01st Change Order 04/22/2020 MONROE E / PROJECT MANAGEMENT
CHANGECONTRACT
PROJECT TITLE:. CHANGE ORDER NO: 001
Plantation Key Courthouse& Detention Center INITIATION DATE: March 24, 2020
COMMENCEMENT DATE August 5, 2019
CONSTRUCTION DAYS 913
TO CONTRACTOR APPROVED DELAY DAYS: 0
Biltmore Construction Company
1055 Ponce De Leon Blvd
Belleair, FL 33756
The original (Contract Sure)(Guaranteed Maximum Price) 32,818,441.14
Net change by previously authorized by Amendments 202,086.00
Net change by previously authorized Change Orders $ -
The (Contract Sum)(Guaranteed Maximum Price) prior to this Change order was $ 33,020,527.14
The(Contract Sum)(Guaranteed Maximum Price)will be (increased)(decreased) (unchanged)
by this Change Order b� $ (684,007.00)
The new(Contract Sum) (Guaranteed Maximum Price)including this Change Order is $32,336,520.14
The Contract Time will be(increased)(decreased)(unchanged) by 0 Days
The date of Substantial Completion as of the date of this Change Order is February 3, 2022
Detailed description of change order and justification:
Monroe County wishes to purchase the Generators directly from the supplier to take advantage of the County's
tax free status.The GMP will be reduced and the funds will then be used to procure the same materials via a
purchase order from OMB (attached).
This Change Order is: -2.08% of the original contract price
Not valid until signed by Owner Architect(if applicable) and Contractor
ARCH ITECTPDESIGNER: T A, !� 4/15/2020
Date
CONTRACTOR. .�..uw-.
Da
Digitally signed by Cary
Ca 1 Knight ht Knight
Date:2020.04.17 12:14:38
DIRECTOR OF PROJECT MANAGEMENT: -04'00'
Date
Digitally signed by Kevin G.Wilson,P.E.
DN:cn Kevin G.Wilson,P.E.,o Monroe
r ,> County,Fl-(the Florida Keys,ou,eail=wilson-
.� •`. ,� m-
' kevin@monroecounty fl.gov,c US
COUNTY/ASSISTANT ADMINISTRATOR' Date:2020.04.22162 '
4:31-0400
Date
MONROE COUNTY PURCHASE ORDER NO. 00061937
BOARD OF COUNTY COMMISSIONERS
1100 Simonton Street, Suite 2-213 PAGE NO. 1
Key West, FL 33040
SALES TAX EXEMPT NO.:85-801 3825294C-7 PDF COPY ---°- °--`
V F-98570 PHONE: 954-868-0642-1 H FMONROE COUNTY ENGINEERING DEPT
E STEWART & STEVENSON FDDA LLC 1 11.00 SIMONTON ST 2ND FL ROOM 2-215
N D/B/A FL DETROIT DIESEL-ALLISON
D P KEY WEST, FL 33040
4141 SW 30TH AVE
FORT LAUDERDALE FL 3 3 312 O ATTN: OLYMPIA NEWTON
ORDER DATE:02/14/2 0 BUYER:B ERICKSON REQ.NO.: 00056514 REQ.DATE:
TERMS: NET 3 0 DAYS F.O.B.: DESC.:
ITEM01 QUANTITY UOM I DESCRIPTION UNIT PRICE EXTENSION
01 1.00 LOT OWNER DIRECT PURCHASE 684007.0000 684,007.0
GENERATOR PACKAGE FOR THE NEW PLANTATION
KEY COURTHOUSE AND DENTENTION CENTER (2
GENERATORS)
SHIP TO ADDRESS:
88770 OVERSEAS HWY
TAVERNIER,FL 33070
ITEM# COST CENTER ACCOUNT PROJECT PROJECTACCT AMOUNT PAGE TOTAL $ 684, 007.00
01 26008 560620 CP1503 530340 684,007.00 TOTAL $ 684, 007.00
PARTIAL PAYMENT
FINAL PAYMENT
INVOICE NO. INVOICE AMOUNT
PAYMENT DESC.
PAYMENT APPROVAL PURCHASING AGENT
sr� y
a CHANGE ORDER LEDGER
PLANTATION KEY COURTHOUSE & DETENTION CENTER
01 ODP Generators $ (684,007.00)