2nd Change Order 08/16/2017 MONROE COVNTYANG E C/ PROJECT AUNAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Big Pine Shade Structure Retrofitting and New Bocce Courts INITIATION DATE: 08/14/2017
CHANGE ORDER NO: 2
TO CONTRACTOR:
Pedro Falcon Electrical Contractors, Inc.
d/a/a Pedro Falcon Contractors, Inc. CONTRACT DATE: 04/12/2017
The Contract is changed as follows:
The original(Contract Sum) (Guaranteed Maximum 'Price)......,..w. .. ................ .... ......$184,820.00
Net change by previously authorized Change Orders. .......... ....... .. . ........................$2,249.00
The(Cant act hum (Guaranteed Maximum Price)prior to this Change order was,............$187,069.00
The(contract Sum) (guaranteed Maximum Price)will be('increased)(decreased)
(unchango)by this Change Order ,,.$0
The new(C n raot Suno)_(Guaranteed Maximum Price) including this Change Order is.......$187,069.00
The Contract Time will be(increased) (decreased) (unchanged,)by....__ .. ............... .... 60 Days
The date of'Substantial Completjcn as of the date of this Change Order is., ...... 10/13/2017
Detailed description of change order and justification:
o Cost Time Extension due toextended/e d times l°or m erialin oribinal that oo�afd no e arr i r ted or included
modificMioncto movehadylp ! e1 erne. dct�ytic�!�ars From rat too Otto .tow Owner to orsue revised e�eertia fdr fi�tr�re o ndr° ct
dri h e r er is lie s l� 0 o/the odgrinal contract r/ e.
Not valid until_sinned§y Owner,Architect IN al2plicakbUe and Cont ctor
ARCHITECT: NIA.
Da e
CONTRACTOR: w '
to
DIRECTOR PROJECT MANAGEMENT '
Dat
COUNTY/ASSISTANT ADMINISTRATOR:
main astesi D
evin Nilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Lead times for materials.
0 Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
w Change Order exceeds $50,000 or 5%of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes❑ No
If no, explanation of why: Architect has no Construction Administration,
Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: