2nd Change Order 11/15/2018 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Scenic Hwy Overlooks INITIATION DATE: 11/13/2018
CHANGE ORDER NO: 2
TO CONTRACTOR:
Charley Toppino & Sons, Inc.
CONTRACT DATE: 03/21/2018
The Contract is changed as follows:;
The original (Contract&m) (Guaranteed Maximum Price).....................................___...$762,854.75
Net change by previously authorized Change Orders.....................................................$ 0.00
The(Contract SUrn) (Guaranteed Maximum Price) prior to this Change order was..................$762,854.75
The LQontragt510) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order.,,,.......$ 0.00
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.,,,,......$762,854.75
The Contract Time will be (Increased) (decreased) (unchanged) by.......................................... 20 days
The date of Substantial Completion as of the date of this Change Order is........................... 12/04/2018
Detailed description of change order and justification:
A r�c�coat ha�ar e order'fora 2f1 cla trraae exterrsi'arr e/rye I`e��vea//tern c:r�rat///irse�s arty�� Jicad�'e ra/ia s
thus adLysting the substarW l coMple Lion elate frc n Novetriber 14 2018 to December 04. 2018,
Not valid until signed by Owner Architect if applicable), and Contractor
/t
Cr� J,<4P ^ram Date
CONTRACTOR:
Dat
DIRECTOR PROJECT MANAGEMENT
Day
COUNTY/ASSISTANT ADMINISTRATOR:
R n astesi Date
�vin ilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: Additional weather conditions in November have delayed construction of the
Reynolds Street Pier for 13 days plus the addition of 7 applicable holidays in November which has
moved the substantial completion from November 14, 2018 to December 4, 2018. This change order
is for the time lost due to the weather and approved holidays.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why: This is a FDOT funded project therefore, the CEI instead of the Architect
approved the time associated with this no cost change order.
• Change Order is correcting an error or omission in design document. Yes ❑No El
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: