1st Change Order 08/26/2019 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Big Pine Community Center Drywall Repairs INITIATION DATE: August 26, 2019 CHANGE ORDER NO: 1 TO CONTRACTOR: Pedro Falcon Contractors, Inc CONTRACT DATE: 6/14118 31160 Ave C Big Pine Key, FL 33043 The Contract is changed as follows: The original (Contract Sum) (Guaranteed Maximum Price)..................................... ......$47,513.00 Net change by previously authorized Change Orders............................................. .....$0 The(Contract Sum) (Guaranteed Maximum Price)prior to this Change order was...... ., ..$47,513.00 The(Contract Sum) (Guaranteed Maximum Price)will be(increased)(decreased) (unchanged)by this Change Order,......$7,500.36 The new fContract Sun)LQuarantg9d Maximum Price) including this Change Order is..,....$55,013.36 The Contract Time will be (increased) (decreased) (unchanged)by............................14 Calendar Days The date of Substantial Completion as of the date of this Change Order is.................. September 14, 2019 Detailed description of change order and justification: Th ri in f co e of Voa onl aclu d a'inlin of lre dgmagpd gn.4re lac d dawall, VoLodunglely, the aint color couill n t be matched and therefore all walls/room that had d'a as e n w need to ere- ainted &1.gr qgr to ensaire a finished _n'odnnct tlnal lraatches. During repair wok, it was also identified that the raylking has fails aLouno the gerimeler base of the buil in. Ban the secon fi ran gand need to be re Paced to r v•r wvater fro enterrn the t1 ildrra an a in /ae new °n I � n d d all iris alled_n lie b ni in i a nsr n to be 14 cal ra ar Upy §to coaM/ete then' This change order is 16,of the original contract price. Not valid until signed by Owner Architect if applicable),and Contractor ARCHITECT: N'.: . Date VY CONTRACTOR: m� „/ �. Dal DIRECTOR PROJECT MANAGEMENT at COUNTY/ASSISTANT ADMINISTRATOR: � � --�- R m n Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ❑ No If Yes, explanation: • Change Order was included in the original specifications. Yes❑ No If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order, Yes ❑ No If no, explanation of why: There is no architect for this project. • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: Bring-Keith From: Bring-Keith Sent: Monday, August 26, 2019 2:41 PM To: Ken Bygler; 'Christian Brisson' Subject: - - RE: Big-Pine Community Drywall Pay App Attachments: Change Order#1.pdf Christian & Ken, Here is Change Order#1 for the additional painting and caulk. Please review and sign, and that can be sent via e-mail directly to me and I will send it for internal execution. Any questions feel free to contact me. Thanks, Keith From: Ken Bygler [mailto:kenb@pedrofalcon.com] Sent:Thursday,August 22, 2019 10:38 AM To: Bring-Keith<Bring-Keith@MonroeCounty-FL.Gov>; 'Christian Brisson' <cb@pedrofalcon.com> Subject: RE: Big Pine Community Drywall Pay App CAUTION:This email originated from outside of the County.Whether you know the sender or not, do not click links or open attachments you were not expecting. Keith, Please see attached Request for Change Order per your request for the additional painting and caulking. If you have any questions please give me a call. Thanks, Ken Bygler Project Manager Pedro Falcon Contractors, Inc. 31160 Ave C Big Pine Key, Florida 33043 Office: 305-872-2200 Ext. 28 Fax: 305-872-2219 Cell: 305-731-6978 E-mail kenb(, p Cgf glcon ca,r From: Bring-Keith [n1_4J ,ring 1 ��tit� Ir r tq o�ata El ] Sent: Tuesday, August 20, 2019 10:17 AM To: Ken Bygler; 'Christian Brisson' Subject: Big Pine Community Drywall Pay App GeneralPedro Fal'con Contractors, Inc. Contracting 31160 Avenue C,Big Pine Key,FL 33043-4516 (305)872-2200•Fax(305)872-2219 CGC 1507617 Request for Change Order 22 August 2019 Project: Big Pine Kai° Park `ommu'lt.%�... Change Order Request No: PCO - 001 Description: Owner Requested Work Additional Perim and C`waqlk Paint Walls Additional Coat of Paint Office 206, Meeting Room 209& Storage 210 Paint Ceiling Additional Coat of Paint Room 206 Approximately 3240 SF Total.............................,,, ,.........,.,................$5,3 82.47 Rake Out,and Re-caulk with Polyurethane Caulk At l xterioi°2',d Floor Where Siding Meets Slab.......................................$1,420.58 Subtotal...................................................................................... 6$ ,803.05 Overhead@ 5%.............. .......... . ............ .... ......... ....<,. ,. .,....... .....,... ...,......_3340,15 Subtotal.._......... ....................,,.,,.,,,,,.,.,,..,.,.......,...... ......... ......$7,143.20 Profit@ 5% ......... ......... ... ...... .............. .... ......... .......... . ........ ......... ...,,..,.....$357.16 Total................ .,.......................,..........,... ..........................$7.500.36 Net Amount of Request for Change Orden......,... ......... .......... ......... .......$7,500.36 Additional Time Requested for Change: 14 Calendar Days for Substantial Completion. Industrial • Commercial •Institutional • Utility Established 1985 Respectfully Submitted, Ken Bygler i Project Manager 2111