1st Change Order 05/07/2019 MONROE COUNTY/ENGINEERING/ PROJECT
MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 1
Key Largo Library roof repairs
INITIATION DATE: 05/06/19
TO CONTRACTOR: CONTRACT DATE:09110118
A-1 Property Services Group, Inc.
The Contract is changed as follows:
The original (Contract Sum)(Guaranteed Maximum Price) .............. .................$155,250.00
Net change by previously authorized Change Orders...,. ... 11. ... ...............1. $0
The(Contract Sum) (Guaranteed Maximum Price) prior t l P e order was...$155,250.00
( ..,..,) ( ce will ' decreased)
The Contract Sum Guaranteed Maximum Pri a ncr a , hangs Order......$1,750.00
The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is
...............................................................................I...............................
157,000 00
The Contract Time will be(increased)(decreased) (unchanged) by..............................90 days
The date of Substantial Completion as of the date of this Change:Order is...May 18, 2019
Detailed description of change order and justification:
Ow•ic�inal- ownsue3uts rto Iont�er tit the ra lacd rootin ara cat wall to ro erl drain She u er®
-most rain..coltection area:.... . ...e.... . _........ ,_ ----. �... . ..._
®Not Valid 'b a l cible anA Contractor
ARCHITECT:
Date
CONTRACTOR_
Yosvai adruga .. ,.. Del
DIRECTOR PROJECT MANAGEMENT: ._.__I _
Ca y Ki t ate
COUNTY/ASSISTANT ADMINISTRATOR `
Roman Ga.tesi, Kpvin Wilson, Christine Hurley Date
Change Order Attachment per Ordinance No. 004-1999
e Change Order was not included in the original contract specifications. Yes ® No❑
If Yes, explanation: Contractor needs to time handle storm damaged materials, replace
installations as neccessary
Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
o Change Order exceeds$50,000 or 5%of contract price(whichever is greater).Yes❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
Project architect approves the change order. Yes ❑ No❑ N/A
If no, explanation of why:
Change Order is correcting an error or omission in design document. Yes []No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Via Ern a�i 6 JLJ1 9
Aluminum for downspouts 40' @17,50 $700.00(cost amount)
Turn joints for downspouts 4 @$75,00 ea. $300.00(cost amount)
Paint 1,gal. @q3100 ea. $35.00(cost amount)
Material cost profit 15% $155.25(cost amount)
Labor 16 hm 2 guy�s �JE,91 Lt!LQIQ-qLI!]
TOTAL $1,750.00(total amount of Change order)
Vosv,axiijif d'GEO ldadrt,trqn
890'011)69" Ave 0,40irr�i, 11 1; AVj),44
0�30�� 7�352,1,x,110,3 F: 3051 471-3702 PvC 1'504�
I
A-1 Property Services, Inc.
890 SW 69th Avenue
Miami, FL 33144 r
Phone: (305)471-7353
Fax: (305)471-3702 IV
r
www.aIpropertyservices.net a v`r®89�r 4 n a q ovr rs
e
CHANGE ORDER REQUEST FORM
CONTRACT WITH: -Unknown-
DACE:03/08/2019
PROJECT: Islamorada and Key Largo Library
A-I Properly Services,Inc.proposes to do the follolving ivory
Install new Custom downspouts as existing were deterlorated
TOTAL COST OF THIS CHANGE ORDER $1,760.00
ORIGINAL CONTRACT AMOUNT $155,250.00
NET CHANGE BY PREVIOUS CHANGE ORDERS $0.00
REVISED CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $166,260.00
TOTAL,COST OF THIS CHANGE ORDER $1,750.00
REVISED CONTRACT AMOUNT $167,000.00
Approved By.�
PRINTNAME - �
Yosva ny(Goo)Madruge
SIGNATURE A-1 Property Services,Inc.