6th Change Order 10/28/2019 CoNTRAcr CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO, 6 Demolition of Old,and Installation of Now Transfer Station Offices INITIATION DAT E:October 8,2019 CONTRACTDATE:May 17„2017 TO T CTO : Pedro Falcon Contractors,Inc. 31160 Avenue C Big Pine Key®FL 4 -410 The Contract is changed as follows The original(Con_1Lacl Sure)(Guaranteed imum Price), ,.. . . ,.. 1„106,410,00 t change bypreviously authorized Change Orders—,—......... 070.62 The(Contract hum (Guaranteed Maximum Price)pricer to this Change Order was.-- —$1,160,286,62 The(Contract Sum)(Guaranteed Maximum )will be(Increased)(dscreased) (unchanged)by this Change Order. ,.,..$ ( 0®1 9.42) The new(C tract tarn)( uaranteMaximum Price)Including this Change Order is.,....,$1,122®137.20 The Contract Time will be(Inc ed (decreased)(unchanged)by.... ., ...,.. ,,..,.,.a. ..,,.., w.. 114 Days The date of Substantial Completion as of the date of this Change Order Is, ...December 2„2010 [detailed description of change order and justification; Lh substantial,cogm/t llo date. The Contract 5tren/s t frtep redaeced due to the®act that the daci_�araortlas revioust as roved in Chertcre ender!t 5 cannot��Installed as B e d�riot eB v�Ind toad re Wrements. The addltio t 1 i4 de woanld�laca corr►oBation data�n fU rraber 3 `which is� attrrday. a are iviraaT c®nBra�Ba�r r.arrtit rsaxt lauslne.ss day whrch is�nda�, Cecea7aber 2. 2019 to flnall�e and dose cart reraiect. Change Order is 3.491.of ori nal contract rIc . Not valid until eiaxned b�Owner,Architect flf as Ilea ie}m and Contraote}r ARCHITECT: A n „- Date �µ 9 COST" CTOR,°°� Falco a � n .... w.�. . „Inc C le DIRECTOR PROJECT MANAGEMENT _ u ..."� ..,.. _,. ....... rtriM ...�: le COUNTY/Aa i T"ANTADMINISTRATOR yin �Y _.._ ��� tesi Date is Christine Hurley Change Order Attachment per Ordinance Change Order was not Included In the original contract specifications. Yes El No If Yes,explanation: * Change Order was Included In the original specifications, Yes 0 No If Yes, explanation of increase In price: The Inclusion of canopies was treated as an alternate bid price n the project went out for compedtive soficilaffon. n was determined after we accepted change order#5 that the canopies as designed will net meet wind load requirements and cannot be constructed This change order is a credit for the work added In change order#5 that net be completed. ® Change Order ex 50,0 or 5 of contract price(whichever Is greater). Yes No CK If Yes,explanation as to why it Is not subject for a calling for bids: a Project architect approves the change order. Yes 0 No If no,explanation of why: a Change Order Is correcting an error or omission In design document. `fee No Should a claim under the applicable professional liability policy be made? Yes o Explain: