2nd Change Order 08/06/2019 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Big Coppitt Ramp Repairs INITIATION DATE: 07/290/19
CHANGE ORDER NO:
TO CONTRACTOR:
Charley Toppino & Sons) CONTRACT DATE: 2/20/19
129 Toppino Industrial Drive
Key West, FL.
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price). . .. ... ...... ... .. .... .$252,000.00
Net change by previously authorized Change Orders.... ....... ......... ..................... . .$0
The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was...... .$0
The (Contract Sum)(Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order.. $
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.. .. $252,000.00
The Contract Time will be (increased) (decreased)(unchanged) by.. ...................... ... 10 days
The date of Substantial Completion as of the date of this Change Order is... ..... ........... 7/31/19
Detailed description of change order and justification:
F,r;al sheet pile pull-out taking Igniter than planned. Substantial completion date needs to be delayed by 10
d 7ys
n
This change order is 0 % of the original contract price. ` 0 98i
Not valid until signed by Owner, Architect (if applicable), and CoiAtctor
STATE QERe V
r g
�
ARCHITECT
,rr�-y rr �eRlfd� Dat
CONTRACTOR 7 31 Xq
D to
r
DIRECTOR PROJECT MANAGEMENT �'3
ate
COUNTY/ASSISTANT ADMINISTRATOR. � �- 6 AUG 2019
Ro na.�i Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: A delay on an anchor submittal was not included in the original contract
• Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price(whichever is greater). Yes ❑ No El
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes M No ❑
If no, explanation of why: Submitted for his signature.
• Change Order is correcting an error or omission in design document. Yes ®No ❑
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Due to the dynamic nature of parts within the design, this submittal needed to be addressed for an
accurate sizing.
l
i 1 1 i
Charley Toppino&Sons
129 Toppino Industrial Dr
Key West, FL
305-296-5606
July 29, 2019
Rob Tutor, P.M.
Monroe County Public Works& Engineering
Mr.Tudor,
Charley Toppino& Sons is requesting a time extension for the Big Coppitt Boat Ramp.
We would like to request a substantial completion date of 7/31/2019.
Thank you,
/t, '�j G 4' ...
Michael Labrada
Charley Toppino & Sons