1st Change Order 04/14/2020 DocuSign Envelope ID: FE6D22E1-05813-41F5-B268-6CBAOD933E3F
MONROE CouNTYANGINEERING/ OMANAGEMENT
CONTRACT CHANGE ORDER
PROJECT TITLE: 1
Historic Courthouse Gutters INITIATION DA4/3/20
CONTRACTT 1/22/20
TO CONTRACTOR:
Roofing by Ruff, Inc.
1010 Kennedy Drive, Suite 201
Key West, Florida 33040
The Contract is changed as follows:
The original (Contract Sum) (Guaranteed Maximum Price) ........................................... 152,851.00
Net change by previously authorized Change Orders................................................... n/a
The(Contract Sum) (Guaranteed Maximum Price) prior to this Change order was ............ 152,851.00
The(Contract Sum) (Guaranteed Maximum Price)will be(increased)(decreased) (unchanged) by this
Change Order.............$ 6, 90.47
The new(Contract Sum) (Guaranteed Maximum Price) including this Change Order is .......$159,741.47
The Contract Time will be(increased) (decreased) (unchanged)by................................. 0 days
The date of Substantial Completion as of the date of this Change Order is........................ 3/26/20
Detailed description of change order and justification:
An allowance of 50'of damaged wood, underlying the Courthouse gutters was established in the original
contract documents. The Contractor encountered an additional 90'of damaged wood that needed to be
replaced(totaling 140'). Materials and labor documentation is attached.
Change order is 0.05 to of odg;gal contract orr'ce
Not valid until signed by Owner Architect Jif applicable),and Contractor
ARCHITECT:
Ben er Assor ` -s Architects ate
Docusigned by:
4/7/2020
I CONTRACTOR: 6'
- 7F783ADCC353S36..
I®vv.—u my .'U..' u.1c. Date
Digitally signed by Cary Knight
Cary Knight Date:2020.04.13 11:21:58
DIRECTOR PROJECT MANAGEMENT -O'Vou
Cary Knight, Director Date
Project Management
Digitally z g-d by Kevin G.Will-PE.
' r � DN.—Ke-G.WI PE. �Aonroe Counry FL(tbe Ff-da
COUNTY/ASSISTANT ADMINISTRATOR:
� - wil k °n,��°°�fl.g°°`-°s
Roman Gastesi Date
Kevin Wilson
Christine Hurley
DocuSign Envelope ID: FE6D22E1-05813-41 F5-B268-6CBAOD933E3F
Change Order Attachment per Ordinance No. 004-1999
• Change Order was not included in the original contract specifications. Yes Z No❑
If Yes, explanation: It was assumed that there would be an estimated 50' of damaged facia and
underlying wood to the box gutters that would need to be replaced. Upon commencement of work
and demolition, the Contractor found 90' of additional damage (beyond the 50' allowance) for a total
of 140' of wood needing to be replaced.
• Change Order was included in the original specifications. Yes❑ No Z
If Yes, explanation of increase in price:
• Change Order exceeds$50,000 or 5%of contract price(whichever is greater). Yes❑ No Z
If Yes, explanation as to why it is not subject for a calling for bids:
• Project architect approves the change order. Yes Z No El
If no, explanation of why:
• Change Order is correcting an error or omission in design document. Yes❑ o Z
Should a claim under the applicable professional liability policy be made? Yes ❑ No Z
Explain:
Wood Repairs
Materials Qtv Unit UaLj Extended $
1x4x12' 4.0 ea $6.57 $26.28
1 x8x8' 16.0 ea $7.98 $127.68
2x4x10' 1.0 ea $5.98 $5.98
2x4x4' 2.0 ea $3.37 $6.74
Fasteners 1.0 lot $12.00 $12.00
Subtotal Materials $178.68
Discount for 50' included ($44.67)
Tax 7.50% $10.05
Total Materials $144.06
Labor #of Men Hrs Rate Cost
Replace/repair deteriorated wood 3.0 32.0 $85.00 $8,160.00
Labor credit for replacement included in bid 3.0 (8.0) $85.00 ($2,040.00)
Labor Total $6,120.00
Equipment Days Rate Cost
Total Equipment $0.00
Subcontractor
Subtotal $6,264.06
Sub Mark up @ 8 % $0.00
Mark up @ 10 % $626.41
Total $6,890.47
Time Extension