Item E5 Cudj oe Status
March 2015
(Snapshot at March 17,2015)
Finance Status
(Since AUG 2012)
FKAA
Advances to date $106.5 million
Expenditures to date
-Fully processed against advances $ 93...9 million
-"in process" w/in County & FKAA $ 4.3 million
Subtotal Expenditures $ 98.2 million
Advance Balance on hand $ 8.3 million
w n
CURRENT STATUS REPORT FOR CUDJOE REGIONAL WASTEWATER PROGRAM
(As of February 20,2015)
1. Inner Islands' Collection Giannetti continues installing sewer lines on Cudjoe and
System Summerland Keys. Line work complete on Upper Sugarloaf
Key. Transmission work on US1 continues. Asphalt restoration
including full road overlay and leveling course being applied
on Cudjoe and Upper Sugarloaf Keys.
Action: Complete Cudjoe Key work for interim substantial
completion. Continue transmission system,pump stations
and pavement restoration.
2. Advanced Wastewater Wharton-Smith anticipates startup of AWTF in March 2015 for
Treatment Facility testing and preparation to receive flow.Tracer testing to be
conducted by FIU staff prior to plant operation.
Action: Complete electrical and instrument controls.
Complete programming for system operations.Preparing
for system testing and start-up.
3. Outer Islands' Collection Layne complete with collection system piping on Lower
System Sugarloaf. Other collection system work on Little Torch,
Ramrod and Big Pine Keys continues.
Action: Continue transmission work along US1, collection
system completions on Little Torch, Ramrod and Big Pine
Keys.Asphalt overlay on Lower Sugarloaf
4. Public Information FKAA has sent letters to Big Pine Key for hook-up information
and to provide project status and easement requests. Updates
to Cudjoewastewater.com website ongoing.
Action:Continue with public outreach, website updates and
field meetings.Letters for grinder station easements sent to
commercial properties approved by Monroe County.
5. On-Site Systems FDOH permitting underway for systems to be built on Big
Torch and Big Pine Keys. Evaluation of LPS in certain areas to
consider more central sewer connections
Action:Improve permitting efforts to obtain smaller
footprint systems. Initiate work with FWS to build EPA/DOH
innovative system on federal property on Big Pine Key.