4th Change Order 01/28/2020 MONROE / E G/ CONTIRACF CHANGE ORDER PROJECT TITLE: Pigeon Key Ramp Rehabilitation Project CHANGE ORDER NO:4 TO CONTRACTOR: INITIATION DATE: 7/27120 American Empire Builders, Inc. (AE ) CONTRACT DATE: 12/19/18 The Contract is changed as follows: The original Contract Sum ............................................................. .... .... ._, ..... . ..31,960,000,00 Net change by previously authorized Change Order 1 ....................................................$477,103.68 Net change by previously authorized Change Order 2(technical only) $0 00 Net change by previously authorized Change Order 3 $35,000M The Contract Sum prior to this Change order was......... .......... , .....$2,472,103.68 The Contract Sum/Time is affected by this Final Reconciliation Change Order 4 ( 90,124 16) The Revised Contract Sum including this Final Reconciliation Change Order....._............. $2,381,979.52 Pursuant to contract article 7 2 2, the cost or credit to the owner resulting from a change in the Work shall be determined in one or more of the following: 7 2.2.1 mutual acceptance of lump sum properly itemized and supported by sufficient substantiating data to permit evaluation . 2r t pRimq It two�I�gr�tu t Ummtamrnprxt .P�.st�lseq. tAly quel,aat,7, 7 2 2,3 cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or percentage fee Due to 22 weather days and 63 change order days the contract time was increased from 270 to 355 days. The CEI has reconciled the plan versus in place final contract quantities per attachment and concurs with this Final Reconciliation Change Order 4.The resulting changes to the contract bid line items are as follows: Bid Item No i D- ....... ----m__ ... u ......_. -.. . Description Underr p n UOM Unit cost $Amount Decrease/Overrun - ; Increase Quantity, _ 104 11 Floating Turbidity Barrier 110 LF _ 53.00 ($5,830.00) 4l)0�-5 Concrete Class IV Substructure -6,20 CY W $1,453.79 ($9,013.50) emenits s IV .... ........ ... —,---4, ...m,-- 4,10 ..,........cY. -$1...453.79, .,-w.m._ . $5,960 54 E®cas , ... _,_.. ........ .._-w .. - - - 400-4-5 Conc.r.emeete Class IV Decrease per - 510 28) Encasements FDOT spec 411-1 Epoxy for Crack Injection 4 00 GA $250 00 ($1,000,00. 411 2 Cracks Inject and Seal 26 00 LF $56.00 ($1 456 00) ee........... -...--LB--- ... ..._ 415-1-5 Reinforcing St._' "Ieel-Sub b structure 3589.00 $4.90 ($17,586.10) 8-1-26 Bridge Deck Expansion Joint -30.00 LF $12.00 ($360 00) Rehab 47 ..._ . _ _..,m. . _. -.$. 1226.00_...-. ($4B 5�) Omm1 Treated Structural Timber 3 70 MB $11 36 20 460-1-15 Structural Steel Rehabilitation 309 15 LB $60 75 80 86 400 4-5 Concrete-original bid math increase 26.. error(see attached corrected bid sheet) 415-1-5 Reinforcing math error(sae Steel-original bid decrease � (12 22) m...... had _ rrected bid sheen . � . .... co..., Total Final Re, - .................................._..—............ ...... .. _. a Order 4$9tl 124 1Bj Reconciliation Deduct Chase�g��-�_-.__-._....w a PKR-AEB Final Reconciliation Change Order 4 This Change Order Is(046%)of the original contract pd CONTRACTOR ° ENGINEERING SERVICES DIRECTOR f fat �,..... ... ...w_.� � ? ASSISTANT COUNTY AD'MINdSTRANOR ...��+ 28 JDate FLORIDA DEPARTMENT OF TRANSPORTATIONIFWWA Pigeon Key Ramp Bridge#904480 Rehabilitation FPN:436566-1 Contract:GOW60 Federal Id:D618-030-8 Acknowledgement: Date PKR-AEB Final Reconciliation Change Order 4 Change Order Attachment per Ordinance No. 004-1999 Change Order was not included in the original contract specifications. Yes® No❑ If Yes, explanation: Final Reconciliation—the difference between plan and in place final quantities. Change Order was included in the original specifications. Yes❑ No If Yes,explanation of increase in price: C o Change Order exceeds 25 000 or 5/a 9 $ of contract whic e rice p ( h ver is greater). Yes❑No Change order is deduct amount. If Yes, explanation as to why it is not subject for a calling for bids: Project engineer/architect approves the change order. Yes® No❑ If no, explanation of why: e Change Order is correcting an error or omission in design document. Yes❑No Should a claim under the applicable professional liability policy be made? Yes❑No Explain: K -AEB Final Reconciliation Change Order 4 I t 16/2020 Debra London Project Manager Monroe County Engineering Department 102050 Overseas Hwy, Suite 229 Kay Largo,FL 33037 OVE RR'0/0DERRUN FINAL RECONCILIATION I RE: PROJECT NAME: Pigeon Key Ramp Bridge#904490 Rehabilitation PROJECT FIN: 436566-1-58-01 CONTRACT: GOW60 FED AID NO.: D618-030-B COUNTY: Monroe Ms,London: The summary of contract dollar changes is shown below: Original Contract Amount $ 1,960 000.00 Chan a Order#I.S"r" _..