Marathon Tax Collector 12/17/2019 P
TASK ORDER FOR
PROFESSIONAL ENGINEERING AND SURVEYING SERVICES
FOR THE MARATHON TAX COLLECTOR BUILDING REPAIR
In accordance with the Continuing Contract for Professional Engineering and Surveying Services,
made and entered on October 21,2015,as first amended an April 19,2018,as second amended on
October 17, 2018 and as third amended on August 21, 2019, between MONROE COUNTY,
hereinafter referred to as the "County" and PEREZ ENGINEERING & DEVELOPMENT,
INC., hereinafter referred to as "Consultant", or "Contractor" where professional services are
allowed for miscellaneous projects in which construction costs do not exceed One Hundred
Thousand 00/100 Dollars ($100,000.00.) or for study activity if the fee for professional services
for each individual study under the contract does not exceed Ten Thousand and 00/100 Dollars
($10,000.00); hereinafter referred to as the"Agreement"the parties enter into this Task Order.
This Task Order is effective on the I fir' day of Decapllacr ,2019.
WHEREAS,the Marathon Tax Collector Building was damaged during Hurricane Irma and is in
need of repairs,and
WHEREAS, the Consultant is qualified and able to perform engineering design services for the
repairs to the Marathon Tax Collector Building.
NOW, THEREFORE, in consideration of the mutual promises and covenants set forth below,
the parties agree as follows:
1. In accordance with Article II, SCOPE OF BASIC SERVICES, of the Agreement, the
Consultant will perform services as described below:
Consultant shall visit the Marathon Tax Collector Building site to determine the existing
conditions and shall create a complete set of construction documents for the repairs. The
construction documents will include partial floor plan,repair plan,and repair details.
Proposed repairs to include:
• Settling slab in"vault room."
• Settling slab adjacent to vault room.
• Damaged concrete tie beams and columns.
No mechanical, electrical,or plumbing plans will be included.
Note: Prior to proceeding with design, partial excavation or demolition may need to be
done to allow for observation of existing structural members. This demolition is not
included in this Task Order.
Page 1 of 2
l
2. In accordance with Article VII,Paragraph 7.1.1, COMPENSATION,the County shall pay
the Consultant monthly in current funds for the performance of this Task Order as an agreed
upon lump stun fee as follows:
• Preliminary Plans for Monroe County Review S3,000.00
• Upon Completion of Construction Documents 14,050.00
Total Fee $7,050.00
3. All other terms and conditions of the Agreement remain in full force and effect.
IN WITNESS WHEREOF, each party caused this Task Order to be executed by its duly
authorized representative.
CONSULTA
hi
Perez Engine Devclopment, Inc._A&
ate
r *�"
Printed Name Title
MONK CO NTY
I�
County nimistrator or desigoee ate
Printed N c�
M �TrORN OFFICE
jf
pATFacw EMLES
AssisrArt'r co nmrCANEv
DATE: