2nd Change Order 01/31/2018 ONROE COUNTY/ENGINEERING/ PROJECT MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: Key West Library HVAC INITIATION DATE: 01/22/2017 CHANGE ORDER NO: 2 TO CONTRACTOR: T.E.M. Environmental &Mechanical Services,Corp CONTRACT DATE: 06/21/2017 The Contract is changed as follows: The original(Contract Sum)(Guaranteed Maximum Price)............................................$267,500.00 Net change by previously authorized Change Orders...................................................$0 The(Contract Sum)(Guaranteed Maximum Price)prior to this Change order was.............$267,500.00 The(Contract Sum)(Guaranteed Maximum Price)will be(increased)(decreased) (Unchanged)by this Change Order.......$0 The new(Contract Sum)(Guaranteed Maximum Price) including this Change Order is.......$267,500.00 The Contract Time will be(increased)(decreased)(unchanged)by..................................42 Days The date of Substantial Completion as of the date of this Change Order is........................ 02/16/2018 Detailed description of change order and justification: Increase Substantial Completion Date front .man 2018 due to materials delays for a ui ment TEM needs to extend to 2/16/2018 i Not valid until signed by Owner Architect if applicable),and Contractor ENGINEER: Date CONTRACTOR: , ,!�° , • 7r Date DIRECTOR PROJECT MANAGEMENT //, llel� Date' COUNTY/ASSISTANT ADMINISTRATOR: " `)z oma Gastesi Date Kevin Wilson Christine Hurley Change Order Attachment per Ordinance No. 004-1999 Change Order was not included in the original contract specifications. Yes X No❑ If Yes, explanation: Delays of equipment&materials Change Order was included in the original specifications. Yes ❑ No X If Yes, explanation of increase in price: • Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes❑ No X If Yes,explanation as to why it Is not subject for a calling for bids: e Project architect approves the change order. Yes X No❑ If no, explanation of why: e Change Order is correcting an error or omission in design document. Yes ❑ No X Should a claim under the applicable professional liability policy be made? Yes ❑ No X Explain: Services,T.E.M. Environmental & Mechanical 1/5/2018 Key West Library AC Systems Upgrades Re:Request for a No Cost Time Extension due to Hurricane Irma Delays in equipment material deliveries We request a 59 day time extension be added to the contract schedule due to delays of equipment &material deliveries due to Hurricane Irma. This should extend our completion date to March 5, 2015. If %, v questions please do not hesitate to contact us. j" I r.,ttt lite Vice President 3210 Flagler Avenue Ivey West, F1,3:3040 "Tel:305-414-8290 :y':�� w 9[=�r���at�tr�t3�,Y�'4'}t i•rr��'l temenvironmental@yahoo.com