Item C22 C.22
C�" t, BOARD OF COUNTY COMMISSIONERS
County of Monroe � Ffi� ��`"1 Mayor Sylvia Murphy,District 5
The Florida Keys Mayor Pro TernDanny Kolhage,District I
�pw° Michelle Coldiron,District 2
gym, , EM"Kfaµ Heather Carruthers,District 3
David Rice,District 4
County Commission Meeting
September 18, 2019
Agenda Item Number: C22
Agenda Item Summary #6025
BULK ITEM: Yes DEPARTMENT: Project Management
TIME APPROXIMATE: STAFF CONTACT: Breanne Erickson (305) 292-4427
N/A
AGENDA ITEM WORDING: Receipt of monthly change orders for the month of August
reviewed by the County Administrator/Assistant Administrator.
ITEM BACKGROUND: There were seven change orders considered and approved by the County
Administrator/Assistant Administrator during the month of August. The total cost of these change
orders is $56,665.22.
PREVIOUS RELEVANT BOCC ACTION: On September 9, 1998, Ordinance No 027-1998 was
adopted in order to provide that the County Administrator may approve separate, non-cumulative
change orders for construction projects and professional service contracts in amounts not to exceed
$50,000 (as amended per Ordinance No. 024-2015), or 5% of the original contract price, whichever
is greater. The BOCC requested a monthly report of all change orders considered by the county
Administrator.
CONTRACT/AGREEMENT CHANGES:
N/A
STAFF RECOMMENDATION: N/A
DOCUMENTATION:
Change Order Report August 2019
FINANCIAL IMPACT:
Effective Date:
Expiration Date:
Total Dollar Value of Contract:
Total Cost to County:
Packet Pg. 691
C.22
Current Year Portion:
Budgeted:
Source of Funds:
CPI:
Indirect Costs:
Estimated Ongoing Costs Not Included in above dollar amounts:
Revenue Producing: If yes, amount:
Grant:
County Match:
Insurance Required:
Additional Details:
N/A
REVIEWED BY:
Cary Knight Completed 09/03/2019 11:30 AM
Chris Ambrosio Completed 09/03/2019 11:41 AM
Budget and Finance Completed 09/03/2019 3:33 PM
Maria Slavik Completed 09/03/2019 4:51 PM
Kathy Peters Completed 09/03/2019 5:22 PM
Board of County Commissioners Pending 09/18/2019 9:00 AM
Packet Pg. 692
( snBnV- :podeN japio OBue4D) 6W sn ode japio eBueqD :4uewqoe44VM
N + 0 `c w
CS! n3 c a o M 0) C Q 6
a) � E o � Uc n3 � c � o` °� o LSl
V 0) O � -o c_i 2)a) C Y c 3 � ` �' d
c a) m o o °� `o c
o n3 au,, o E — c) 3 � U +� o a) d
o � � � � 0 6o� Ya) � c � o` E v
O O a) n3 m a)
2 3 0 -o �' a E m a) o o
+� a) o � � oa) a°i3 c0000 > 6 d
. —a°), a)Nna) > Ea) C Ea) a) a m3a)
a 70 _ C
0 0 3 a) 0 �, a) c)
a) Q 0 +�6 0 Q a) C C O E O 6 O m C 0)
O yi — O C O
O 01 N V N V Po
O "06 O m V "O i -O "O
ami 0 N a) a) f0 Q O_ Q f�0
m N 03 —fu V a) j V � 0 iCZ5 C O fa
C C V W N a�..i "O "O m W >
1Lax) m83 � 0oam) r � 3LL � 3 ¢ 0M
W W
0 _0 Q ^ N Q
W N 0 N
w 0 Z 00
LLIQa, rn rn rn 0) L O 00
N Z00W W W W m T 'O O O
LL O C L f0 "O (3)
0 U °) 0 6 0 c _0 0
T 0 "O —Ln W W V m a) � O 0 O (p O "O
o aci � +� -0 Ln c c c 3
C) o a a) E n Ln O + a) 0 -
W 0 E — � � a) a a) +� o (A Z 3 ,� o�
0 \ o a) 0_ a a0i a�i c O a i V M c aa)) 70 G7
M Z 0 ° E c W 'm E c c n3 =
} �' a) o > n3 a n3 r1 a n3 O a) U
O rj -, a`) o 0 V c m n3 +� n m 3
,, cn3 a) oa) a) c 3 , — mLn m 0 � �o c +gym +
rl V auimC), oc� CEIn C � coon W 0 � 0x) - o
W \ � o 0Fu0 � � � - E > om w M H a`) oE � � cn30 fC
0 W a) n w " 0-s N ai oou c m C o +� Q 0- +� Q c +�
Q 0 0 � +� o m }' m oN O m 0 J O +� a) m Q ai a) a
O � ;° oEn3 °gym 3n3m c 0 ELU 0) 3 0 U
Z W C " o 'n O a a) c o m fu M ° - m a`� 0-m o a) m
