1st Change Order 02/28/2020 ONROE COUNTY/ENG EE G/ PRojEcr MANAc.EmENT
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: #1
Tiny House Construction &Demonstration INITIATION DATE: 02/11/2020
Key Largo Location
CONTRACT DATE:07/17/2019
TO CONTRACTOR:
Cornerstone Design Build, Inc.
d/b/a Cornerstone Tiny Homes
1687 Timocuan Way, Suite 101
Longwood, Florida 32750
I
The Contract is changed as follows:
The original(Contract Sum)(Guaranteed Maximum Price) ...........................................$ 101,197.00
Net change by previously authorized Change Orders...........................................---..$ 0.00
The(Contract Sure) (Guaranteed Maximum Price)prior to this Change order was . ..........$ 101,197.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)by this
Change Order.............$ 4,025.88
The new(Contract Sum)(Guaranteed Maximum Price) including this Change Order is......$ 105,222.88
The Contract Time will be(increased) (decreased)(unchanged)by................................. 0 Days
The date of Substantial Completion as of the date of this Change Order is........................05/01/2020
Detailed description of change order and justification:
4 ' sf�er/ s��kab�a, disl� sh r and is osa!were n+�l art c� the sari rtai IMF'and harts been
ro crested to,be included by the County. The shippLng,qhame has inccre sed since_a year a o when the
pr o/ect was bid.
he ge order is 4%of original contr ctpric
Not valid until sinned bv Owner.Architect if applicable).and Contractor
ARCHITECT: NIA to this change order
Date
CONTRACTOR: h /'Z
Aor4ne Design B Date
DIRECTOR PROJECT MANAGEMENT
Director Date
Project,Management
COUNTY/ASSISTANT ADMINISTRATOR: _ " 28 FEB 2020
Roman Gastesi Date
Kevin Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes ® No ❑
i
If Yes, explanation:
Washerldryer stackable, dishwasher, and disposal where not part of the original RFP and has been
requested to be included by the county. The shipping charge has increased since a year ago when
project was bid.
• Change Order was included in the original specifications. Yes❑ No
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes ❑ No
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes ❑ No
If No, explanation of why: This change does not involve structural changes,
Change Order is correcting an error or omission in design document. Yes❑ No
Should a claim under the applicable professional liability policy be made. Yes ❑ No
If Yes, Explain:
oic-ornerstone
Tiny Homes Change Order
1687 TJmocurrn Way,Suite 101,Longwood,F132750 Project Monroe County Key Largo
W7)413-,9660 CBC1255395 Tiny Home Jenny Lane
Date 2/10/2020
Change Order
i
THE CONTRACT IS CHANGED AS FOLLOWS:
Description of Change
LL
et
1 Add Stacking thrasher dryer unit Whirlpool Model WET4024HW
2 Add 1/2 HP Garbage Disposal Moen Model GXP50C $ .00
$200.00
3 Add 24"Dishwasher GE Model GDT605PGMWW 200
4 Change in Delivery Costs since Contract Bid August 2019 $652,00
$1,661.88
Original Contract Sum
The Net Change By Previously Authorized Change Orders $101,197 00
The Contract Sum Prior to this Change Order Was
The Contract Sum Will be Increased/Decreased by this Change Order $10 ,02 00
$4(l
The New Contract Sum Including this Change Order Will Be 5 i38
$105,222.88
Price above does not include tax
The Contract Time Will Increase by 0 Days
Y
NOT VALID UNTIL SIGNED BY CORNERSTONE TINY HOMES AND MONROE COUNTY, FLORIDA
ACONERSTONE TINY HOMES MONROE COUNTY, FLORIDA
BY(Signature) BY(Signature)
KIMBERLYJ HILTBRAND
Date PRINTED NAME
Date