4th Change Order 05/06/2019 ,ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Scenic Hwy Overlooks INITIATION DATE: 04/25/2019
CHANGE ORDER NO: 4
TO CONTRACTOR:
Charley Toppino&Sons, Inc.
CONTRACT DATE: 03/21/2018
The Contract is changed as follows:
The original (Contrast Sum) (Guaranteed Maximum Price)............................................. $ 762,854.75
Net change by previously authorized Change Orders.................................................... $ 24,791.25
The (Cdrrtract Sumt (Guaranteed Maximum Price) prior to this Change order was....... .........$ 787.646.00
The Contract...a ) (Guaranteed Maximum Price)will be(increased) (decreased)
(unchanged) by this Change Order....,,. ...$ (357.50)
The new(contract 5gm)_(Guaranteed Maximum Price)including this Change Order is......,.,,.$787,288.50
The Contract Time will be (increased) (decreased) (unchanged) by......................................... 0 days
The date of Substantial Completion as of the date of this Change Order is........................... 04/18/2019
Detailed description of change order and justification:
There is one isgue that requires this than e Marc/er:
1) Final quanIgies have. been reconciled which h ac1"cLrst for under masts and over runs ih some pay
items, These acliustments in final tr ntities results in a net cost ad°rstrnent of 57. M
Not valid until si ned by Owner Architect if a licable an Contractor
CEI.
' Date
CONTRACTOR:
Date
DIRECTOR PROJECT MANAGEMENT
at
COUNTY/ASSISTANT ADMINISTRATOR: ` � �•- 6 MAY 2019
Roma n Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: This contract is governed by an FDOT LAP Agreement which requires that pay
applications (invoices) be based on actual pay item quantities and unit prices. The project is
complete and a reconciliation of final quantities and pay items resulted in this change to the total
contract amount for the final invoice (final pay app).
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No❑
If no, explanation of why: This is a FDOT funded project therefore, the CEI instead of the Architect
approved the time associated with this minor cost change order.
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes❑ No
Explain: