06th Change Order 08/06/2015 ^ u
MON OE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO:6
Marathon Airport Custom Facility,
Guardian Ad Litem INITIATION DATE: June 26,2015
TO CONTRACTOR: CONTRACT DATE:July 16,2014
Pedro Falcon Electrical Contractors
31160 Avenue C
Big Pine Key,FL 33043
The Contract is changed as follows:
The original(Contract Sum)(Guaranteed Maximum Price)................•..... ..........$1,091,403.00
Net change by previously authorized Change Orders......................... ......................$ 84,624.82
The JQQatr@gLjVj33j(Guaran,teed Maximum Price)prior to this Change order was,.....
The(Q r ) )(Guaranteed Maximum Price)will be w r (decreased)
(unchanged)by this Change Order.......$ 6,304.73
The new(Contract Sum)(Guaranteed Maximum Prig)Including this Change Order is.......$1,182,332.55
The Contract Time will be(increased)(decreased)( j)by.., .„• •....... NIA
The date of Substantial Completion as of the date of this Change Order is.... .....•....August 12,2015
Detailed description of change order and justification:
n
I"P , contractB
l
ARCHITECT: 10
ate
CONTRACTOR: XD
P ro con Electricai Contractor
DIRECTOR, PROJECT MANAGEMENT
ADoug poslto COUNTY/ASSISTANT ADMINISTRATOR:
vInWilson
Gastsl Date
Christine Hurley
T
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The original specifications specified data cables running to the Customs
and Border Patrol server. These cables are to be installed in the other existing offices.
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$25,000 or 5% of contract price (whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ®No ❑
Should a claim under the applicable professional liability policy be made? Yes ❑ No ❑
Explain: TBD
, w
,
Pedro, Falcon Contractors
General & Electrical Contracting
31160 Avenue C,Big Pine Key,FL,33 3- 16
(305) 72-220 -Fax(305)g72-2219-falc®nelC ellsouth.net
C C'150717/ EC13003416
Request for Change Order
26 June 2015
Project Marattion Arc® CpsA1om',sTerj...n z aal
Change Order Request No: Six
Description: 1 c�niove S.ieci lied Leaja Cable at GAI, ace and i tin New data Cables t�
1,x,i,s.ta ng 1_pgrt,QV
1.1n:iversal Cabling 8 sttems Lnc.
Remove CAT6 cables from Room 120 and 121 to
LAN Room 107 Install New CAT6 cables from Main
Terminal IT Closet to Rooms 120 (three F2 outlets)
and Room 121 (one F2 outlet):........................... .......$2,123.00
One additional cable terminated above ceiling
in Conference Room(not shown in quote)............... ....... ...$145.00
Total Universal Cabling.................................................................$29268.00
Pedro Falcon Electrical
Provide conduit raceway run on exterior of building from
Airport IT closet to GAL space (conduit exposed as entry/exit
points and shallow underground along perimeter of building)
and rough-in box for additional cable in Conference Room
Industrial
J Established 1985
u
Materials (including tax.....................................................................$717.82
Labor 35 MHS at$48.30 (+Taxes Insurance @38%).................. . ............$2,332.75
Total Electrical............................................................................$3,050.57
Project Coordination:
4 Hours (a,$100.00.........................................................................$400.00
SUBTOTAL LABOR,COORDINATION MATERIALS,
DISPOSAL & EQUIPMENT...........................................................$5,718.57
Overhead (c 5%.............................................................................................-.........$285,93
Subtotal.....................................................................................$6,004.50
Profit(a,) 5%............................................................................................................$300.23
TOTAL ALL OF THE ABOVE:.................................$6,304.73
Permit Fees and Design Drawings are Not Included in this proposal. If additional
permit fees are required the Owner is to reimburse all permit fees.
Net Amount of Request for Change Order: ........ .......... ........ ...................$69304.73
Additional Time Requested for Change: 0 Calendar Days
Respectfully Submitted,
Ken -Bygler
Project Manager
Universal Cabling Systems, Inc.
Proposal
Customer Name/Address
Pedro Falcon Electrical
31 160 Avenue "C„ Date Proposal#
Big Pine Key, Florida 33043-4516 6/26/2015 5341-MVSD
Project Estimator
Marathon Airport Customs-Change Order MV
Description Qty Cost Total
Attention: Ken Bygler
Ref: Marathon Airport Customs- Change Order for Data Outlets- Room
120/121 to Existing Airport IDF
Universal Cabling Systems, Inc. will supply labor and material for the
removal of CAT6 cables from Room 121 and 120 to LAN Room 107.
Universal Cabling Systems, Inc. will supply labor and material for the
installation of CAT6 cables from Main Terminal IT Closet to Rooms 121
(one F2 outlet), and Room 120 (three F2 outlets), for a total of 8 CAT6
cables.
Total Change Order 1 2,123,00 2.123.00
This Proposal is valid for(30)days from this date: 6/26/2015
All drawings,specifications and related documents are the copyright property or the
Contractor and must be returned upon request. Reproduction of drawings, Total $2,123.00
specifications,and related documents in part or whole is forbidden without the
Contractors written pennission.