Ln V Z Z D o ) o m a`� C a In ate) O c ;a N U S axi 3 Q E ac) O N
— m +� a n3 0 a) m a) u o C O N
O o` C ° O a) ° T a) 0 n3 0 N
a00 z � mO = ALE > Ccnwo V o LA Ln
Z V U N W Z c) o W
W a o o� m C) O0 z 0 C) Ln
O O C)
V T r1i Ln
O � C 0) m � FI Q +
W n�i R
0
C O + o
W LL �# O Ln
0 W O N N M M 3 V _
0 V1-4
� L
U
Z oC a U
m m
C V V V C O O J
0 � s s s 8
V °o 0 0 0 °Z V u am�i
C w
C V V V C `` LL O
d i i i d r
O Ln Q 0
Z T U U U T V
O
V ami ami ami
N
o 0 0 a a o 06
0 0 0 0 0 aa)) O
00 a ate) Q
a LE iL iL a 0
0) "a "6 'O 0) (3) f0
Fa U U U m LL
( sr� ode ae a u uD) 6LO sr� ode aa a uego : uewgo v
� rn
N co
N
ci a
V V )
i O N N V
N c1 c1 d
ro ro
L V
6 C C C
a) 2 2�
-O a)
O 0 O Q Q Q
O O O
n � ro � �
i� rl � Vi
O a) 4- 4- 44-+
O O a) p p 0 a)
-p E >
a)
76 �
Q Q O > O
a) V cn cn Ln
LA r6 O O -
O ate+ N r-I rro (�6 E 0
O a--+
O, — a O L ro ro
0 ro V O vi 'U U) SQ a) 75
W N O L a E E }' a)
fC p 4- E -aro O O O O O -p vi
O C 4O V a) U rfo = fo
O Q 0L >
0 4- 4- 4- 0
O vOcn -0 UN) W�
Z a N a(A O O O a) v a) a OO +- 4- +- 4- +- ro Ocn�
rn
L O - C C M L N C a) a) 4—fo Q C)Z ++ 0) = O fl o V U)U)
Y.I OL L t6 � � � � � ro
O a U) OM
— (1) (1) (1) (1) a O N 3: 4- ro ro fo a)
gO^ N aLO OC }' tero ro W - C aOO4- O
iO
� � � �> k a) o C -0a) a) a) a)� �— �4 o -0 _0 -0 o
a r r r � 4- o O a V
L � NoE -U a ppp O 0. O O70 CD 7
oo a Eo a�) o o o
a O O O U � OO O oV
LU -0 °' a
Q = cn cn cn cn cn N O O O
_ +- roro -a rororo � � � i i - � a) � 0)
v� ~ Q"p "O fo E "p "p "p a4-' a4-' ro a) fl. i Q Q C:). V O Q
W E o o -0 . 0 0 0 0 0 0 E a) E �; E o o
0 O O 4-+ 4-+ Co 4-+ +� +� +-+ +-+ +-+ W O � O L O V V O V O p,
(A ro — ro a) V .� ro
W s= cn cn 'L cn cn cn U) cn cn s= 4- C a O a) fo E
IV
++ +T ro ro -a ro ro ro ro ro ro +� +- a) 4- V +� 2
Z y a aC) a a a a a a }' - � -0 O � a) � � � � cn
_ £ cLn .00� Ni �OOOM Ln OM �O = Lnn 4- LnnU Lnn U) Z Lnn rfo
U O "O "O "O "O "O "O "O "O "O "O a) O -0 O O 70
> a) rn a
O a) a) a) a) a) a) a) a) a) a) a) a) a) fo a) a) O
a � ww 0w '� � wow
'"' I I I
0 £ ,-iNLn .o norn ,�� � � -1 -1 -1 -1 -1 � a
4) *k 4 W W *k W W *k *k *k *k *k *k *k *k *k i6
LL 0000 000000 O O O O 00 0
LU V V V V V V V V V V V V V V V V H
= U
H
C.22.a
ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
e
PROJECT TITLE: Al
Big C'oppitt Ramp Repairs INITIATION DATE: 071 l9
CHANGE ORDER NO:
TO CONTRACTOR:
Charley Toppino & Sons) CONTRACT DATE: 2/20119
129 Toppino Industrial Drive U)
Key West, FL. cm
0
The Contract is changed as follows: CL
C
The original (Contract Sum) (Guaranteed Maximum Price)__ ,. $252,000.00
Net change by previously authorized Change Orders.... ....... ............. ................. .$0
The(Contract Sum) (Guaranteed Maximum Price)prior to this Change order was...,.., .$0 as
The(Contract Sum)(Guaranteed Maximum Price)will be (increased) (decreased) cm
(unchanged) by this Change Order,. , .$
The new(Contract Sum)
_(Guaranteed Maximum Price) including this Change Order is.,.,.,,$252,000.00 U
The Contract Time will be (increased)(decreased)(unchanged) by.. .................. 10 days
The date of Substantial Completion as of the date of this Change Order is-... ... . 7/31/19 cy
U)
Detailed description of change order and justification:
Final sheet )ile
Lg1l-ou1 dckm loner �7 LalneC. Subst
°a ys an/r�l orrrpl tiorr date_a�ee ss'tc�be t1o/�yed icy�
CL
This change order is 0 f of the original contract price, + NC $982
Not va fiduntil.,gLq ned b v.Owner Architect if applicable), and, Co wtr cior
STATE
ARCHITECT: C
;,,,,,,►' fiat E
CONTRACTOR: �.w �....... j �q
D to
DIRECTOR PROJECT MANAGEMENT
ate.. _.
.m� ^ �•�..w�� �1 �' �°�,,..�COUNTY/ASSISTANT ADMINISTRATOR, 6 AUG 2019
_ ,..... ... _,
Pori+"bra Gastesi Date
Kevin Wilson
Christine Hurley
Packet Pg. 695
Change Order Attachment per Ordinance No, 004-1999
0 Change Order was not included in the original contract specifications. Yes No [I
cm
|f Yes, explanation: A delay onmn anchor submittal was not included in the original contract '
CL
� Change Order was included in the original specifications. Yes No ��
If Yes, explanation of increase in prime:
� Change Order exceeds $50,000 or 5% of contract price(whichever is greater). Yes No ��
|f Yes, explanation eato why itim not subject for a calling for bids:
CL
� Project architect approves the change order. Yes No � �
|f no, explanation ofwhy: Submitted for his signature, �
0
� Change Order ia correcting mn error or omission in design document. Yes ZNoFI �
Should a claim under the applicable professional liability policy be made? Yea [I No ED
Explain:
Due hz the dynamic nature of parts within the demiQn, this submittal needed to be addressed for en
accurate aizing
� °�
C.22.a
Charley Toppino&Sons
129 Toppino Industrial Dr
Key West, FL
305-296-5606
July 29, 2019
Rob Tutor, P.M.
Monroe County Public Works& Engineering
Mr.Tudor, o
CL
Charley Toppino& Sons is requesting a time extension for the Big Coppitt Boat Ramp. 0
0
We would like to request a substantial completion date of 7/31/2019. cm
Thank you,
cv
U)
0
Michael Labrada
Charley Toppino& Sons
Packet Pg. 697
C.22.a
MONROE CouNriy1ENGwEERiNG1 PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Cudjoe Fire Station No. 11 INITIATION DATE: 07/24/2019
CHANGE ORDER NO: 01
(West CPR#001)
TO CONTRACTOR:
West Construction, Inc.
CONTRACT DATE: 08/15/2018
e
The Contract is changed as follows: o
CL
as
The original (�Qoratract Sum) (Guaranteed Maximum Price)........................................ $3,884,185.00
as
Net change by previously authorized Change Orders.................................................... $0.00
The(Co ntract Surat) (Guaranteed Maximum Price) prior to this Change order was................. $3,884,185.00 as
The (Contract Sum) (Guaranteed Maximum Price)will be (increased) (decreased)
(unchanged) by this Change Order.,.... . ,. $26,000.00
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is..,......$3,910,185.00
The Contract
Substantial eo c eta ) (decreased) (unchanged) by.......................... ,. ...... 0 days
The date
p s of the date of this Change Order is.......... ..... .. 11/12/2019
Detailed description of change order and justification:
n ' M
There is ores issue that ret trues tlrrs chararre_order.,
tf
) A 5 rrre stt raa it one tlae ro'ect site eras disca vetted to contain a lar e r trat tit ca/or` ataic aratlCL
other unstrilable rnaterr`aL The contractor excavated and gli Deed caf tlae rrrastrr"tattle rr�aterral °b
filled the excavated cif'with c/ean f nnerock and compacted the it to re triter/densit . T"tae as
CountZ and West Construction have mutual1v a reed tt era an incremsed atnount of 26 000.00
toot this additional work and materials,
Not valid until si ned by Owner Architect if applicable). and Contractor
as
CEI: none E
" Date
CONTRACTOR: _ µJTat
Dat
DIRECTOR PROJECT MANAGEMENT Z'!�
Date
...
