19th Change Order 05/09/2019 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 19 HVAC System Improvements Stock Island Jail Complex INITIATION DATE: May 6, 2019 TO CONTRACTOR: CONTRACT DATE: June 15, 2016 Sea Tech of the Florida Keys, Inc 131 Palomino Horse Trail Contractors Change Order Request: 19 Big Pine Key, Florida 33043 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)................................$1,538,612.00 Net change by previously authorized Change Orders.................................. .... $ 92,873.14 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was..$1,631,485.14 The (Contract Sum) (Guaranteed Maximum Price) will be(increased) (decreased) (Unchanged) by this Change Order.. $ .00 „m The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order $1,631,485.14 The Contract Time will be (increased) (decreased) (unchanged) by.................._90_DaMys- The date of Substantial Completion as of the date of this Change Order is July 30, 2019 Detailed description of change order and justification: Sea Tech is requesting a Ninety(90) day no cost time extension to our contract. We have had delays due to engineering problems with the cooling towers overflowing. We are working on a cost proposal in a change order to include the installation of two automatic control valves needed. Once the price proposal is completed and approved,we will be able to complete the Schedule the installation of the valves. These delays will result in a substantial completion date of 30JUL2019. This chan a Order is 0 0% of the original conlj'actmm Not valid until sl ned by Owner, Architect if applicable), and Contractor ARCHITECT: Date CONTRACTOR: Date PROJECT MANAGEMENT: _... Date COUNTY/ASSISTANT ADMINIST T Date Change Order Attachment per Ordinance No. 004-1999 Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Sea Tech is requesting a Ninety (90) day no cost time extension to our contract. We have had delays due to engineering problems with the cooling towers overflowing. We are working on a cost proposal in a change order to include the installation of two automatic control valves needed. Once the price proposal is completed and approved, we will be able to complete the Schedule the installation of the valves. These delays will result in a substantial completion date of 30JUL2019. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds $50,000 or 5% of contract price (whichever is greater).Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ®No ❑ Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Errors and omissions will be resolved with Architect at the end of the project. i n /da, May 1, 2019 Attn: Dan Hensley Monroe County PWD 1100 Simonton St Key West, FL 33040 Re: MCSO HVAC Upgrades Subject: Time Extension De ar Mr. Hensley, Sea Tech is requesting a Ninety (90) day no cost time extension to our contract. We have had delays due to engineering problems with the cooling towers overflowing. We are working on a cost proposal in a change order to include the installation of two automatic control valves needed. Once the price proposal is completed and approved,we will be able to complete the Schedule the installation of the valves. These delays will result in a substantial completion date of 30JUL2019 Sea Tech has every intention of accelerating the work progress to reduce the time indicated on the project schedule. Please advise if you need additional information. I may be reached at (305) 872-0888. Sincerely, RyorvZaChape&e, Ryon LaChapelle Project Manager l 1 h e%,,o i n c 41", May 1, 2019 Attn: Dan Bensley Monroe County PWD 1100 Simonton St Key West, FL 33040 Re: MCSO HVAC Upgrades Subject: Time Extension Dear Mr. Bensley, Sea Tech is requesting a Ninety (90) day no cost time extension to our contract. We have had delays due to engineering problems with the cooling towers overflowing. We are working on a cost proposal in a change order to include the installation of two automatic control valves needed. Once the price proposal is completed and approved, we will be able to complete the Schedule the installation of the valves. These delays will result in a substantial completion date of 30JUL2019 Sea Tech has every intention of accelerating the work progress to reduce the time indicated on the project schedule. Please advise if you need additional information. I may be reached at (305) 872-0888. Sincerely, A- yotv IaC ell, Ryon LaChapelle Project Manager