1st Change Order 06/29/2015 MONROE COUNTY ENGINEERING
CONFRACr CHANGE ORDER
PROJECT TITLE: US1 Bayside Trail Project
CHANGE ORDER NO: 1
INITIATION DATE: 6/19/15
TO CONTRACTOR: Construct Group Corp. CONTRACT DATE: 7116/14
The Contract is changed as follows:
The original Contract Sum.....................................................................$2,176,320.01
Net change by previously authorized Change Orders..................................................$0
The Contract Sum prior to this Change Order was......................................$2,176,320.01
The Contract Sum will not be changed by this Change Order........................................$0
The new Contract Sum including this Change Order is.................................$2,176,320.01
The Contract Time (FDOT holiday specification)contract days will be increased .....12 Days
The Contract Time (MC contract article 4.7.8.2) contract days will be increased ....... 6 Days
The date of Substantial Completion as of the date of this Change Order is revised from
6/19/15 to 7/7/15.
Detailed description of Change Order:
FDOT specification 8-6.4 Suspension of Contractor's Operations — Holiday and Special Events, lists
specific holidays that the contractor shall not work and provides for contract time to be adjusted.
FDOT specification 8-7.3.2 provides for contract time extensions for weather.
In regard to the 18-day extension of time based upon the FDOT holiday shut down schedule and adverse
weather conditions that is the subject of this Change Order, Contractor agrees to accept the 18-day
extension of time without monetary compensation therefore as its sole and exclusive remedy for the delay
due to this time extension change, and Contractor hereby waives and releases any and all claims for any
additional compensation related to the 18-day extension of time that is the subject of this Change Order.
Stantec(CEI)concurrence letter attached.
r
CONTRACTOR:
Cos roue Corp. Date,
ENGINEERING SERVICES DIRECTOR: 4, 4 9�;�
i
dith S. Clarke, P.E. Date
COUNTY ADMINISTRATOR:
Roman Gastesi, Jr. Date
Stantec Consulting Services Inc.
fi1113 I'll
r,
3200 Bailey Lane Suite 200,Naples FL 34105-8523
June 11, 2015
File: 215612273
Attention:Ms. Debbie London
Monroe County - Murray Nelson Bldg.
1.02050 Overseas Hwy, Suite 229
Key Largo, FL 33037
Dear Ms. Debbie London,
Reference: Time Extension Letter One (1) for US-1 Bayside Shared Use Path Project
In accordance with the FDOT (Florida Department of Transportation) specification
governing this project, an extension of eighteen (18) days shall be added to the
contract for holidays and weather, as outlined in the FDOT Standard
Specification Section 8-6.4, Suspension of Contractor's Operations - Holidays and
.8-7.3.2 Contract Time Extensions.
In summary, during the time period from October 1st, 2014 through June 14th
2015, the days outlined below meet the specifications for adding days to the
contract under their specific specification (ie Holiday or Weather).
Holidays:
December 24th 2014 to January 2 20105: 8 Days
Martin Luther King, Jr. Day 2015: 1 Day
Memorial Day 2015: 1 Day
July 4, And July 4th Observed 2015: 2 Days Total
Holiday days: 12
Weather Days (1 day per date) 10/24/14, 1/19/15, 2/18/15, 4/29/15, 4/30/15,
5/5/15
Total Weather days Days: 6
Total days to be added to the contract 18