1st Change Order 11/07/2017 NROE COUNTY/ EKING/ PROJECT MANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE:
Key West Library HVAC INITIATION DATE: 1 011 7/201 7
CHANGE ORDER NO: 1
TO CONTRACTOR:
T.E.M. Environmental &Mechanical Services, Corp CONTRACT DATE: 06/21/2017
The Contract is changed as follows:
The original (Contract Sum)(Guaranteed Maximum Price)............................................$267,500.00
Net change by previously authorized Change Orders..............................................--$0
The(Contract Sum)(Guaranteed Maximum Price) prior to this Change order was.............$267,500.00
The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased)
(Unchanged)by this Change Order..,,...$0
The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is—....$267,500.00
The Contract Time will be(increased)(decreased) (unchanged) by.................................. 59 Days
The date of Substantial Completion as of the date of this Change Order is........................ 01/05/2018
Detailed description of change order and justification: Increase Substantial Completion Date from
November 6th to Jan 5 2018 due to Hurricane IRMA
Not valid until signed b Owner Architect Lif a licable- and Contractor
ENGINEER:
f e
CONTRACTOR:
r' a e
DIRECTOR PROJECT MANAGEMENT ,If
NaZl'e
COUNTY/ASSISTANT ADMINISTRATOR: _ �,
rewn
an astesi Date
Wilson
Christine Hurley
Change Order Attachment per Ordinance No. 004-1999
Change Order was not included in the original contract specifications. Yes X No ❑
If Yes, explanation: Hurricane IRMA
• Change Order was included in the original specifications. Yes ❑ No X
If Yes, explanation of increase in price:
• Change Order exceeds $50,000 or 5% of contract price(whichever is greater). Yes ❑ No X
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes X No ❑
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes ❑ No X
Should'a claim under the applicable professional liability policy be made? Yes ❑ No X
Explain:
Environmental &
T.E.M.
Mechamical Services, Corp.
11/3/2017
Key West Library
HVAC Systems Upgrades
Re: Request for a No Cost Time Extention due to Hurricane Irma
We request a 59 day time extension be added to the contract schedule due to delays
associated with Hurricane Irma. This should extend our completion date to January 5,
2018.
lfy�u have anyl, uestions please do not hesitate to contact us.