1st Change Order 07/19/2019 Key West International Airport 07/19
Monroe County
NIP Construction for KWBTS Building B Floors 3 -6
Project No. GAKAP156
CHANGE ORDER
PROJECT: CHANGE ORDER NO.: 1
NIP Construction for KWBTS
Buildin. B Floors 3-6 INITIATED ON: June 19 2019
CONTRACT:,,,, � GAKAP 156
TO(Contractor): DEC Contracting Group,Inc.
1560 Matthew Dr.,Suite B
Fort Myers,FL.33907
CONTRACT DATE:September 19,2018
You are hereby authorized and directed to make the following change(s)to this Contract:
The Ori final Contract Sum is than ed ,er the attached documents.,The Schedule of Values is being reduced b total,
of 271 936.80 to account for the removal of two ed
Contract Sum is bein�&increased bw the app oval of one J,D,,Contract Modification for an ad ditive value of 17 011.50.
The net change will be the reduction in the contract sum,of�254,925,30.
The original Contract Sum............................... $,___ 3,16 070.52
Net change by previously approved Change Orders.........
The Contract Sum will be reduced
by this Change Order...................... $ -254 925.50
The new Contract Sum including this Change Order
will be............................................... $ 2,905,145.02
The Contract Time will be increased by........................................ ZERO 10)CALENDAR DAYS
Signature of the Contractor indicates agreement with the terms of this Change Order, including any adjustment in the
Contract Sum and/or the Contract Time. Adjusted cost and time include all direct, indirect,and impact costs and time
for delays,disruption,inefficiency,acceleration,and all other claims that pertain solely to the specific work covered by
this change order.
RECOMMENDED: AGREED TO:
THC,Inc. DEC Contracting Group,Inc.
By Coll Date y Date
AUTHORIZED:
Key West International Airport Monroe County
3491 South Roosevelt Blvd. 1100 Simonton Street
Key West,FL 33040 Key West,F 3040
BY a¢e By Date
Change Order Request
Project: Key West by The Sea
Owner: Monroe County Board of County Commissioners
Date: 6/19/2019
Item#1: ERV soffits over entrance door-Four to Date
Material Cost: $25.00 x 4 $100.00
Labor Cost @ $75.00 per hour: 4 hrs. x 4 $1,200.00
Bi-Fold Door Cost (1)total $75.00
Sub-Total: $1,375.00
General Contractor overhead @ 10% $137.50
General Contractor profit @ 10% $137.50
Item#2: Trap modifications for condensate drain
Material Cost: $15.00 x 27 $405.00
Labor Cost @$85.00 per hour: 1 hrs. x 21 - $1,785.00
2 hrs. x 6 = $1,020.00
Sub-total $3,210.00
Sub-contractor overhead @ 10%: $321.00
Sub-contractor profit @10%: $321.00
General Contractor Profit @ 5%: $160.50
Item#3: Unknown condition requiring relocation of disconnect at 202 203 204 207 209 211
Material Cost: $100.00 x 6 $600.00
Labor Cost @ $85.00 per hour: 4 hrs. x 6 $2,040.00
Sub-total
$2,640.00
Sub-contractor overhead @ 10%: $264.00
Sub-contractor profit @10%: $264.00
General Contractor Profit @ 5%: $132.00
Item#4 Painting of disconnect boxes and feeders
Material Cost: $15 x 27 - $405.00
Labor Cost @ $75.00 per hour: 2 hrs x 27 = $4,050.00
Sub-Total: $4,455.00
General Contractor overhead @ 10% $445.50
General Contractor profit @ 10% $445.50
Page 1
Item#5 Vertical Condensate Lines from 6th floor to ground
Material Cost PVC: $50.00 2 $100.00
Labor Cost @ $85.00 per hour: 4 hrs. 2 $680.00
Sub-total $780.00
Sub-contractor overhead @ 10%: $78.00
Sub-contractor profit @10%: $78.00
General Contractor Profit @ 5%: $39.00
Material Cost Paint: $20.00 2 $40.00
Labor Cost @ $75.00 per hour: 4 hrs. 2 $600.00
Sub-Total: $640.00
General Contractor overhead @ 10% $64.00
General Contractor profit @ 10% $64.00
Item#6 Install new bi-fold door to accommodate ERV
Material Cost Misc: $50.00 1 $50.00
Labor Cost @ $75.00 per hour: 8 hrs. 1 $600.00
Bi-Fold Door Cost (1)total $150.00 1 $150.00
Sub-Total: $800.00
General Contractor overhead @ 10% $80.00
General Contractor profit @ 10% $80.00
CHANGE ORDER TOTAL: $17,011.50
Page 2
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No r]
If Yes, explanation: Adjustment to Original Contract Sum rEducing the value by
$271,936.80 for the removal of two (2) properties, and $140,000.00 for the removal of the
unused construction contingency from the contract. The DEC Contracting Group requested
to increase the Contract Sum by $17,011.50 for one (1) approved modification. Net change
to the Original Contract Sum of-$254,925.30.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids: The change order is the
result of a combined deductive change order and an additive changE order. The results are
a deductive change order which reduces the Original Contract sum by greater than 5%.
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: