Notice to Proceed KEY WEST INTERNATIONAL AIRPORT
3491 S. Roosevelt Boulevard Key West,Florida 33040
January 16, 2020
Douglas R. Masch II,
President DEC Contracting Group, LLC
1560 Matthews Drive, Suite B
Fort Myers, FL 33907
RE: Administrative Notice to Proceed for Construction:
Key West International Airport Noise Insulation Program
Construction of Key West by the Sea, Building C
Project No. GAKAP160
Dear Mr. Masch:
Please consider this letter as Notice to Proceed with Construction for the above contract
dated September 30, 2019.
The Program Manager has approved the schedule and has confirmed that the Contractor
has a minimum of two (2) weeks of materials stored on site and has obtained all the
necessary permits.
The Building C Construction Period represents a total of 268 Calendar Days consisting of
the following time periods:
Construction Period January 28 — October 6, 2020
Post Construction Period October 7 —October 21, 2020
It is expected that the Contractor will begin construction as scheduled on January 28, 2020.
If you have any questions, please contact me.
&Z;tk�
Beth Leto
Deputy Director, Airport Finance & Admin.
XC: Deborah Lagos, Deborah Murphy Lagos &Associates
Steve Vecchi, THC