3rd Change Order 11/05/2019 MONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Pigeon Key Ramp Rehabilitation Project CHANGE ORDER NO: 3 INITIATION DATE: 10/24/19 TO CONTRACTOR:American Empire Builders, Inc. (AEB) CONTRACT DATE: 12/19/18 The Contract is changed as follows: The original Contract Sum ..................... ..... ....................... ... ....... ........ ........$1,960,000.00 Net change by previously authorized Change Order 1 ........................... .. ....,. ..$477,103.68 Net change by previously authorized Change Order 2(technical only) $0.00 The Contract Sum prior to this Change order was......................... ....... ..$2,437,103.68 The Contract Sum is affected/Time is not affected by this Change Order 3 $35,000.00 The Revised Contract Sum including this Change Order.............................. $2,472,103.68 Pursuant to contract article 7.2.2, the cost or credit to the owner resulting from a change in the Work shall be determined in one or more of the following: . ;2.ijLi utua accepttarna fafmmftarrgt Burn f�ropcfr iftonaized„�sp i s lg �ar s fficwer t strtastl nti ,xug we k to pgrr si evaluation 7.2.2.2 unit prices stated in the Contract Documents or subsequently agreed upon 7.2.2.3 cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee The contractor submitted RFI 08 suggesting a 50 ft linear gravity wall due to significant erosion creating an unsafefunstable drop off condition of approximately 35 inches at the ramp landing. (refer to attachments). On September 11, 2019, staff met on site with the Engineer of Record (Metric Subconsultant ASA), Construction Engineering and Inspection (CEI-WSP, USA, Inc), Contractor(AEB)and FDOT environmental consultant(Terramar) to determine an appropriate cost effective solution that would not require an additional environmental permitting process or be as costly as a gravty wall. It was determined that a rubble rip rap system would be an acceptable solution. AEB has provided negotiated fine item pricing for these items(refer to attachment for cost breakdown)and has determined that no additional time is necessary to complete this additional scope of work since it can be accomplished concurrent o other ttasks.The CE PI concurs wit h this Change Orde r er 3. The resulting changes to the contract are as follows: p ®. . .......-_ . .... _— Quan"'°..�..m __...... _... Descri lion tity UOM $Amount —IRW DrawingRASA Consultants dated Protection Details — 1 Lump Sum d 10.19.19 -....�_ .. —_ m.�_.n.. _.......... _ .. _.. . .... . ._ Total Increase to Contract Change Order 1 $35,000.00 ................ This Change Order is.017/ of the original contr rice wee CONTRACTOR � _...... � � � Dat , ENGINEERING SERVICES DIRECT�-R 7k .__ ..... `� �� � Date ASSISTANT COUNTY ADMINISTRATO ". �.. 5 NOV 2019 Date PKR-AEB Change Order 3 FLORIDA DEPARTMENT OF TRANSPORTATION/FHWA Pigeon Key Ramp Bridge#904480 Rehabilitation FPN: 436566-1 Contract: GOW60 Federal Id: D618-030-8 Acknowledgement: Date PKR-AEB Change Order 3 Change Order Attachment per Ordinance No. 004-1999 • Change Order was not included in the original contract specifications. Yes ® No ❑ If Yes, explanation: Unforeseen conditions—the erosion condition was not present at time of bid and if not corrected will create a liability and a severe unsafe condition of an almost 3 foot drop off at the landing edge of the ramp. • Change Order was included in the original specifications. Yes ❑ No If Yes, explanation of increase in price: • Change Order exceeds$25,000 or 5% of contract price (whichever is greater). Yes ❑ No Change order exceeds$25,000 but not 5%. If Yes, explanation as to why it is not subject for a calling for bids: • Project engineer/architect approves the change order. Yes ® No ❑ If no, explanation of why: • Change Order is correcting an error or omission in design document. Yes ❑No Should a claim under the applicable professional liability policy be made? Yes ❑ No Explain: PKR-AEB Change Order 3 , * r F �r 1 e � " " F �s " � /lY l� .