COUNTY/ASSISTANT ADMINISTRATOR: �� � �"-��.��� d� �-���- 27 AUG 2019
l�o.nan Gastesi Date
Kevin Wilson
Christine Hurley
Packet Pg. 698
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The location of possible organic or other unsuitable materials was discovered by
a Geotech survey conducted as part of the project design. However, the extent and quantity of such
material was not completely defined by the Geotech report. Although the Contractor should have
expected to encounter some unsuitable materials, the exact quantity and level of effort to remove and
replace said material was not known at the time of bidding.
• Change Order was included in the original specifications. Yes ❑ No
0
CL
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ No ® 0
If Yes, explanation as to why it is not subject for a calling for bids:
N
• Project architect approves the change order. Yes 2 No
U)
If no, explanation of why:
0
CL
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: 0
Packet Pg. 699
C.22.a
MONROE CouNTYANGwERiNG1 PRojEcT MANAGEmEyr
CONTRACT CHANGE ORDER
PROJECT TITLE:
Cudjoe Fire Station No. 11 INITIATION DATE: 07/08/2019
CHANGE ORDER NO: 02
TO CONTRACTOR: (West CPR#002)
West Construction, Inc.
CONTRACT DATE: 08/15/2018
The Contract is changed as follows:
e
The original (Contract Sum) (Guaranteed Maximum Price)....................................... $3,884,185.00
Net change by previously authorized Change Orders..................................................... $26,000.00 CL
The (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was......., $3,910,185.00
The LQontract Sum) (Guaranteed Maximum Price)will be(iincre�ased)(decreased)
(unchanged) by this Change Order.................... $1,972.19
as
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.... $3,912,157.19
The Contract Time will be (increased) (decreased) (Las ha_nge ) by............................. 0 days
The date of Substantial Completion as of the date of this Change Order is................. 11/12/2019
Detailed description of change order and justification: 04
U)
There is one issue that re wires this change order:
1) The water heaters ecified in t/'Lg b d.documents for the Fire Station is an AO Smith 80 al. 240
tf
sirup hale r'nod'ewl. The power service at the breaker erne/is desk ned for 208 v single ahase. CL
The AO Smith model cannot be converted to 208 v without voiding the warrant' The °b
r conaraaended water heater is a State 8t)c r . 2()8 v siracrle, base model wvlfich will match the
available nower�:t the vanet Mus offer heat pump ca mbill'ties which will be raaarc/a naorae eraer E
efficient and therefore higher scoring arnder FQBC standards.4 0
as
This change order is 0.05% of the original contract price.
Not valid until signed by Owner Architect it applicable),and Contractor a
E
CEI: none
Date
CONTRACTOR: 8° 13
DIRECTOR PROJECT MANAGEMENT
ate
COUNTY/ASSISTANT ADMINISTRATOR: ;.�� . '?.- �� r a,. ..� 27 AUG 2019
Ro r an Gastesi Date
Kevin Wilson
Christine Hurley
Packet Pg. 700
C.22.a
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The original design recommendation for the AO Smith model was for a 240V
single phase model. The standard design for the electrical service is for 208V single phase. Since
the AO Smith model was very specific to the 240V requirements, it would not be suitable for this
installation. The recommended model is a very high efficiency, heat-pump based model that will work
with the electrical system design and provide higher FGBC scores.
Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price: CL
o
o Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
o Project architect approves the change order. Yes ® No❑
If no, explanation of why:
U)
CD
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
CL
Explain:
0
CD
Packet Pg. 701
C.22.a
ONROE CouNTYANG E G/ PROJECT MMAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Cudjoe Fire Station No. 11 INITIATION DATE: 0726/2019
CHANGE ORDER NO: 03
TO CONTRACTOR: (West CPR#004)
West Construction, Inc.
