01st Change Order 12/03/2014 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 1
Marathon Airport Custom Facility,
Guardian Ad Litem INITIATION DATE: November 18, 2014
TO CONTRACTOR: CONTRACT DATE: July 16, 2014
Pedro Falcon Electrical Contractors
31160 Avenue C
Big Pine Key, FL 33043
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)............................................$1,091,403.00
Net change by previously authorized Change Orders................................................—$ 0.00
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was........ ....$1,091,403.00
The(Contract Sum) (Guaranteed Maximum Price)will be (increased)(decreased)
(unchanged) by this Change Order. .,.,.$ 28,595.18
The new(Contract Sum)(Guaranteed Maximum Price) including this Change Order is,,..,—$1,119,998.18
The Contract Time will be(increased) (decreased) (unchanged) by...............................
The date of Substantial Completion as of the date of this Change Order is.................. .....July 15, 2015
Detailed description of change order and justification:
P vi w ll gild doQtgi b Len t m 1 r n iO ule and raga m to barllet , to at An
additional 5 days extension to substantial com letion. from July 10. 2015 to.JuA 15 20,15
tli-o m .Qr eri, .0 2f.2.-r1flinal contraoLprice.
Not valid until stoned bv Owner, Architect If applicable applicablel, and Contractor
ARCHITECT:
K2M Date
CONTRACTOR:
ro can Electrical Contractors D to
PROJECT MANAGER mm ..........._..__ 1115 1;—
Do Sposito D to
DIRECTOR PUBLIC WORKS/ENGINEERING
vir it Date
COUNTY/DEPUTY ADMINISTRATOR:
man1tl sdDebbie Frederick D e
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The original specifications included bullet resistant walls and doors on
three sides of the vestibule including the ceiling. This change order adds bullet resistant
walls and doors on the remaining side of the vestibule between room 105 and room 120.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
q 7w Pedro Falcon Contractors
General & Electrical Contracting
31160 Avenue C,Big Pine Key,FL 33043-4516
(305)872-2200-Fax(305)872-2219®fcalconelgbellsouth.net
C GC 1507617 / 1 C 13003416
Request for Change Order
18 November 2014
Project: Marathon Airport Customs Terminal
Change Order Request o: One
Description: e r....I tcgg�:^il l���r
Revise Walls and Doors Between Room 105.S'ecttre L'nfrjr I/estibrde and Room 120 to
Bullet Resistant per Revision One dated 2014.10.16 and indicated on. )rawin s A.211
A211A adA611A
Labor
Additional Labor to Demo Existing Wall, Frame New Wall, Additional Insulation,
Drywall, Bullet Resistant Panels, A A Bollards, Bullet Resistant Door, Offload
Materials:
108 flours at $3 .5 ......... ...... .... ..... ... .............. $3.726m
Additional Labor to Provide Power to NewDoor-,
Hours at $ .30.......... ................................................................ SI9)"').()
Subtotal Direct Labor.....................................................................$3,919.20
Taxes/Insurance, Etc. at 3 %...............................................................................$1, 9.30
Total Labor...............................................................................$5,
408.50
Industrial
Commercial Institutional Utility
Established 1985
68
Profit @ 5%........................................................................ ........ ......... .........$ , .
TOTAL ALL OF THE ABOVE:.....................................................$28,595.1
Permit Fees and Design Drawings are Not Included in this proposal. If additional
permit fees are required the Owner is to reimburse all permit fees.
Net Amount of Request for Change Order:...................................................$28,595.18
Additional Time Requested for Change:
A. If Modification is issued within(10) Ten Calendar Days from . . ate of the
"' . ecluest for Change Order then a(5) Five Calendar hla 115 e Extension is
req�i� �.