� nit A „ � '�• " �ry o ,'« 7 y IY� REQUEST FOR INFORMATION NO. 08 From: Rigoberto Tirado `ro Jordan Salinger American Empire Builders, Inc WSP Phone: 305-261-9276 Fax: �Phow 305-916-5690 Fax: Project Name: Receipt L.oggcd: Pigeon Key Ramp Rehabilitation Project 2/14/2019 Submitted By: Date: 2/14/19 Dwg/Spec No./Revision/Detail/Sect.No. Rigoberto Tirado Subject: Erosion at approach to ramp Problem&suggested solution: The approach area to the ramp presents significant erosion (see pictures attached). We propose the construction of 50 lineal ft of gravity wall as per FDOT Standard Index No. 520, and a 10 ft approach slab. The wall would extend from pier 23 through the end of the ramp plus 40 ft following the coastline. Engineering Dept. Review Solution: Instead of Gravity Wall, a Rubble Riprap System is the approved solution; please see attached detail & notes. 1vV1inw Bs only rM rp w'11nll cr„oidannrnau'ice with flirt ck'sVgii rauwap:au ofpojou tmd grrrrm+ll Wilk comur,arp dociurmem "oi illiralloi i,a-,1pov VOrk Vm roorili ning-wd c¢uu'u'vu m!I119+ irirtairui"sir„iva.at fob riv"too 111[roil 11"a,uhouv rvlhilk Ili l),,italluu,lva P,aONnrmulr.ara Iln raa:a ,O�rol iaill ucOrniu trrrl n 1rpiw,,,roI¢,oil dihiann air rnrovl�raft all I,rr.a&,,A,d rnr Irmrrvauinrmurp allVmr¢rrl¢oiif ,arrf;eronl�a0u�(fu<::uarryimamma-ut ff{c*vu+:^waif Iliril:vr„Ouavnluirp,=,Vintlll oin plea way urilovm flea raonfiarunr ear ll[,rr„suli,miii,uIi.idly ro, rualll rcimps!liriucr,vrtlr o: , ra%cbi,ahrorrmu uu:r mf dNrr a rs ofi rtr:f eflo�rfuu nrnPr roaru rrvr+i i rues cn^Homo,^�urau ia,lin^�If iop�rllr�dtinriuiry„ Solution By.Soheila Sadou h Date: 10-19-19 Eng.Dept. Date: J V} fiW@CC'-!:I J19 k7a1�M�3C1lVWrV cPi PV3.JNU LF PPJJ dS.tY kVd!'.DRU 3➢di AW MfPdl:S3l3 349d Si 1_R.{P94 4tPJJ.�G fJ19PP k3"d�VX3F Sd¢t 3C4L �f t'1 Y�✓ I ��:.re��iN 1r�N"�X r ➢. o 4 7F ti r� , hl y O o m o T l 2 0 � I r�. Off uw ,,f eN• u o o u c a "_N F It ``stif�K,�J ...��6 W J Y 00o x Pia z ,t Yb`JYdfIm'M'H InW ci M J o P,G4IWAMII74 �CY 4p 4 ( }a" "y P kPPtl WW XN'N5h TM t � As A fP>7 "rr, 1 z C„ p Y C5 „i too loop!h 3 Ulf ryry'� " k LM F VY 6 vs v M sd'a SIR IR ✓ !A," 4Y 1 s .i" 4 $' Yk'a'A 4 *Y �p �.._. r F" yyy 'V�. '�., y� wV S z Oil v r , ryn ' ? i '�'Y C'i to L`i ✓w V- a; ^ ..'G:"^ I (5 K rZ C; S bS �Eiji" l S x, 0 .... ,� to .. Y 4 C5 r 'Y 19 .yr Y na`q "{ 5"t W }tV A" � °' 1 s r X )H V �`SA big Arm s a, w,4 W Xr K l MIKE t C� x kYk S C 1 e' 4 a VM t plot 1 a m r a HOW W L�hcc "A,vow. V 'L tti Y 4 ✓,1 '^;'- "$ k ._ v k X Y tS- v'"t't 4vi Y 1 V $lk QXI W F Itt ry'x*` t\ 4,..� � ,. }nc -- ,,�.: d,�n!+.,.0 I ta U 2 V1 VS 4, O P'wC "," �,:UN��,4,Vv 4i U 6,4..C:5 V 4A f',Y�..... F 4�lY •^• s.- G rW ky uj M.Y 4i :pry rvY"'k v4 W Pigeon Key Project October 24, 2019 FDOT Financial Project ID Number: 436566-1-58-01 j To: WSP USA Contract Number: ATT. Ms.Jessica Miles GOW60 Dear Ms. Miles, Per your request, please see below our proposed price for the construction of the ramp approach according to the details shown on the Engineer's drawing, with the exception of the dowels and the rip-rap shown on the bridge side under the deck. Please note that our price is based on the use of the large stones (rubble rip rap) existing in the island. Item Unit No. Description Unit Quantity Price Amount Ramp Approach and Erosion LS 1 35,000.00 35,000.00 Please note that if the quantities change, AEB reserves its rights to reevaluate the quote and resubmit a revised price. If you have any further questions, please don't hesitate to call Antonio Gonzalez at (305) 345-5484. Sincerely, Antonio M. Gonzalez President 13775 SW 145h CT, Suite B Miami, FL 33186 305-261-9276 Office americanempirebuilders.com 0 0 0 0 0 E LO Q m rrn n 0 0 0 0 0 0 3 O LO .--� N O1 O E Ln M Ln LA N N N N Tri ri r-1 m f0 a+ O H O Ln 0 O O o 0 O o 0 0 0 0 0 47 r-1 N 1� O al O O O O �., O O O O O O ++ N r-I ++ 0 w O l0 C 0 0 0 0 0 0 N M I� 01 m 0 r-I � LA 3 0 Ln w Ln m M m V N Q: n _4 m M OO w I- Ln r, � M m m � C/1 6E -L d O O Q Ln ri ri O O O O O O 0 0 O 0 O c ri r-I -1 N C 00 n In I, U3 r u H C 0 Ln O O ri -1 -1 rl rl rl ri r-I ri N n O >.. a ri N r-I n a•+ = M �T N N fC0 LCO 7 3 m (n T7 �..... O rn O O O Ln O 0 0 O O 00 'Ln LO O Ln � 01 l6 0 lO d; 0'... m aO+ M Ln W LO al 00 M N n l0 0 rn LO Q M It N N ++ r-I Ln m o O1 o v v LI7 m m � O N rn m > c p a o o tD Ov a o Y J J J M 0 3 t u m O a a Q a E m a m c O t a u am+ ro p o a v a m m t -0 m w E to cu O m c v Q a" u t 0 E '� a w OmC L — 4 4 aci a Y m LL Y u N +' m ` C N U 3 C, dJ v o V C ` ~ m c m o E X ` m c m'' cu 0 Y O m m E a v v w m E v o L a Ln cl m a v tU ro '� �° r'o cc .C' v ^ ,c., *' m O. L.L UL U u LM Ln PL O N W m m C C LL 72 J O_ Vf LA u W L 0 O H ri N M rf NI. fYY