08th Amendment 01/25/2019Jacobs Key West International Airport 01/19 Monroe County Drainage Improvements Phase 2 & 3 Project No. GAKAP 149 CHANGE ORDER PROJECT: CHANGE ORDER NO.: 8 Draina a Im rovements Phase 2 & 3 INITIATED ON: January 15, 2019 CONTRACT: GAKAP 149 TO (Contractor): Charley Toppino & Sons 129 Toppino Industrial Drive Key West, FL 33040 CONTRACT DATE: November 22, 2016 You are hereby authorized and directed to make the following change(s) in this Contract: The actual field conditions did not reflect the record drawings that the design was based on. In order to connect the pumped injection well to the existing drainage system an additional 266 LF of pipe is needed This change order includes the renegotiation of the unit cost for drainage pipe under turf and under pavement. The cost includes the credit for using ADS pipe. The original Contract Sum ............................... Net change by previously approved Change Orders......... The Contract Sum will be unchanged by this Change Order ...................... The new Contract Sum including this Change Order willbe ............................................... The Contract Time will be increased by ........................................ $ 1,655,480.85 69,928.20 $ 68351.20 $ 1,793,760.25 NA Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time for delays, disruption, inefficiency, acceleration and all other claims. RECOMMENDED: Jacobs Engineering y Date Key West International Airport 3491 South Roosevelt Blvd. Key West, FL 33040 B Date AGREED TO: Charley Toppino & Sons AUTHORIZED: Monroe County 1100 Simonton Street Key West, FL 33040 M RO J. ERCA�0 AS313TANT C NTY ATTORNEY Date mm I Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The actual field conditions did not reflect the record drawings that the design was based on. In order to connect the pumped injection well to the existing drainage system, an additional 266 LF of pipe is needed. This change order includes the renegotiation of the unit cost for drainage pipe under turf and under pavement. The cost includes the credit for using ADS pipe. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: 'Adgmullba,. qw E PRICE QUOTATION Attention: Lasa Ennis DATE 1/1019 Jacobs Engineering Inc. 3750 NW 87th Ave #750 Miami, FL 33178 -ocation: KWIA Apron Project, Key West International Airport Z-�cope: EYW Drainage irriprovements Phase 2 & 3 - Additional Drainage I tQ11 Description Line item Co`stng�� ...... .... - -- - ----- ------------------------ 24" Storm Pipe (Turf) 24" Storm Fipe (Pvmt) Periormance/Paymenrgo—nds ($Z0MffhM= Mobilization/Demobilization General Conditions (Permits, Management PedestrianSaftey, etc ........ Charley Toppino & Sons, Inc. ---------------