2nd Change Order 09/26/2019 ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: 2 Freeman Justice Center—Hurricane IRMA repairs INITIATION DATE: 09/23/19 CONTRACT DATE: 01/01/19 TO CONTRACTOR: SeaTech of the Florida Keys The Contract is changed as follows: The original Contract Sum.......................................................................................$ 76,745.00 Net change by previously authorized Change Orders...................................................$ 4,664.58 The Contract Sum prior to this Change order was ...............................---...............$ 81,409.58 The Contract Sum will be increased by this Change Order ...........................................$ 49,110.86 The new Contract Sum including this Change Order is .................................................$130,520.44 The Contract Time will be increased by.................................................................. ...... 150 Days The date of Substantial Completion as of the date of this Change Order is......................... 12/11/19 Detailed description of change order and justification: Additionally identified damage needing repair, including baseboards, door casings&arches, caulking of doors &windows, and replacement of 240 linear feet of storm damaged roofing drip edge. Original substantial completion was April 8, 2019. Change Order#1 changed the substantial completion date to July 8, 2019. This change order(#2)extends the substantial completion date to December 11, 2019. Chan e order is 64%of on�ntr°aot price Not valid until sI ned by Owner Architect If applicable), and Contractor ARCHITECT: NIA. Date CONTRACTOR: S ch ate DIRECTOR PROJECT MANAGEMENT 7f Ce�ectmapgelt nigh , Oire for ate � ent COUNTYIASSISTANT ADMINISTRATOR: R�° � 26 SEP 2019 man Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Additional Irma storm damage (documented in another FEMA damage description), 240 linear feet of roofing drip edge is being added to this project. Also, additional baseboard damage and caulking damage discovered after the initial FEMA damage description is being repaired. • Change Order was included in the original specifications. Yes❑ No If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater), Yes ❑ No If Yes, explanation as to why it is not subject for a calling for bids: • Project architect approves the change order. Yes ❑ No If no, explanation of why: No Architect contracted for original work. • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes❑ No Explain: Tudor-Rob From: Tudor-Rob Sent: Monday, September 23, 2019 2:50 PM To: Cuneo-Julie Subject: RE: Freeman Justice IRMA work Thanks Julie! Thanks, Rob f Rob Tudor Project Manager Monroe County Public Works& Engineering Project Management Department 0: (305)292-4416 C: (305)850-8124 t Lido r-rob monroe oun -fL ov From:Cuneo-Julie<Cuneo-Julie@MonroeCounty-FL.Gov> Sent: Monday, September 23, 2019 1:47 PM To:Tudor-Rob<Tudor-Rob@MonroeCounty-FL.Gov>; Bailey-Katrinka <Bailey-Katrinka@MonroeCounty-FL.Gov> Cc: Howard-Matthew<Howard-Matthew@MonroeCounty-FL.Gov> Subject: RE: Freeman Justice IRMA work I sent an email the day we discussed this, but I see now I sent it to Tuttle and NOT Tudor! I got Matt correct at least. Sorry about that. You can submit a Hurricane Request for a change order to the contract you want to add this to. Julie E. Cuneo Management and Business Services Administrator Office of Management& Budget, Purchasing, Grants Administration 1100 Simonton Street 2-213 Key West, FL 33040 305.292.4460 Stop 1 www.monro+ count -fl. ov ft Board of County Commissioners Monroe County, Florida "The Florida Keys" 1 From:Tudor-Rob Sent: Monday, September 23, 20191:38PM To: @ai|ey'Katrinka < : Cuneo-Ju|ie Cc: Howard-Matthew � Subject: Freeman Justice |RMAvvorh So what's the verdict? Should we keep the two pieces of work separate, or combine them as a Change-Order(or as an � Amendment)to K8att'oexis1ing' active project? Thanks, Rob Rob Tudor Project Manager Monroe County Public Works& Engineering Project Management Department 0: (305)292'4416 feaTech ox%fto ifli kC OF THE FLORIDA KEYS DESIGN BUILD CONTRACTORS September 3,2019 Monroe CountyEngineering g g Attn: Matthew Howard 1100 Simonton Street,2-216 Key West, FL 33040 Re: Freeman Justice Center Drywall Repairs Subject: Change Order#02—Replace Damaged Wood&Caulk Doors/Windows We hereby propose to furnish materials, equipment and perform the labor necessary to complete the following: 2-Seal Doors/Windows&Replace damaged trim 2.1 Install Baseboards 50 If @ 54 $2,700.00 2.2 Install Door Casing 90 If @ 57 $5,130.00 2.3 Install Door Arches 4 ea @ 1130 $4,520.00 2.4 Caulk Doors 10 ea @ 100 $1,000.00 2.5 Caulk Windows 51 ea @ 95 $4,845.00 2.6 Manlift Rental 1 mo @ 3250 $3,250.00 2.7 Replace drip edge 240 If @ 90 $21,600.00 2.8 Supervision 6 wks @ 250 $1,500.00 Subtotal $44,545.00 Overhead 5% $2,227.25 $46,772.25 Profit 5% $2,338.61 TOTAL. $49,110.86 All material is guaranteed to be as specified and the above work to be performed in accordance with the manufacturer's specifications and completed in a substantial workmanlike manner for the sum of: Forty Nine Thousand, One Hundred Ten 86/00.........................$49,110.86 Payment in full upon completion. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents,or delays beyond our control. Owner to carry fire,tornado and other necessary insurance upon above work. Workers Compensation and General Liability insurance on above work will be taken out by SEA TECH, INC. Note-This proposal may be withdrawn by us if not accepted within 30 days. ACCEPTANCE OF PROPOSAL The above prices,specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work specified. Payment will be made as outlined above. Signature Date Page 1 of 1 FREEMAN JUSTICE CENTER ROOF REPAIRS ARCHITECTURAL ASSESSMENT In general, the highest priority for any building is making the building watertight and reversing the damage caused by water intrusion. Inattention to these problems will cause additional damage to the building and increase costs in the long term. w 0 a . General view of roof penthouse. The damaged flashing is along the bottom of the penthouse wall. The damaged flashing is approx. 120 I.f. long on both sides, for a total of 240 linear feet. FREEMAN JUSTICE CENTER ROOF 4 , Detail photo of damaged flashing. The seams of the membrane flashing have come apart. The seams are spaced approximately 8' to 10'on center. Detail view of membrane flashing at existing door. There is a 3" gap between the bottom of the brick veneer wall and the roof.The brick veneer wall is supported by a steel angle.The failed roof membrane flashing is installed between the brick and the steel angle. FREEMAN JUSTICE CENTER ROOF Typical door to roof.There are 4 total. The top of the door frames are rusted and require refinishing. The doors should be recaulked where the metal meets brick. I p i h ` i G.. Detail view of top of door showing rust. FREEMAN JUSTICE CENTER ROOF f Detail photo of damaged flashing, r � fr 'G,a �o u Detail of damaged flashing,. FREEMAN JUSTICE CENTER ROOF o U ,r r r G � V � f r i 1 ll i irk il�4iir�i/� 0 PAM� FIT!W„**`aw4 ,�,".. �"'Ww�M Existing intake louver. There are 4 per side.The louver frames need recaulking. FREEMAN JUSTICE CENTER ROOF i e v v ........... < Q I Q� cr ® 0) Cl Q ;^ c fr, n IV, u,m - 0 OD tir 2 iv � cn 3 i, rz z Z. z z In u) y a d