B. If Modili�a'iton.."s to be issued later diaii 1"en Calendar Days from the Date of
the Request for Cli rder tli. i'di the time extension and cost proposal will
need to be evaluated at t -kl ttn.' ,f e(l )roposal will be submitted
reflecting requir i(,,,extension and cost i ric rease a 61le o
Respectfully Submitted,
Ken Bygler
Project Manager
�
�
Materials
Miscellaneous Additional Metal, Drywall , losukatioo"
Bollards, Electrical................................................................'.........$725.75
Bullet Resistant Panels.....................................� —.36,549.75
Bullet flesimtm dIJooruudFcumme..........................,.,,......'.......'..'.-..-36,675.AU
DoorDard*vore.............,....................,.,.......................................32,l84.54
Subtotal Materials.... ..................�$16,l35.04
Sales tax at 7.596_....—.-._..._.,_....._...._.-- ........................ — .......... .3l`2l0.l3
TotalMaterials...........................................................................$17345-17
Disposal,Eguipment& Freight
Disposal Fees.................._................-....... .......$2QQ.00
Equipment for Off-load Materials................._....................................$450.O8
Freight~.~,,,^,.^^,^........,.,............... _...........................-.-$933.)Q
TotalDisposal and ..............-............^...........................~$1,583.00
Project Coordination:
16 Hours * $100...........................................................................$1
SUBTOTAL LABOR,COORDINATION MATERIALS,
DISPOSAL & EQUIPMENT.........................................................$25,936.67
Overhead * 5%...................................................................................................$D,296.83
SubtotaN........,..........-..........~...^.........,..................~..,...,..-.-...~.$2
Sales Order
Waco Composites, Ltd. Sales Order Number:
102114-4
Wnkm' i's 747o.' 11 1.11 Sales Order Date:
Tofl 11-vuii�, M,56-688-3088 Oct 2.1, 2014
Phow $ ;fi'�I'll ��ax "�4 7�"..r36,"34
Ship By:
,',' r G d; Oct 31, 2014
�o
Page:
1.
Sold To: Ship I o.
I I a^d r o F a I co i, G( e r�i I Co iLrac,L 3 r s c d r o W,�i I I i r
31 1 60 Av(mue C. 9800 Ovor',eas Iiighway
11i,m, Key, F1, 3 3 0 4 Marathon, F1, 330 "O
PO Number Sales Rep Name
629Wr contullmd ImA in k, Cllai k
. .. ......
Customer ID...........................
Customer Contact Shipping Method Payrnevit Terms
....... .......
Net 30 )ays
............ .......................................................................... - ----
......................... .............................................. ---- .. ...........................................
Quantity hem Descd pli on I J1111,fIrk"C' Extension
.............
GI A Q Arrnr,rrCoyc E3 4Xy I , lH '3 1) 1')
0(1 ki� A 1 0 A r.mrji-Co v e I,c-ve B R,�a i t-en r J p 10 T�
II
Subtotal 6,549.75
Freight 933.00
Sales Tax
TOTAL ORDER AMOUNT 7,482.-75
WuwwWDiww.....
yew M E
Ken Byglell-
Pedro Fake:°a-uuu C"sane r aa:tors, Inc.
M60 AwL C.°
RE: Waalon &Ma:uu`¢ Q.a; mnu.us "71'cu-auauaMD
Maaaaad.Wna.unu., BwWau
s per y uur a axpcm, "r Irop yaw the Mm ugg:
Fn:nnua6h o ny one (1) new BR Lx.,rvel➢N'd(xn-aaand moot [nuuaaa Im opa°niirig"d-iDC- No , GLASS,per
yn Ir a ah<,aarllunnwnnty
For dw nun uFAM ,nnciu:u.dinng T-u°aght and taxes, No installation,
I will NOT puveca:wd mwaaDmut aura->imun duva°&mi hum W°aum Pllaaasc Nia:,a:to Ines Nvic a any
a�,u�aasu;ln�an�. .
SaWOnh
A.auaa aw Ir,
� aka� �Paa��ala.°ua�
33 627:3.877 8
lab MARfCU M Ac E•MO NT(i()MFRY.AI ABAMA 36117.I X N(334)273 9776
l
Change Order AHC -01
Date 11/10/2014
1923 SW 2nd Street
Pompano Beach, FL 33069
954-316-6160
Ar ASS HARDWARE CORP, 954-316-1360
Project: 2014245
Reference: Changes to opening 120C
Gentleman,
Our analysis of the referenced results in:
XX 1) Addition of , 1 .61
2) No known affect or change in contract price
3) Affects our work, but no known change in contract price is required.
4) This change will require a contract time extension of days.
5) Lead time for material is_week.
