3rd Change Order 05/10/2019 ONROE COUNTY/ENG E G/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Fence Repairs at Big Pine Parks INITIATION DATE: 05/07/2019
CHANGE ORDER NO: 3
TO CONTRACTOR:
Florida Fence Corp. CONTRACT DATE: 11/16/18
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)............................................$579,000.00
Net change by previously authorized Change Orders...................................................$5,180.00
The(Contract Sum) (Guaranteed Maximum Price) prior to this Change order was.............$584,180.00
The(Contract Sum) (Guaranteed Maximum Price)will be
(unchanged) by this Change Order.......$0
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is........$584,180.00
The Contract Time will be(changed)by 30 days...............................
The date of Substantial Completion effective after this Change Order is .................—06/09/19
Detailed description of change order and justification:
D ae to the as /salt pro"dct at the laodlre einkr"1 a ketball comp lex creat'ed'' delay in corn letion of th ion e
rxa e dlll raa raaerat Qqpartrnent recommends 30 no cost Nne,gxtn i n. This Limeextern n
would move the substantial com�aletion date to 6/9/2019.
Not valid until signed by Owner Architect if licable and Contractor
ARCHITECT: N/A
Date
CONTRACTOR:
Date
DIRECTOR PROJECT MANAGEMENT .57/10 1
ate
COUNTY/ASSISTANT ADMINISTRATOR:
. .. ` � rw.W .. 10 MAY 2019
f�o, an Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ❑ No�
If Yes, explanation:
• Change Order was included in the original specifications. Yes ElNo�
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ No(�
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes El No®
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No®
Explain:
Bring-Keith
From: floridafence@aol.com
Sent: Wednesday, April 24, 2019 11:13 AM
To: Bring-Keith
Cc: tgordon@florid akeysfencing.com;accounting@floridakeysfencing.com
Subject: Request for Extension
To: Keith Bring, Project Manager
RE: FENCE REPAIRS AT BIG PINE PARKS
Mr. Bring,
Due to the delay in the resurfacing project of the Hockey Rink at Big Pine Park,
Florida Fence Corporation is respectively requesting a 30 day extension of time.
Thank you for this consideration and we look forward to your favorable reply.
Respectively,
Elizabeth Sassine
for Ted Gordon
Florida Fence Corporation
p
1