10th Change Order 07/05/2019 Jacobs Key West International Airport 06/19
Monroe County
Drainage Improvements Phase 2&3
Project No. GAKAP149
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 10
Drainage Improvements
Phase 2&3 INITIATED ON: June 27 2019
CONTRACT: GAKAP149
TO(Contractor):Charley Toppino&Sons
129 Toppino Industrial Drive
Key West,FL 33040
CONTRACT DATE:November 22,2016
You are hereby authorized and directed to make the following change(s)in this Contract:
The hatch for structure B3 has faced delays at the manufacturing_plant, which has impacted the critical path for
construction. The additional 9 Calendar Days will allow for Toppino to complete the installation of this structure and
the associated pine. The contract's last day will now be July 12,2019.
The original Contract Sum............................... $ 1,655,480.85
Net change by previously approved Change Orders......... $ 544,789.80
The Contract Sum will be changed
by this Change Order...................... $ N/A
The new Contract Sum including this Change Order
will be............................................... $ 2,200,270.65
The Contract Time will be increased by........................................ 9 CALENDAR DAYS
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct,indirect and impact costs and time for
delays,disruption,inefficiency,acceleration and all other claims.
RECOMMENDED: AGREED TO:
Jacobs Engineering Charley Toppino&Sons
y ate I y a Date
AUTHORIZED:
Key West International Airport Monroe County
3491 South Roosevelt Blvd. 1100 Simonton Street
Key West,A;'33040 . Key West,FL 33040
ON
�w W
By Date By-m &�"- -n Date
qi
0 OE C ORNEY
V
Date T ATTORN / �
qM
Charley Toppino&Sons
129 Toppino Industrial Dr
Key West, FL
305-296-5606
June 27,2019
Lasa Ennis, P.E.
Jacobs Engineering Group
Dear Lasa,
Charley Toppino&Sons is requesting a time extension for KWIA Drainage Project for CO#8 and#9.
The hatch for structure B#3 has faced delays at the precast manufacturing plant,which has affected
our critical path.We would like to request a substantial completion date of 7/12.
Thank you,
Jordan Mannix-Lachner
Charley Toppino&Sons
n Equal Opportunity Employer
County of Monroe BOARD OF COUNTY COMMISSIONERS
1T�
Mayor Sylvia J. Murphy,District 5
The Florida Keys ',r.. Mayor Pro Tern Danny L.Kolhage,District 1
Y Michelle Coldiron,District 2
Heather Carruthers District 3
David Rice,District 4
Monroe County Board of County Commissioners
Office of the County Administrator
The Historic Gato Cigar Factory
1100 Simonton Street,Suite 205
Key West,FL 33040
(305)292-4441—Phone
(305)292-4544-Fax
MEMORANDUM
To: Kevin Madok, Clerk of Courts
From: Roman Gastesi, County Administra •
Date: July 1, 2019
RE: Out of Key West Office
I will be out of the Key West office on Tuesday, July 2, 2019 through Friday, July 5, 2019. During my
absence, Tina Boan, Director of the Office of Management and Budget shall have full authority to act on
my behalf.
Roman Gastesi
Cc: County Commissioners and Aides
County Attorney
Senior Management
Payroll
Finance