6) Work has proceeded per your direction. Please provide a change order in the
amount requested. If this change is not acceptable we must receive written notification
within 48 hours.
7) Work will proceed upon receipt of a written change order.
XX 8) Notes: Delete door and frame for opening 120C, change hardware to
accept bullet resistant and add exit device.
This change request is based upon the timely issuance of a written billable change order so that the
scope change and affected work adjacent to the area can be completed within the normal sequence.
Failure to receive a timely change order may result in additional cost and delay the completion date.
If further information is required, please contact the undersigned.
Sincerely,
Carol A White
SR Detailer/ Project Coordinator
carolw@atlasshardwarecorp corn
Atlass Hardware Corp.
1923 SW 2nd Street
a
Pompano Beach, FL 33069
AT LASS ASS HARDWARE CORP. (954) 316-6160
(954) 316-1360 FAX
Date: 11/10/2014 Change Order : AHC -01
T Pedor Falcon Electrical Contractors, Inc, Project: Marathon Customs Terminal
31160 Avenue C 9400 Overseas HWY
Big Pine Key, FL 33043-4516 Marathon, FL 33050
ATT : Ken Bygler
Atlass Job# 2014245
REF: Changes to opening 120C
CITY Description C h n r
Add uct
Omit Hollow Metal Door& Frame $ (467.96)
-1 HMD RI 18 A60 3070 F W/SEM 1 3/4"
-1 HMF SU 16 A60 614 SGL 3070 KID EBP
Change hardware to accept Bullet Resistant 2,652.50
-3 Hinges TA2714 4.5 x 4.5
1 Continuous Hinge CFM 83 HD1 SER12
I Lockset LC 8204 LNL
-1 Construction Cylinder
-1 Mortise Cylinder
1 Exit Device 43 53 59 8910 F 24V
I Closer 281 O
I ElectroLynx Harness QC-C1500P
I High Security Switch MSS-1
1 Power Supply BPS-24-1
I Apdapter Harness Connector 52-2946 8-4 pin
1 Smoke Seal S88 D20'
S.Total $ 2,184.54
Tax $ 131.07
Freight
Installation
Change Order Total 2,315.61
Approved By: Date
Atlass Hardware Corp.
1923 SW 2nd Street
Pompano Beach, FL 33069
,ar 'AS ,HARDWARE CORP. (954) 316-6160
(954) 316-1360 FAX
Date: 11/10/2014 Change Order : AHC -01
TO: Pedor Falcon Electrical Contractors, Inc. Project: Marathon Customs Terminal
31160 Avenue C 9400 Overseas HWY
Big Pine Key, FL 33043-4516 Marathon, FL 33050
ATT : Ken Bygler
Atlass Job# 2014245
REF Changes to opening 120C
TYDescri tfon Change Order Value
Add ct
Chuck West
Project Manager
Change Order Accepted Y:
Name: Date:
Title:
Atlass Hardware Corp
1923 SW 2nd Street
IL A" Pompano Beach, FL 33069�� '
ATLAss HARDWARE CORP (954)
316-6160
(954) 316-1360 FAX
Date: 11/10/2014 Change Order AHC - 01
TO: Pedor Falcon Electrical Contractors, Inc. Project: Marathon Customs Terminal
31160 Avenue C 9400 Overseas HWY
Big Pine Key, FL 33043-4516 Marathon, FL 33050
ATTN', Ken Bygler
Atlass Job# 204245
REF: Changes to opening 120C
QTY Description
Add
�.
TERMS AND CONDITIONS
This change order quotation (the"C/O Quote"or the"C/O Agreement") between Atlass Hardware Corporation (the"Supplier")and the
Purchaser (the party to whom this Quote is addressed) shall be binding on both parties and shall modify and be made a part of the
above-referenced Purchase Order Agreement(CUSTOMER JOB NUMBER)upon C/O Acceptance for all purposes.
Notwithstanding any provisions to the contrary in the Purchase Order Agreement(CUSTOMER JOB NUMBER),this C/O Quote and
any subsequent C/O Quote issued in reference to the Purchase Order Agreement(CUSTOMER JOB NUMBER) or this C/O Quote
shall incorporate, in whole, the terms and conditions set forth in the Original Quote issued by Supplier for the Project and the
Purchase Order Agreement (CUSTOMER JOB NUMBER) executed by Supplier and Purchaser (collectively, the "Contract
Documents").