CONTRACT DATE: 08/15/2018
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price)................................... $3,884,185.00
Net change by previously authorized Change Orders..................................................... $27,972.19 CL
0
as
The(Contract.Sum (Guaranteed Maximum Price) prior to this Change order was.........., $3,912,157.19
The.( orrtract Sum) (Guaranteed )' (��) (decreased) $2,348.03 as
u.raranteed Maximum Price will be wreased decreased
(unchanged) by this Change Order...................
The new(Contract Sum)_(Guaranteed Maximum Price) including this Change Order is.... $3,914,505.21 °b
The Contract Time will be(incr ed) (decreased) (unchanged) by........................ 0 days
The date of Substantial Completion as of the date of this Change Order is................ 11/12/2019
Detailed description of change order and justification:
There is crrre issue that requ s this change order.-
1) At the d to he added to
tf
the decontaraaination shower alreadv clesi ned for this fire station. A make and model similar to 0
CL
e e wash stations installed in other Counter stations was .rMcased. The Contract ha,s
provided the aLha rri gq_quote to install this e e w+�ash station. as
This change order is 0.06% of the original contract price.
as
Not valid until signed by Owner Architect if ap 21licablel, and Contractor
as
E
CEI: none
Date
CONTRACTOR:
ate
DIRECTOR PROJECT MANAGEMENT
Dat
f
,d^
.. r
n�
COUNTY/ASSISTANT ADMINISTRATOR: .: w,. - 27 AUG 2019
Ro an Gastesi Date
Kevin Wilson
Christine Hurley
Packet Pg. 702
C.22.a
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No ❑
If Yes, explanation: The original design for this station includes a decontamination shower in the
apparatus bay. Based on the current building codes, the decontamination shower serves as both a
full body shower and a face & eye wash, therefore a separate eye wash station is not required by
code. Every other fire station in the County has an eye wash station, but only a few have a
decontamination shower. The Fire & Rescue Department is requesting the addition of an eye wash
station soh that staff that may not be familiar with a decontamination shower will be able quickly
e to u c I use
Y q Y
the eye wash instead.
• Change Order was included in the original specifications. Yes ElNo® o
CL
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ® No❑
U)
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
CL
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
0
Packet Pg. 703
C.22.a
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Big Coppitt Boat Rarnp Repairs INITIATION DATE: 8128119
CHANGE ORDER NO: 3
TO CONTRACTOR:
choth"Y 1opl.)ino& Sans CONTRACT DATE: 2/20119
129 foppino lmluslriol Niwo
J Key Wesl l 1_ 33040
0
CL
'I he Contract is changed as follows W
The original Contract Sum) (Guaranteed Maximum Price) $252 000 00
Net change: by previously authon7ed Change Orders $0
1 he (Contract Sum) (Guaranteed Maximum Price) prior to this Change order was $252,000 00 cm
as
The (Contract Sum) (Guaranteed Maximum RriGe) will be (increased) (decreased)
(unchanged) by this Change Order .$ 3,500.00
The new(Contract Sum)_(Guaran teed Maximum Rrice) including this Change Order is .._ $255,500.00
the Contract 1-ime will be (increased) (decreased) (unchanged) by 35 days ✓
1 he date of Substantial Completion as of the date of this Change Order is 9/4/19 ✓
Detailed description, of change order and justification:
Adding 3)uads.of 1157 inch 10 j)a1htLjg lo0.)oat hording area.__ cm
® mm,..e_m� .. ........... ee... e.. . .,M ..... 0
CL
1 �
this ch,,mw oak, is 1.4 % of the oricrinal conhact/)/Ico
Nol yalid (jn1,tsyi%tLp )„tq4C)wvrotcw „Fat lydtfw :.).41t *atpTlMc )ka p,)a..ond Contri mtor
ARCH ITEC 1 (r!... ....m
E
CONTRACTOR
01RF.CTOIR PROJECT MANAGFMFN
COUNTY/ASSISl7WT ADMINISTRATOR � � ����� ��m 1� " 29 AUG 1
1 dnv n Gastesi Date
Kevin Wilson
Christine_Hurley
Packet Pg. 704
C.22.a
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No❑
U)
If Yes, explanation: additional rock needed to make parking and access to ramp more aesthetically
complete.