___..__- e,. ............. ....... _ �.... $,... ...m g tructural Steel Rehabilitation 477,103.68 -....... ........ ........ . ._n_ _... Change Order#2 Concrete Material Change(Zero-Dollar Spec Change Only) $ �.... ........._ .... .. - Change Order#3 Ramp Approach $ 35,000.00 ,.,.w ..-A. Cor rec____...t_ion..... ................ Mathematic al Pay item Total Underruns/overrun � � New Contract Tota..w t. $ 2,381,979.52 Contract time was increased 14 days due to weather bringing the total Allowable Contract Days to 355.The summary of contract time changes is shown below: CONTRACT TIME Original Contract Time 270 Weather Days Granted t 22 ® ..._.. Change Order#1 Days Granted 63 Total Co...,...... m ntract Days 355 Listed below is a detailed description of pay item overruns and underruns for the contract: a5111(JSA 95M t_tarers aas liuggIrway, Mmathon, Hl 33050 1 305 916 56190 %% % I ) Pay Item 104-11 Floating Turbidity Barrier: Underrun Floating turbidity barrier was deployed to encompass the entire length of the work area. As this is a shallow area with wide tidal fluctuation, sections of floating turbidity were replaced and paid for as necessary when damaged or deteriorated. However, the turbidity barrier was well maintained and did not require as much replacement as expected resulting in a 1 10 Linear Foot underrun of the pay item. Pay Item 400-4-5 Class IV Substructure(Footers): Underrun Class IV Substructure concrete was utilized and reinforced with rebar to retrofit and enlarge the existing footers. In some instances, solid rock was encountered which reduced the depth of the concrete pour due to existing conditions. Removal of existing solid rock may have undermined the existing footers. As such, this pay item was underrun by 6.2 Cubic Yards. Pay Item 400-4-5 Class IV(Concrete Encasements): Overrun As added by Change Order#1, 1.6 Cubic Yards of Concrete was added to encase 6 of the 10 columns requiring steel repair and coating at Piers 1 and 2. However, field conditions and concrete conditions of existing encasements required replacement of all 10 encasements in lieu of the planned 6 encasements,resulting in the 4.1 Cubic Yard overrun. The Contractor's QC performed cylinder break testing of the last 3 encasements poured.These 3 encasements totaling 1.3 Cubic Yards did not meet the strength requirements as set forth in Section 346-3 of the FDOT Standard Specifications 2018 for Structural Class IV Concrete. However,due to the fact that these encasements are intended for the protection of the steel column and not structural in nature, it was recommended by the Senior Project Engineer to leave the encasement's in place at a reduced payment price per specification 346-11.7, Calculating Pay Adjustments. This adjustment resulted in a line item adjustment of-$510.28. Pay Item 411-1 Epoxy Material for Crack Injection(Structures Rehab): Underrun This line item relates to the material required to inject existing cracks within concrete structures. Existing cracked concrete encasements were removed and replaced with new concrete.As a result,the line item quantity for this line item was reduced by 4.00 Gallons. Pay Item 411-2 Cracks Inject and Seal(Structures Rehab):Underrun This line item relates to the length of existing cracks within concrete structures to be sealed and injected. Existing cracked concrete encasements were removed and replaced with new concrete. As a result, the line item quantity for this line item was reduced by 26 Linear Feet. Pay Item 415-1-5 Reinforcing Steel—Bridge Substructure: Underrun Class IV Substructure concrete was utilized and reinforced with rebar to retrofit and enlarge the existing footers. In some instances, solid rock was encountered which reduced the depth of the concrete pour due to existing conditions, Removal of existing solid rock may have undermined the existing footers. This field adjustment resulted in the utilization of less rebar. As such, this pay item was underrun by 3,589 LBs of reinforcing steel. Pay Item 458-1-26 Bridge Deck Expansion Joint Rehab: Underrun The planned quantity of expansion joint rehabilitation was 72 LF;however,the two measured expansion joints totaled 42 LF resulting