Loading...
11th Change Order 01/07/2016 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 11 Marathon Airport Custom Facility, Guardian Ad Litem INITIATION DATE: November4, 2015 TO CONTRACTOR: CONTRACT DATE: July 16, 2014 Pedro Falcon Electrical Contractors 31160 Avenue C Big Pine Key, FL 33043 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)...... .. ..................... $1,091,403.00 Net change by previously authorized Change Orders................................ ....... $ 286,569 34 The ( ar�tracl a,pw) (Guaranteed Maximum Price) prior to this Change order was.,.... $1,377,972.34 The( ortract G,rtL)(Guaranteed Maximum Price)will be (rnrr scd (decreased) (unchanged) by this Change Order,, ,.,$ 8,81228 The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is,, ...$1,386,784.62 The Contract Time will be (increased) (decreased) (unchanged) by.......................... N/A The date of Substantial Completion as of the date of this Change Order is............. .. January 11, 2016 Detailed description of change order and justification: F-or 'wyp t1ai a arvi elecmmtric�)l t ar t r 'cip� d r� d e t9 ,kr fi r, t l t o e ^t,t� sty cJ F.r,r.�L) eta,t rra ��rkst This changew o er is 8074/°of;�the ri �?,at contract puce m.,w.._. ..n ....., ,.,. w_ m....� . Not v rtlbct wantil s'ic ra nt by Owner. ~ r_cl itec ut a tii le and Contractor ARCHITECT K M D wsi . � Date CONTRACTOR, m'' n Electrical Contractor W Da� Wn eoro F co DIRECTOR, PROJECT MANAGEMENT Dou, t Date COUNTY/ASSISTANT ADMINISTRATOR: � � w R rnaan Gastesi Date Kevin Wilson Christine Hurley E Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: The Customs and Border Patrol personnel requested different cubicles which require hardwire data and electrical outlets. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price (whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Pedro Falcon Contractors ro 'F General & Electrical Contracting 3110vercue C,Big Pine Key,F1 33114 -4516 (305) 72-22 0®F (30 ) 72-2219-falconel@bellsoutli.net CCC 157617( EC13003416 Request for Change Order 04 November 2015 Project: Marathon Ah ���,� Custorns rtlern��r�al Change Order Request No: Nine Description: Hardwire wir Data Outlets and,1_lcotrical 011flets to S stcm Furniture in Break Room Data Outlets Universal Cabling(see attached Proposal) HardwireData per Proposal ...................,,...... ..................................$2,792.00 Electrical Hardwire Electrical Outlets to System Furniture Miscellaneous Material.............................................. ...............a„,.....$240.00 Labor 60 Manhours @ $48.30............................................................$2,898.00 Taxes, Insurance, Etc. @ 38%... ......... ......... ,...—S1,101.24 Subtotal:....................................................................................$4,239.24 Industrialr Institutional Utility Established 1985 Disassemble/Re-assemble System :Furniture 16 Manhours @$34.50......................«.. ...«...,............«.w«.,.,...,.«.....«....$552.00 Taxes, Insurance, Etc. @ 38%.........,«....................----...............« ....$209.76 Subtotal:.......................................................................................$761.76 Project Coordination: 2 Hours *, $100.00.........................................................................$200.00 SUBTOTAL LABOR,COORDINATION MATERIALS, DISPOSAL & EQUIPMENT..........................................................$7,993.00 Overhead (a)5%......................................................................................................$399.65 Subtotal......................................................................................$8,392.65 Profit@ 5%.............................................................................................................$419.63 TOTAL ALL OF THE ABOVE:..................................$8,812.28 Permit Fees and Design Drawings are Not Included in this proposal. If additional permit fees are required the Owner is to reimburse all permit fees. Net Amount of Request for Change Order:...................................................$8,812.28 Additional Time Requested for Change: 30 Calendar Days from CBP Punchlist Which is Currently Scheduled for 01 December 2015. Final Completion to Be December 31,2015 Respectf illy Submitted, Ken B gler Project Manager Universal Cabling Systems, . o," 11w LINE 7oice/ Data / 1'ibel'®)tic 914 Fern Street Phone (561) 659-6224 Proposal West Palm Beach, FL 33401 Fax(561) 659-6305 Email: info@ucscable.com Customer Name/Address Pedro Falcon Electrical Date Proposal # 31160 Avenue "C" - - Big Pine Key, Florida 33043-4516 11/3/2015 5420-RVKM Project Estimator Systems Furniture Change Order RV Description Qty Cost Total Attention: Ken Bygler RE: Marathon Airport Customs Terminal - Systems Furniture Change Order Universal Cabling Systems, Inc. will provide labor and material for the following structured cabling scope of work: 1.) Supply and installation of(6) CAT6 CMP cables in room 119 (break room) including jacks, faceplates and patch panels. NOTE: These cables will be hard wired into the systems furniture with an Ortronics faceplate and bezel. 2.) All testing and labeling will be preformed by Universal Cabling Systems, Inc. along with a 1-year warranty on work performed and as-built drawings. Total Cost 1 2,792.00 2,792.00 This Proposal is valid for(30)days from this date: 11/3/2015 All drawings,specifications and related documents are the copyright property of the Contractor and must be returned upon request. Reproduction of drawings, Total $2,792.00 specifications,and related documents in part or whole is forbidden without the Contractor's written permission. MEMORANDUM TO: Board of County Commissioners From: Christine Hurley Assistant County Administrator Date: January 5, 2016 RE: Change Orders Attached is a proposed Change Order #11 Pedro Falcon Electrical Contractors, Marathon Airport Custom Facility, Guardian Ad Litem. The Contract Sum will be increased by this Change Order $8,812.28. Substantial Completion as of the date of this change Order is January 11, 2016. According to Ordinance No. 004-1999 adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Assistant County Administrator intends to approve this change order on W e-sda�y, Jam Chni ne Hurley Assistant County Administrator CH/ef