0
CL
s Change Order was included in the original specifications. Yes ❑ No
If Yes, explanation of increase in price:
0
CD
w Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
U)
0
• Project architect approves the change order. Yes ❑ No® CL
C
If no,explanation of why: Area out of scope of Engineer's task order
0
Change Order is correcting an error or omission in design document. Yes❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain:
Packet Pg. 705
C.22.a
CHARLEY TOPPINO & SONS, INC.
FRL"rt�l�l INO 8 ON'S,I D, Change Order Request
OX 787Number,WEf,FL 33041 Phone: 305 296-5606
Fax: 305 296-6189
PROJECT: Bi Co itt Gulf View Boat Ramp DATE: 8/27/2019
TO: Rob Tudor PROJECT#: 1904
Monroe County BOCC
i
COST CODE:
U)
as
DESCRIPTION OF CHANGE: �
Additions to multiple line items
ITEM DESCRIPTION AMOUNT O
Quantity Unit Price
l Furnish and Install 3 Loads of#57 Rock 1 S 3,500.00 S3,50o.00
2
3
4 �
5
6
7 so.00 �?
8
TOTAL: $3,500.00
U)
1. It is understood and agreed that the acceptance for this Change Order by this Subcontractor constitutes an accord and satisfaction with the terms of this Change Oider
2. The amount of the Change Order covers all direct and Indirect costs
3. It is rudher understood and agreed that all terms and conditions or said Contract,as t may therefore have bean modili d shall remain the same
4. Acceptance of the Change Order acknoYdedges acceptance of all previous Change Order work by the Subcontractor and ConlraMor as well as any adjustments to the Subcontractor amount and mCdificalions as reflected above
5. This Change Order includes all items necessary for a complete instaltahon including,but not necessarily limited to labor,supervision..materials.Iranspodalion,mcidenlals,taxes,and any other ilems necessary fora complete Installation
The Original Contract Sum was................................................................... $252,000.00
Net Change by Previously Authorized Requests&Changes................................. $
$ 252,000„00
The Contract Sum Prior to This Change Order was.......................
.„,.„.„„.„,
$3,500.00 t0
The Contract Sum Will be Increased/Decreased.............................................„.
$ 265,500.00
The New Contract Sum Including This Change Order.......„«........................„„,„„„„
The Contract Time Will/Will Not be Changed (Days).„......,...„.....,„„„,„...„.„„„„...... 0
O
ACCEPTED:
CHARLEY TOPPINO&SONS,INC. MONROE COUNTY
By: Michael Labrada By:
Project Admin
Printed Name&Title Printed Name&Title
Date 8/27/2019 Date:
Packet Pg. 706
C.22.a
Project Management Department
MEMORANDUM
Mon...
roe County BOCC ,
Office of Project Management
1100 Simonton St,Suite 2-216
Key West, FI 33040
(305)292-4526
U)
To: Kevin Madok,Clerk of Courts
0
From: Cary Knight, Director of Project ManagementCL
Date: August 23, 2019
Re: Out of Office 0
MEMORANDUM �?
..............,. mme
will be out of the off' from Monday August 26, 2019 through Friday August 30, 2019. During my
absence, Brean r�itson, Budget/Contract Administrator shall have full authority to act on my behalf, U)
0
Cary Knight
�s
Cc: County Commissioners and Aides
County Attorney
Senior Management
Payroll
Fiance
Packet Pg. 707
C.22.a
MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Fence Repairs at Big Pine Parks INITIATION DATE: 07/2412019
CHANGE ORDER NO: 5
TO CONTRACTOR:
Florida Fence Corp. CONTRACT DATE: 10/17/18 U)
0
The Contract is changed as follows:
The original(Contract. urp)(Guaranteed Maximum Price).. ............$579,000.00
Net change by previously authorized Change Orders, ......... ......... ......... ...........$21,180.00
The(tract Sum,)(Guaranteed Maximum Price)prior to this Change order was.............$600,180.00 0
The ntract Scar ) (Guaranteed Maximurn Price)will be(increased) (unchanged)
(decrease)by this Change Order $-8,000.00
The new( ontract Su )_(Guaranteed Maximum Price) including this Change Order is........ $592,180.00The
The new date o
Contract
Time
f (changed)bydays—Substantial Completion effective after this Change. ..Order is ...................06/23/19
N
Detailed description of change order and justification: U)
Wexts n Fie*ld, nd Bi have documented
a—dptnaQqs-,.
rot / icatt+ 1 ar�d se al cep r�t..m. e a m r flee re f r 16 QQ-QQjo rerrrcyp
/ r r ra rete in e wv r�et os ! l g P Logdd/-erg o f
�an was no d�rrwr
the an le round:sleeve s��e�d c�rrrre to Phe coracle�spor� rt/�/eo ec lWlan en�eral that tlrr�ra
r�rader round to the stee v on/ t t/re ost , avl iealr e.e ur e tf the pro 0 of or1c i,/tin in t/ae 8/ Cl OBCL
ire? i his c r . stance the.ex ent of e'labor ,nd ne? r�crte wa,s not erforme�i.