in an underrun of 30 LF. Pay Item 470-1 Treated Structural Timber: Underrun The planned quantity of structural timber was an estimated quantity; timber was ordered and installed according to measured field quantities and cut to exact sizes resulting in a 3.7 MB underrun. The final reconciliation summary of quantities is listed below: FINAL RECONCILIATION CHANGE ORDER icon UNIT TY UNDER ADJ. UNIT TOTAL Pay Item: Oesc:rip " Q COST TOTAL OVER 104-11 Floating Turbidity Barrler LF 110.00 Under $53.00 -$5,830.00 400-4-5 Concrete Class iV Substructur _e,_ :," e CY -6.20 Under $1,453.79 -$9 013.50 (Footers) __. _, . . ., row, 400-4-5 Concrete Class IV(Encasements) CY 4.10 Over -$510.28 $1,453.79 $5,450.26 411-1 Epoxy Material for Crack GA 4.00 Under $250.00 $1.0100.00 Injection-Structures Rehab 411 1 11111111 Cracks Inject and 'll1 11 .. �A Sc .... .... -Structures LF -26.00 Under $56.00 -$1,456.00 Rehab 41.... 1-5 Reinforcing Steel-Bride LB 358 9.. _ �. .. .._ 5- g 6 9.00 Under $4.90 -$17,586.10 Substructure 458 126............B... e ................ .... �.... .. �. g Deck Expansion Joint LF 30.00 Under $12.00 4360.00 Rehab 460-1-I5 Structural SteeI Re"ha,"bit—it ation LB 0,J-. 0 8- -309.15 Under $60.75 $18,780.86 470-1........ ._ Treate—�. - 2 d Structural Timber MB 3.70 Under m $11,226.00 -$90 112.40 Should you have any questions or concerns,please do not hesitate to contact us at 954-658-9259, Sincerely, Jordan Salinger Project Administrator Equivalent 28 day compressive strength=f c(28),where: rr�aF f'(28) = 0.794 f'(t)e l (Type I Cement) G 02 1 f'(28) = 0.730 f'(t)e .g (Type II Cement) n r. x 2 YG f'(28) 4 0.826 f,'(t)e ' � (Type III Cement) f(t) =Average Core Strength at time t(psi) measured(t, 346-11.7 Calculating Pay Adjustments: The Engineer will determine payment reductions for low strength concrete accepted by the Department and represented by either cylinder or core strength test results below the specified minimum strength, in accordance with the following: F Reduction in Pay is equal to the reduction in percentage of concrete cylinder strength (specified minimum strength minus actual strength divided by specified minimum strength). For the elements that payments are based on the per foot basis,the Engineer will adjust the price reduction from cubic yards basis to per foot basis,determine the total linear feet of the elements that are affected by low strength concrete samples and apply the adjusted price reduction accordingly. rwnurrmr�.a r!tyr�vifr�uv��a�t�r�ar�rur�rrirndfahhn�i,�uirP�,"rr;Y,rrJlrfrwlf��Y�vw>///itamr/,17il�//aJ,X�;��it�rrd�u&�,U//%r'"iyylt7tlnrr�N//�l/lrlr�rlllW�'�a/llgl��Gi/P/;��10�1!!!!/lx�U/� i�,;;e�r��a rxiiiari,,, -> �Ir�'R �NWiNYdtfllk'A!9YW.Mk:W1pf�ll�p„Vf&d7/ tRIX�I%"M'J047�'� ..G/lG1011l/////iP IIVZgp,//,fV,�RO/ Yll//l '� wiYdiLu' 346-12 Pay Reduction for Plastic Properties A rejected load in accordance with 346-6.4 is defined as the entire quantity of concrete contained within a single ready mix truck or other single delivery vehicle regardless of what percentage of the load was placed. If concrete fails a plastic properties test and is thereby a rejected load but its placement continues after completion of a plastic properties test having a failing result,payment for the concrete will be reduced. The pay reduction for cast-in-place concrete will be twice the certified invoice price per cubic yard of the quantity of concrete in the rejected load. The pay reduction for placing a rejected load of concrete into a precast product will be applied to that percentage of the precast product that is composed of the concrete in the rejected load. The percentage will be converted to a reduction factor which is a numerical value greater than zero but not greater than one. The precast product payment reduction will be twice the Contractor's billed price from the Producer for the precast product multiplied by the reduction factor. If the Engineer authorizes placement of the concrete,even though plastic properties require rejection, there will be no pay reduction based on plastic properties failures; however, any other pay reductions will apply. 6 � F I I �ITAU Y sf I � tp j Q „, ..r..,...r.�..m .wrw.w.......... j a w ¢ Fd so III ro kg -- ' 8 58 m t y. Ji w m N J m W ` CD C CI f �'1 IF .I C R m U IN p � «M a m` avr ymgi a mC mu � E _dILL 0 1A Ifw �FF ui 6 D N o kim u a w oc U rY m crT h^. ., f wn N t ..w, _ .w� .... .....�,...,., !If q!j i,e II _' _