,I GLASS BE/q)S 3F $ 4,50 2,600 1 �, 7()0,00 978 00 4,40I'Do 3,.w8 $ 27 1' 1, H 2 -- -- -- - --------------- - ------------ fl� F..0 I VE PAVE MI, N1 MARKING SF $ 4,00 9,900 39,600,00 1 �)64,00 7,856,00 Il,R64 . $ . ....... 4 7,4 54, 00 2 1 Fl P 620 3 ITFf,',PORARYFIA\tFNP[NFN4AvfKING 31 $ 24CD 4,950 $ 11,880,00 (2,61400) (5,273,60) 2,336 $ 5,606,10 29 1 904 1 SOUIDING, WITH 2" -IOPSOU. I SY 12,00 4700 , $ 56,40000 (4,256 00) $ (51,072,00) 444 5328,00 , 3D , I .... L I I I F; -............ �/VRP:ffl D F U N D H 0 F f A $ 1, 100, ......... . . . 2 ..... . L 2,200,00 (2,00) $ (2,2010,00� L 115 2 JADJUS7 AIRRE. LD HANDHOLF -10 FIROPOSE:D GRADE EA 1, 1 rjo, I'M 31 3 $ 3,300,00 32 . . . . �S? . ................. ......... . . - - ----- - $ . ................................... .. J"�W'6'6 ..... 260wj 1 �3 ............ 1.1 $ 52 00 15 1 . . .... 2,340,00 ......................... . ........ . . . . . . .. . . ..... ... . 1 (4500) $ ....... . . ........................ (2,140,0(0 - ----------- TOTAL BID AMOUNT -BASE BID: 1) 100 OM 55 ................ . . Arl 11 VAST ................... .. . . ......................... . . . ...... Bid Additive #1 TOTAL BID AMOUNT - BID ADDITIVE #1: A.Doro-d CIF-io Crdan� 7.777 7 2!�, 21 ul'Phase,3 TiKI,) --- ............. ........................ . .. . .... .. ........ .... 80 $ 31,566,03 C �/093 -------- ------- - ---------C-h.d . ... ..................... . .. . [.I �-k Bo- M.feri.l cy ... . .......................... . . ........ . . . . .............................................. . . Ti -16 4 .. 23 2.567 72 104, --- --------- -- RSfvjx,fnr,wi"-'.)ads FA' 3,850 on I $ 5On On . Tim( ,ELA-37j .................. .....--77 $ 95H 20 .CT076 ...... ............ ........ - $ .... . C/( #0. .... ..... Trarvitiori Rnrvqll8IPvlllllll 11 LA $ 14,355 N, 1 $ _ ...... . .................................... . . -rrarisifiori R-ir Phase I I Mobik,afior, EA . .... .✓ $ "3,856b(i 1 $ 3,650,Do I I LA 29,OJI) '10 1 -f-----7 iI TOYAL C11 ANGI ORDIR AIMOUN f 7LLS�GL-221862MLLU'l-jr �$ 162,862 T5 TO FAIL AMOUNT QBASII: 31111) 11 111111) ADDITIVII. fl , C1111AINGE. 011111DIFIRS) BM _L_19,250,01) 00 ADJUST $ ff_61,354 55_LAS RU L F t A 8 08,645 45 1 of 1