Not add untOsies Oanggt01„ of the can ire l contract price.
3
weer.Ar hitect if a licable and Contractor 0
ARCHITECT: N/A
O
Date
CONTRACTOR: k . ..._ ��. _ .' �1. E
t"� ca
D e �
DIRECTOR PROJECT MANAGEMENT
Date
COUNTY/ASSISTANT ADMINISTRATOR: . �f
v` �
Sri n Geor
esi Date
ke
Christine Hurley
® -° Packet Pg. 708
C.22.a
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ❑ No&
If Yes, explanation:
0
• Change Order was included in the original specifications. Yes ❑ No\
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5% of contract price (whichever is greater). Yes ❑ No
M
If Yes, explanation as to why it is not subject for a calling for bids:
U)
•
Project architect approves the change order. Yes ❑ No
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑No
Should a claim under the applicable professional liability policy be made? Yes ❑ No
Explain: E
Packet Pg. 709
, Flo; j
e
s
r
p,
!
� �✓ //�j NV r D// r �
r
� i/
I�
ria✓
or✓v'�/r i "r /r i ✓�y r�i �f �
CM
r r,/✓ r/i l�9J'�p if /j it%l�r i�/�� r %l�i �/�ii/l(
f8)
�i i✓�`�%%�%irl�0oi� rlrri / irvi//lr r� ✓ / i /D///`���i �
lli�/✓i�0�/r /r�r If�r/� ✓i r✓/a / l %i 'l, I Pr
r �r k✓/rd/r��F/r�//ill r// / D i%%ii:r /"i r"%/i/%/i/�/i ��%y 1�l/�"��i'
(✓//�A/ i�r!%�,�''l p(�� n�� /lr; iyV/r� r r r di;� r �% `I r, `0
r'/51�l��y�//i��i4/f iiyy//l%ri/rr✓�ryy r%/a%rr��/"/r���� %,��t%��� J wi��f(�'J�� �/l� � � V
r(�/�°l�/��������� "�✓//� / ri� 1/%flJ�i/Hni/l� llrl�f��' � �J1����1' =u!',vtrilY��' �
� rr%uir l/�i�i����ri/'�1�r/✓�y/✓i',� � r r la /I ;(��il�/�"�yiy' ' f
I'M
ri / �✓o//° r li 1 y� r rr f� i � 1 l �J'p � r� i l� � ✓rii�r U i r�/ �P�� ,r�� �y � ✓Jl�� ���� �
vc sleeves have a little paint
C
and rust color from old posts
but sleeves are schedule 80
pvc and asphalt has discoloring
from collar of old post wipe
down takes most of it off but
once painted will look perfect
Packet Pg. 710
C.22.a
MONROE COUNTYIENGINEERINGI PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Marathon Annex &Carpenters New Roofs INITIATION DATE: 811312019 U)
cm
CHANGE ORDER NO: 1
TO CONTRACTOR:
Your Roofers, LLC
CL
320 S point Drive as
Sugarloaf Key, FL 33042 CONTRACT DATE: February 19, 2019
The Contract is changed as follows: 0
The Net hannael ( r by f(aft Su n)(Guaranteed Maximum Price). ..... ...... .. .......... ............$122,687,00
previously Change ... $ ✓ �3
The( a7/r_qq!., t,/p 1(Gua anteed�Maxim m Prriice)prior to this Change order was....... _....$122,687.00 ✓
The(Contract Sum) (Guaranteed Maximum Price)will be ljinqp (decreased)
(ur7chartged)by thus Change Order.. $27,84 00'°' °' '
The new( pn(rjpt Maximum Price)including this Change Order i .. $150,532.00 !"
