1st Change Order 07/16/2019 MONROE COUNTYIENGINEERINGI PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Big Coppitt Ramp Repairs INITIATION DATE: 07102119
CHANGE ORDER NO:
TO CONTRACTOR:
Charley Toppino& Sons) CONTRACT DATE:2/20119
129 Toppino Industrial Drive
Key West, FL.
The Contract is changed as follows:
The original(Contract Sum)(Guaranteed Maximum Price)............................................$252,000.00
Net change by previously authorized Change Orders............................................... ..$0
The(Contract Sum)(Guaranteed Maximum Price) prior to this Change order was.............$0
The(Contract Sum) (Guaranteed Maximum Price)will be(increased)(decreased)
(unchanged)by this Change Order . ....$
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.......$252,000.00
The Contract Time will be(increased)(decreased)(unchanged)by........................ ......... 13 days
The date of Substantial Completion as of the date of this Change Order is...................-... 7/19/19
Detailed description of change order and justification:
Due to a delay in an anchor design submittal from the Engineer, substantial completion date needs to be
delayed by 13 days.
1l
This change order is 0 %of the original contract price. a��1 O�
Not valid until siqned by Owner, Architect (if applicable),and Co*accttgr NO, 48982
STATE OF
ARCHITECT: fiG> g �. Ein k
® ate
CONTRACTOR: 2dClaL ac �6rr�°� 712/19
Yale
DIRECTOR PROJECT MANAGEMENT
Date
t
COUNTY/ASSISTANT ADMINISTRATOR: _�" �_ �'r� - ,��ti, ___ 16 July 2019
F;onian Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
® Change Order was not included in the original contract specifications. Yes ® No❑
If Yes, explanation: A delay on an anchor submittal was not included in the original contract.
• Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes X No ❑
If no, explanation of why: Submitted for his signature.
• Change Order is correcting an error or omission in design document. Yes ®No❑
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Due to the dynamic nature of parts within the design, this submittal needed to be addressed for an
accurate sizing.
1 i e i
Charley Toppino&Sons
129 Toppino Industrial Dr
Key West, FL
305-296-5606
June 27,2019
Rob Tutor P.M.
Monroe County Public Works&Engineering
Dear Rob,
Charley Toppino&Sons is requesting a time extension for the Big Coppitt Boat Ramp due
to changes in the anchor design. We would like to request a substantial completion date of
7/19.
Thank you,
Jordan Mannix-Lachner
Charley Toppino&Sons