08/15/2019 Agreement TASK ORDER FOR
PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES
BETWEEN MONROE COUNTY AND
WILLIAM P. HORN ARCHITECT,PA.
FOR
BERNSTEIN PARK FITNESS COURT IRRIGATION ZONE
In accordance with the Consultant Agreement for Professional Architectural and Engineering
Services, made and entered into on December 19, 2018, between MONROE COUNTY,
hereinafter referred to as the"County,"and William P. or Architect, PA, hereinafter referred
to as "Consultant," where professional services are allowed if construction costs do not exceed
Two Million and 00/100 Dollars ($2,000,000.00), or for study activity if the fee for professional
services for each individual study under the contract does not exceed Two Hundred Thousand and
00/100 Dollars ($200,000.00), hereinafter referred to as "Agreement" the parties enter into this
Task Order.
All terms and conditions of the Agreement apply to this Task Order, unless this Task Order
amends,adds, or modifies a provision or an Article of the Agreement of which will be specifically
referenced in this Task Order and the amendment, addition, or modification shall be precisely
described. These additions apply only to the project referenced in this Task Order.
This Task Order is effective on the 15"of August 2019,
WHEREAS, with the addition of a fitness court complex added into Bernstein Park on Stock
Island, it is now necessary to detail the surrounding park area around the court. This will include
adding an irrigation zone to the existing irrigation system. This includes, installation of the correct
valves, pvc pipe and fittings, wiring, and irrigation heads and incorporate a new irrigation zone
into the current irrigation controller and original as-builts.
NOW, THEREFORE, in consideration of the mutual promises and covenants set forth below, the
parties agree as follows:
1. In accordance with Article If, SCOPE OF BASIC SERVICES of the Agreement the
Consultant will perform services as described below:
a. Consultant shall conduct an oh-site evaluation to assess the current irrigation
system and effectively add the new irrigation zone.
b. Consultant shall review the irrigation layout and incorporate the new irrigation zone
into the as-built drawings that are pen-nit-able and show technical specifications, as
available,
Page 1 of 2
i
c. Consultant shall prepare an irrigation construction drawing to extend the existing
i
irrigation system into the existing areas on either side of the fitness court
(approximately 2,800 square feet).
d. Bid phase and construction phase services will be provided as needed for the
position of Architect at$175.00/Hour.
e. The County will provide the Consultant architect a survey of existing conditions,
i
f. Construction drawings shall be completed within fourteen (14) calendar days of
delivery of the survey of existing conditions to the Consultant.
2. In accordance with Article VII,paragraph 7.1.1 of the Agreement,the County shall pay the
Consultant a lump sum fee of One Thousand Five Hundred and 00/100 Dollars($1,500.00)
paid upon document review and approval by the Director of Project Management.
All other Terms and Conditions of the Task Order shall remain in accordance with the Agreement
as amended.
IN WITNESS WHEREOF,each party caused this Task Order to be executed by its duly authorized
representative.
CONSULTANT•
WiIlia,rill, Horn Architect,PA. Ve
MONROE COUNTY:
- t eniinistr°ator or Designee Date
MONROE COtJ'NTY ATTCPNi V
Y
Page 2 of 2