1. THIS C/O QUOTE SHALL REMAIN OPEN FOR A PERIOD OF 30 DAYS(THE"EXPIRATION DATE").
2, THE MATERIALS IDENTIFIED BY THIS C/O QUOTE WILL NOT BE PROCESSED (I.E., ORDERED, FABRICATED OR
DELIVERED) BY SUPPLIER UNTIL SUPPLIER HAS RECEIVED(1)THIS C/O QUOTE COUNTERSIGNED BY PURCHASER
(AND OWNER, IF REQUIRED BY THE CONTRACT DOCUMENTS),AT WHICH POINT THIS C/O QUOTE SHALL SERVE AS
THE CHANGE ORDER, (II)A FORMAL CHANGE ORDER FROM PURCHASER, OR(111)WRITTEN DIRECTIVE FROM
PURCHASER (COUNTERSIGNED BY OWNER IF REQUIRED BY THE CONTRACT DOCUMENTS) ("C/O ACCEPTANCE-)
PRIOR TO THE EXPIRATION DATE. IF PURCHASER FAILS TO DELIVER THE C/O ACCEPTANCE WITHIN THE TIME
PERIOD PROVIDED, THIS C/O QUOTE AUTOMATICALLY EXPIRES AND IS WITHDRAWN, NOTWITHSTANDING THE
FOREGOING, IF SUPPLIER ELECTS,AT ITS SOLE AND ABSOLUTE DISCRETION, TO REINSTATE THE C/O QUOTE AND
ACCEPT THE C/O ACCEPTANCE DELIVERED AFTER THE EXPIRATION DATE, THE C/O QUOTE MAY BE SUBJECT TO
AN ESCALATION OF THE GREATER OF(A) 1-1/2% PER MONTH OR (B)APPLICABLE MANUFACTURER'S PRICE
INCREASES FROM THE DATE OF THE C/O QUOTE TO THE DATE OF RECEIPT OF THE C/O ACCEPTANCE.
3„ UPON RECEIPT OF THE C/O ACCEPTANCE,THIS AGREEMENT MAY ONLY BE TERMINATED OR CANCELLED WHEN
AGREED UPON IN WRITING BY BOTH THE SUPPLIER AND THE PURCHASER. UPON TERMINATION OF THIS C/O
AGREEMENT, THE PURCHASER AGREES TO PAY ALL COSTS, INCIDENTAL OR OTHERWISE, INCURRED BY THE
SUPPLIER IN CONNECTION WITH THIS C/O AGREEMENT. ANY PAYMENTS NOT RECEIVED WITHIN THIRTY (30) DAYS
AFTER SUCH TERMINATION SHALL BE SUBJECT TO AN ESCALATION OF 1-1/2% PER MONTH UNTIL FULL PAYMENT IS
RECEIVED BY THE SUPPLIER,
4, EXCEPT AS MODIFIED BY THIS C/O QUOTE AS ACCEPTED BY THE C/O ACCEPTANCE, ALL OTHER TERMS AND
PROVISIONS OF THE CONTRACT DOCUMENTS REMAIN IN FULL FORCE AND EFFECT,
i
I
I
MEMORANDUM
TO: Board of County Commissioners
From: Debbie Frederick
Deputy County Administrator
Date: December 2, 2014
RE: Change Orders
Attached is a proposed Change Order #1 Pedro Falcon Electrical Contractors for
Marathon Airport custom Facility. The conctract sum will be increased $28,595.18.
Revise walls and doors btween room 105, secure vestibule, and room 120 to bullet
resistant An additional 5 days extension to substantial completion from July 10, 2015 to
July 15, 2015.
According to Ordinance No. 004-1999 adopted by the Board of County Commissioners,
proposed change orders are to be presented to members of the Board of County
Commissioners prior to approval, assuming they are within the Administrator's
prescribed limits. Change orders not within the Administrator's authority are placed on
the BOCC agenda.
The Deputy Administrator intends to approve this change order on Wednesday,
December 3, 2014.
C Z)(�
,.
lbie Freder
ick
Deputy County Administrator
DF/ef