HomeMy WebLinkAbout1st Change Order 02/12/2019Jacobs Key West International Airport 01/19
Monroe County
Faraldo Circle Realignment and Curbside Improvements
Project No. GAKAP155
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 1
Faraldo Circle Realignment
And Curbside Improvements INITIATED ON: January 22, 2019
CONTRACT: GAKAP155
TO (Contractor): Charley Toppino & Sons, Inc.
129 Toppino Industrial Drive
Key West, FL 33040
CONTRACT DATE: September 191, 2018
You are hereby authorized and directed to make the following change(s) in this Contract:
As an owner requested change, the raised crosswalks were added to enhance safety on Faraldo Circle.
The original Contract Sum ...............................
Net change by previously approved Change Orders.........
The Contract Sum will be unchanged
by this Change Order ......................
The new Contract Sum including this Change Order
willbe ...............................................
The Contract Time will be increased by ........................................
$ 397,440.00
$ N/A
$ 7,750.00
$ 405,190.00
N/A
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect and impact costs and time
for delays, disruption, inefficiency, acceleration and all other claims.
RECOMMENDED:
Jacobs Engineering
q
Date
Key West International Airport
3491 South Roosevelt Blvd.
Key West, FL 33040
w
By Date
AGREED TO:
Charley Toppino & Sons, Inc.
04 AAAAAe.- d 112-
Date
AUTHORIZED:
Monroe County
1100 Simonton Street
Key Wes L 33040
By ate
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: As an owner requested change, the raised crosswalks were added to
enhance safety on Faraldo Circle.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
qw
PRICE QUOTATION
Attention: Lasa Ennis DATE, V22119
Jacobs Engineering Inc.
3750 NW 87th Ave #750
Miami, FL 33178
ITEMIZED QUANTITIES
Location: KWIA Apron Project, Key West International Airport 1
Scope: Faraldo Circle (ES1001 REV)
Item
Description
Quantity
Units
Cost er Unit
Line Item Cost
Notes
1
Raised Crosswalk (asphalt overbuild
1.0
LS
$ 3,85000
$ 3,850,00
2
80 LF 3" PVC
1.0
LS
$ 3,400,00
$ 3,40000
3
Concrete Material
2.0
CY
$ 25000
$ 500.00
Subtotal
$ 7,75000
4
Performance!'Pa ent Bonds $20.00/Thousand
1,0
LS
$
$
5
Mobilization/Demobilization
1.0
LS
$
$
6
General Conditions Permits, Management, Pedestrian Safte , etc)
10
LS
$
$
Total:
$ 7,750.00
Notes:
Inclusions:
Exclusions:
Prepared by:
Estimator
Charley Toppino & Sons, Inc.
Sheet
1 of 1
Date:
1/22/19