HomeMy WebLinkAbout2nd Change Order 03/30/2020 MONROE COUNIUDEPARMENT OF AIRPORTS
CONTRACT CHANGE ORDER
PROJECT TITLE: CHANGE ORDER NO: 2
Former Hertz Building Demolition
Key West International Airport
INITIATION DATE: September 27, 2019
TO CONTRACTOR: CONTRACT DATE: September 18, 2019
Charley Toppino&Sons, Inc.
125 Toppino Industrial Drive
Key West, Florida 33040
The Contract is changed as follows
The original (Contract Sum) (Guaranteed Maximum Price) $56,900.00
Net change by previously authorized Change Orders S17,38576
The(Contract Sum) (Guaranteed Maximum Price) prior to this Change order was $74,285.76
The(Contract Sum) (Guaranteed Maximum Price)will be (decreased)
(unchanged)by this Change Order S -0-
The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is $74,286.76
The Contract Time will be(increased) (decreased) (unchanged) by 152 days
The date of Substantial Completion as of the date of this Change Order is March 26, 2020
Detailed description of change order and justification
This time only change order extends substantial completion by 162 days to allow contractor
additional time to form and pour edge around the demo site to fill voids and block cells in
accordance with Change Order No. 1.
This change Order is 0.00%of the original contract price
Not vaI!q natal Ajqplg
CONTRACTOR.
Chart d ppino& Sons, Inc to
of
DIRECTOR OF AIRPORTS
to
COUNTY/ASSISTANT ADMINISTRATOR
Date
'�NAIDE COUNTY A NEY ""'N,
/�AfPAOVE FORM
P - 0 CAW
ASS )
T rC4UJ
S&R UNTY ATTDRNEY
not 3/30/20