The Contract Time will be Lincreased (decreased)(unchanged)by . , , 58 Days , . ..... . ✓
i
The date of Substantial Completion as of the date of this Change Order is ..September 13, 2019.°...., "
Detailed description of change order and justification: sure Darin e,Pion of th r of we disccaverod the C
roofslo as xnwvard t 't tf2�`rrchrs rn llga c raPar, trw ord'rrr frar u 1 rraaet c ode on lli roofve�v�/1 r�Po lrPl CL
thal area it)willm adibl+onaP tS0 fittrsr Prorarfl whrft rrrtrrrrt war"dt rear lfir adcl,"tarara f� s to be added to 11)e rest �
of the foot fo ensure wve rrrrr�t lira i18"ifl rroP r�rirernnt artart . ffr cfiPiormal Bost for ttrr wvill irrr
t148 g0„ e wouldl�lre ter also re rrast�nsrort to tea ut rrr tare for Se�rrrlaat 13,29 9 this �
rj,21 's needed dirt,tc arPoe�srradt tad fptr Prw.tPtr3_psrdprrdpd forpai,prrPrt/rl da(p /1( (r
This change order is 22.7% of the original contract price. ®.. . U
Not valid.. rrr4tI lgged_by Owp er
r hhigh, �� gay lc gl�p man Corltr Cyr �
ARCHITECT; N'/
D, t
CONTRACTOR:
DIRECTOR PROJECT MANAGEMENT
COUNTY/ASSISTANT ADMINISTRATOR; Roman s °
e itlnt8 Date
Kevin Wilson
Christine Hurley
Packet Pg. 711
C.22.a
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes ® No ❑ U)
If Yes, explanation: There were no drawings or specifications for this Hurricane repair project
0
CL
• Change Order was included in the original specifications. Yes ❑ No ® ✓
If Yes, explanation of increase in price: 0
• Change Order exceeds $50,000 or 5% of contract price(whichever is greater), Yes ❑ No ® ..
If Yes, explanation as to why it is not subject for a calling for bids:
0
• Project architect approves the change order. Yes❑ No
If no, explanation of why: No Architect on the project. ,
0
+ Change Order is correcting an error or omission in design document. Yes ❑No ® .
Should a claim under the applicable professional liability policy be made? Yes ❑ No ® ,
Explain:
Packet Pg. 712
C.22.a
sanders-steven
From: michelle hopper <michelle@yourroofersllc.com>
Sent: Tuesday, August 13, 2019 10:37 AM
To: sanders-steven
Subject: extension and change order for Marathon Annex
CAUTION:This email originated from outside of the County.Whether you know the sender or not, do not click links or
open attachments you were not expecting.
Regarding the Marathon Annex building
U)
During our inspection of the roof, we discovered the roof slopes inward by 1 1/2 inches in the center. In order
for us to meet code on this roof, we will need to fill that area in with additional ISO filler board, which intern
will require additional layers to be added to the rest of the roof to ensure we meet the 1/8"/ft code
requirements per plans. The additional cost for this will be $27,845.00.
We would like to also request an extension to be put in place for September 13, 2019, this date is needed due 20
to previous and projected rain in the extended forecast. Please advise with approval so that we may proceed. w
Thanks.
�s
N(6chRU&}fo-ppev�
CEO
803-223-1924 (Cell)
305-240-9444 (office)
0
your owers.. 'LLC
CL
Packet Pg. 713
C.22.a
4
t"r 9CYi T# s M.
Monroe County Engineering
Vr�/' 1100 Simonton Street,2-216
Key West, FL 33040
Project Management
May 31, 2019
Michelle Hopper
Your Roofers LLC.
320 S point Drive
Sugarloaf Key, FL 33042
0
RE: NOTICE-TO-PROCEED FOR: Marathon Annex Building & Carpenters New Roofs
Dear: Michelle
0
cm
This letter serves as Monroe County's official NOTICE TO PROCEED(NTP) to your Company
to commence with the above referenced project. This NTP is issued pursuant to Contract
dated: Tuesday, February 19, 2019 U
This NTP is limited to the scope of work for: Marathon Annex Building & Carpenters New cv
Roofs for the lump sum price of: $122,221.00. Please include the Task Order number and/or
Job Name on each invoice to facilitate the payment process.
Commencement date for the services associated herewith shall be considered to be Tuesday,
June 04, 2019 The substantial completion date shall be considered to be 45 calendar days or
Friday, July 19, 2019 Final completion of all work shall be considered to be Monday, August �
19, 2019.
If you have any questions, please contact me.
Sincerely,-)
E
Steven Sanders
Project Manager
C: Cary Knight, Director Project Management